Download presentation
Presentation is loading. Please wait.
1
Chapter 16 Materials Requirements Planning
Material Requirements Planning (MRP) MRP Logic and Product Structure Trees Time Fences MRP Example MRP II Lot Sizing in MRP Programs 2 2
2
Material Requirements Planning Defined
Materials requirements planning (MRP) the logic for determining the number of parts, components, and materials needed to produce a product. MRP provides time scheduling information specifying when each of the materials, parts, and components should be ordered or produced. 3 3
3
Bill-of-Material List of components & quantities needed to make product Provides product structure (tree) Parents: Children: Shows low-level coding
4
Bill-of-Material Product Structure Tree
5
Product Structure Thinking Challenge
The demand for product A is 50. How many of each component is needed to satisfy demand?
6
Lead Times & Product Structure
Handle Bars 2 wk. Lead time 1 wk. Frame 2 wk. Bicycle 1 wk. 3 wk. Frame Assy Wheels Time (weeks)
7
Additional MRP Scheduling Terminology
Gross Requirements On-hand Net requirements Planned order receipt Planned order release 19 19
8
MRP Formulas Beginning On-hand = Physical On-hand - Safety stock - Allocated On-hand is Allocated is Next Period On-hand = Prior period's on-hand + Scheduled receipts Net requirement =
9
Simple Example of MRP Logic and Product Structure Tree
Given the product structure tree for “A” and the lead time and demand information below, provide a materials requirements plan that defines the number of units of each component and when they will be needed. Lead Times A 1 day B 2 days C 1 day D 3 days E 4 days F 1 day Product Structure Tree for Assembly A B(4) E(1) D(2) C(2) F(2) D(3) A Demand Day A Day B (Spares) Day D (Spares) 4 4
10
First, the number of units of “A” are scheduled backwards to allow for their lead time. So, in the materials requirement plan below, we have to place an order for 50 units of “A” in the 9th week to receive them in the 10th week. LT = 1 day 5 5
11
Spares LT = 2 B(4) E(1) D(2) C(2) F(2) D(3) A 4x50=200
Next, we need to start scheduling the components that make up “A”. In the case of component “B” we need 4 B’s for each A. Since we need 50 A’s, that means 200 B’s. And again, we back the schedule up for the necessary 2 days of lead time. Spares LT = 2 B(4) E(1) D(2) C(2) F(2) D(3) A 4x50=200 6 6
12
Finally, repeating the process for all components, we have the final materials requirements plan:
13 B(4) E(1) D(2) C(2) F(2) D(3) A spares Part D: Day 6 The McGraw-Hill Companies, Inc., 2000 7 7
13
Master Production Schedule (MPS)
Time-phased plan specifying how many and when the firm plans to build each end item. Aggregate Plan (Product Groups) MPS (Specific End Items) 8 8
14
Types of Time Fences Frozen Moderately Firm Flexible 9 9
15
Forecast and available
Example of Time Fences 8 15 26 Weeks Frozen Moderately Firm Flexible Firm Customer Orders Forecast and available capacity Capacity 10 10
16
Firm orders from known customers Forecasts of demand from random
17 Firm orders from known customers Forecasts of demand from random Aggregate product plan Engineering design changes Bill of material file Inventory transactions record file Master production schedule (MPS) Material planning (MRP) Reports The McGraw-Hill Companies, Inc., 2000 12 12
17
Inventory Records File
Each inventory item carried as a separate file Status according to “time buckets”. Pegging Identify each parent item that created demand. 14 14
18
Primary MRP Reports Planned orders to be released at a future time.
Order release notices to execute the planned orders. Changes in due dates of open orders due to rescheduling. Cancellations or suspensions of open orders due to cancellation or suspension of orders on the master production schedule. Inventory status data. 15 15
19
MRP Example A(2) B(1) D(5) C(2) X C(3)
Requirements include 95 units (80 firm orders and 15 forecast) of X in week 10 plus the following spares: 18 18
20
21 21
21
Closed Loop MRP Yes Production Planning Master Production Scheduling
Material Requirements Planning Capacity Requirements Planning No Feedback Realistic? Feedback Execute: Capacity Plans Material Plans Yes 22 22
22
Manufacturing Resource Planning (MRP II)
Goal: Plan and monitor all resources of a manufacturing firm (closed loop): Simulate the manufacturing system 23 23
23
Lot Sizing in MRP Programs
Lot-for-lot (L4L) Economic order quantity (EOQ) Least total cost (LTC) Least unit cost (LUC) Fixed quantity - Minimums, multiples 23 23
24
MRP Management Issues System nervousness
Integration with Just-in-Time (JIT)
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.