1
Recent Plastic Fusion Orders
Con Edison Case Study: Recent Plastic Fusion Orders Lauren Toczylowski Section Manager, Gas Quality Assurance
2
Agenda Con Edison Distribution Overview
Plastic Fusion Remediation Plan New NY State requirements Tracking & Traceability approach Ongoing Fusion Inspections Required Enhancements Other Plastic Joint Enhancements Ongoing Tracking & Traceability Projects
3
Con Edison Distribution Overview
Distributes natural gas to 1.1 million customers in Manhattan, the Bronx, Queens, and Westchester County ~ 4,300 miles of gas mains and ~384,000 services transport about 225 billion cubic feet a year Most of our customers use gas for cooking and ~221,000 also use gas for residential heating
4
Con Edison Distribution Overview
5
Organizational Structure
Gas Operations Compliance & Quality Assessment Training & Employee Development Quality Assurance Quality Control
6
Fusion Compliance Requirements History
September 29, 2014: Con Edison, and other NY LDCs required to submit a remediation plan October 31, 2014: Con Edison, and other NY LDCs, submitted plans to be completed within one year November 17, 2014: Con Edison’s original plan deployed, to be complete by November 1, 2015 December 2014 – May 2015: Discussion with DPS Staff re: plan May 15, 2015: PSC Orders Con Edison to submit revised plan. Also orders NY LCDs to: Peer check 100% of all new fuses being installed Visually inspect all fuses exposed during the course of normal business August 2015: Excavations under new plan begin
7
Plastic Fusion Remediation Plan
8
Overview of Plastic Fusion Sampling Plan
Population: ~805,000 fuses installed in Conduct statistical approach to identify samples to be inspected Fuses/fusers were not previously documented, but segments were mapped A sub-set of pipe segments were randomly selected Fuses were then mapped and labeled for each segment selected Statistician’s analysis includes strata for each type of segment (main or service), geographic areas (Bronx, Queens, Manhattan, Westchester), and each type of fuse (butt fuse, electrofusion and sidewall tee) 200 fuses will be inspected to determine whether additional sampling is needed to develop a remediation plan
9
Inspection Form: Visual Inspection & Destructive Test
10
Field Documentation Piping Retrieval Information Form
Tag sample to indicate: Location (house address & borough) Size of pipe Date removed Supervisor name Piping Retrieval Information Form Filled out for each sample length
11
Inspection/Testing Photos & Videos
12
Manual Data Conversion for PSC Reporting
13
Multiple Documents & Files for One Fuse
Hand written forms Pipe tags Visual Inspection Results Data Destructive Test Results Data Multiple Photos Video file Spreadsheet entries Letters to PSC
15
Solution: Integrated Mobile Data Capture
Application deployed on ruggedized smart phones and tablet computers Real-time data transfer from field to office to field Centralized repository with robust reporting capability Cloud computing/ hosted options
16
In The Field
17
Automated PSC Reporting
18
New Fuse Peer Inspection & Exposed Fuses Visual Inspections
NY State May 15th Order
19
Con Ed Preparation for Additional Inspections
Needed to train and qualify additional employees/contractors to perform visual inspections Developed and deployed additional training Used a Written Evaluation (equivalent to NGA CT#52) developed by Con Edison Qualified additional employees and contractors to perform visual inspections of plastic joints Note: at the time, a separate NGA CT 52 online knowledge test was not available (in NGA’s OQ site: ITS) This process is documented in ConEd’s OQ Plan- under Appendix D Hand Out of Training Packet
20
Field Documentation Identifying PE Plastic Joiner and Inspector
Plastic joints are identified on as-constructed drawings Fuser and Peer Inspector are signing the pipe Each plastic joint is documented Data captured: Job information (M&S plate #, Ticket/Leak #, Location , Layout #) Plastic Joiner employee/ID # Peer Inspector employee/ID # Date Plastic Joint made Joint Type ( Butt Fusion, Electrofusion, Mechanical Joint)
21
Peer Check of All New Fuses
Con Ed began on June 1 with Peer Check of 100% of all new fuses going in the ground May 15th Order (all LDCs in the state): required starting Oct. 1st Additional- Level 1 and Level 2 requirements were added for Con Edison (level 1: 15%, level 2 5%)
22
Fuse-to-Fuser Application
Full Deployment by Jan. 1st, Inquest
23
Fuse-to-Fuser Application
24
Other Plastic Joining Enhancements
25
Ongoing Enhancements in Plastic Joining
Annual OQ: block requalification with 3rd party evaluators Online OQ system: eLearning, online testing and QR codes Level 1/Level 2 inspections of new fuses Remediation Options for visually unacceptable fuses Elimination of the Sidewinder Enhanced QA/QC Programs NTSB Recommendations for Specification Improvements R&D Projects: Heat Fusion Processes GPS Devices
26
Butt Fusion Remediation Sleeve
4” and 6” right now, but working with R&D on other sizes
27
PE Repair Patch
28
Additional QC: Fusion Inspections
Created a separate GQC group Hired a 3rd party inspection contractor Fusion inspectors in the field, making process observations Field visits where ongoing fusions are taking place All GQC inspectors are fusion qualified Level 1/ Level 2 Fusion Inspections
29
Analyzing Inspection Results
Large amount of data around fusion inspections and quality Analyzing and reporting on results Common issues identified and addressed: Damaged Butt Fusion Plates (replacement program) Alignment of Electrofusion (new tools identified) Scraping of Pipe Surface (1” past fusion area)
30
Tracking & Traceability R&D
IT Roadmap Project: analyzing GIS and WMS solutions Trimble R&D Project: Handheld Trimble and smart device connections Testing in areas with Urban Canyons and Tree Canopy issues Comparing usability with other smart device applications
31
Thank You Any Questions?