RFQ Toolbox Nicky Byer, Applications Engineer

Similar presentations


Presentation on theme: "RFQ Toolbox Nicky Byer, Applications Engineer"— Presentation transcript:

1 RFQ Toolbox Nicky Byer, Applications Engineer nicky.byer@munters.com
Dan McClung, Applications Engineer September 29, 2012

2 Heat Recovery: Knowing what to ask
Hot side inlet temperature (operating/design) Cold side inlet temperature Required performance: effectiveness, cold outlet, or hot outlet Pressure drop requirements Gas composition / humidity ratio Max differential pressure Specific material requirements Size limitations / flow arrangement Corrosives (chlorine, sulfur, etc.) Particulates Condensables Accessories (access doors, water wash, sonic horn, etc.) Payback information ($/MMBTU and $/kWh) RFQ Toolbox September 29, 2012

3 Filling Out the Heat Exchanger Questionnaire
Request for Quotation Filling Out the Heat Exchanger Questionnaire RFQ Toolbox September 29, 2012

4 RFQ Toolbox September 29, 2012

5 RFQ Toolbox September 29, 2012

6 Cost of heat exchanger X2
RFQ Toolbox September 29, 2012

7 Major Factors that affect Heat Exchanger Unit Cost
Airstream Properties Temperature Corrosives, Particulates, etc. Max pressure differential Effectiveness Size Limitations Allowable Pressure Drop (DP) –CRITICAL RFQ Toolbox September 29, 2012

8 Pressure Drop Example Customer wants to use the exhaust stream from a 10,000 SCFM incinerator with outlet temperature of 1000°F to preheat a makeup airstream at 70°F. Heat Exchanger Specification: 304 SS Construction, UI flow pattern, 70% Effective, Fully Insulated unit with Expansion Joints If unit has 1.5” W.C. DP per side, Total 3” W.C. DP then: Unit Cost = $92,255 NET If unit has 3” W.C. DP per side, Total 6” W.C. DP then: Unit Cost = $74,191 NET Additional Unit Cost for Lower DP = $18,064 (~20%) RFQ Toolbox September 29, 2012

9 RULES OF THUMB Converting ACFM and SCFM SCFM=ACFM * [530/(460+T)]
ACFM=SCFM * [(460+T)/530] RFQ Toolbox September 29, 2012

10 RULES OF THUMB Converting #/Hr to SCFM (#/Hr.) / 4.5 = SCFM
* 4.5 = (Density of Standard Air, #/Cubic Foot) * 60 Min./Hr. RFQ Toolbox September 29, 2012

11 RULES OF THUMB Converting Temperature
Celsius to Fahrenheit °F= 1.8 X °C + 32 Fahrenheit to Celsius °C= (°F - 32)/ 1.8 RFQ Toolbox September 18, 2018

12 RULES OF THUMB Converting Pressure psig to psia Psig + 14.7
psia to psig Psig – 14.7 psig to inches of H Psig X 27.7 inches of H20 to psig inches of H20/ 27.7 RFQ Toolbox September 18, 2018

13 RULES OF THUMB tho tci thi tco RFQ Toolbox September 18, 2018

14 RULES OF THUMB Stacks Measure free flow area
Measure velocity with flow meter Measure temperature with IR gun or TC Calculate BTU’s available RFQ Toolbox September 18, 2018

15 RULES OF THUMB Energy Available in Exhaust
BTU/Hr = Mass Flow * Cp * DT or BTU/Hr = 1.08 *SCFM* DT DT = Desired Exhaust Temperature change Mass Flow = #/Hr Cp = Average Specific Heat SCFM = Standard Cubic Feet per Minute RFQ Toolbox September 18, 2018

16 RULES OF THUMB Stacks Rule of thumb is 1000 FPM minimum velocity
Higher velocities are often seen on stacks with fumes for dilution such as from exhaust hoods or oxidizers Max is typically in the FPM range RFQ Toolbox September 18, 2018

17 Prices this year are the lowest they have been in the past 10 years.
RULES OF THUMB Natural Gas Prices Good Internet Source: Prices this year are the lowest they have been in the past 10 years. RFQ Toolbox September 18, 2018

18 Fuel costs are currently approximately $5.00/MMBTU
RULES OF THUMB 1 Therm = 100,000 BTU's. $5/MMBTU’s = $0.50/Therm Fuel costs are currently approximately $5.00/MMBTU RFQ Toolbox September 18, 2018

19 Equipment Cost / Yearly Savings = Simple Payback
RULES OF THUMB Simple Payback Yearly Savings = MMBTU/hr Saved * Yearly hours of Op * Cost of Fuel ($/MMBTU) Equipment Cost / Yearly Savings = Simple Payback RFQ Toolbox September 18, 2018

20 Stoichiometric Combustion Process
RULES OF THUMB Stoichiometric Combustion Process This relates to the ratio of natural gas to air for a combustion process. Standard is 10 parts air to 1 part gas assuming the system DOES NOT run with excess air. RFQ Toolbox September 18, 2018

21 Stoichiometric Combustion Process
RULES OF THUMB Stoichiometric Combustion Process If you have an exhaust from a gas fired oven and you know the gas usage then you can estimate the stack flow rate for quick energy savings calculations. This only works for 10:1 air to gas ratios. You will have to adjust if it is running with excess air. RFQ Toolbox September 18, 2018

22 Stoichiometric Combustion Process
RULES OF THUMB Stoichiometric Combustion Process If oven gas usage is 3 MM BTU’s /Hr then this equates to 3000 Ft3/hr of natural standard conditions (1000 BTU/Ft3 for Natural Gas). Since we are assuming 10:1 air to gas then we know that the combustion air flow will be 30,000 Ft3/hr. RFQ Toolbox September 18, 2018

23 Stoichiometric Combustion Process
RULES OF THUMB Stoichiometric Combustion Process This gives a total of 33,000 Ft3/hr (SCFH). Convert to SCFM = SCFH/60 Stack Flow = 33,000/60 = 550 SCFM RFQ Toolbox September 18, 2018

24 Questions? 24

25 Thank you! 25