Presentation is loading. Please wait.

Presentation is loading. Please wait.

Emily Pike Community Liaison Manager, SUEZ

Similar presentations


Presentation on theme: "Emily Pike Community Liaison Manager, SUEZ"— Presentation transcript:

1 Emily Pike Community Liaison Manager, SUEZ
Suffolk EfW Facility Emily Pike Community Liaison Manager, SUEZ Friday 24th February 2017

2 Programme Welcome - Introduction Presentation Site induction
Project Outline EfW Process Site induction Site visit Visitor Centre Control Room

3 Project Outline

4 Suffolk EfW Facility Project
Financing, Construction and Operation of a 269,000 tpa EfW Facility Treatment of the Residual Waste collected by Suffolk’s Councils 25 year PFI Contract with Suffolk County Council Partnership between Suffolk County Council and SUEZ Four phases: Procurement: Autumn 2008 – 5th October 2010 (Financial Close PFI) Planning: Spring 2010 – 8th August 2011 (Planning permission) Construction: 25th November 2011 – 1st December 2014 Operation: until 30th November 2039 (25 years) Potential extension up to 5 years

5 The benefits EfW provides a cheaper, greener solution to disposing of household and some business waste It puts the waste to good use as a fuel to generate enough electricity for 30,000 homes + potentially some heat Economic benefits – 45 permanent jobs plus around £1million spent in the local economy per annum Cost benefits: at least £350 million cheaper than continuing to landfill. Reduction in greenhouse gases – 75,000 tonnes a year

6 EfW in context: What is the cost of dealing with non-recyclable waste v’s recyclable waste
For councils in Suffolk, waste management costs are made of 2 elements. Collection costs Treatment costs Indicative costs based on last full year of data available 2014/15. Shown as approximate estimates to the councils in Suffolk. Direct collection and treatment costs only, excludes other associated costs such as admin, support staff and premises. Costs are shown per household per year. 20/09/ Page 6

7 Waste specification Suffolk energy-from-waste facility can only accept non-recyclable waste The waste has to have a certain calorific value - between 8910 kj/kg and 9800 kj/kg Electricals items are a serious problem as they can causes spikes in our emissions, which we can control but would rather not have in the first place 20/09/ Page 7

8 The Build - EPC Contractor: CNIM-Lagan
CNIM provided the Process Equipment Lagan provided the Civil Works CNIM is the leading manufacturer of EfW plants: incineration lines - 9 new plants being built in the UK currently

9 Main Project Features Site: Council’s former highways depot site in Great Blakenham The facility has 2 lines designed to process 15 tonnes per hour per line Landscaped wildlife area A visitor centre for community use An onsite ash processing facility

10 The site

11 Suffolk’s Energy-from-Waste visitor centre
2 rooms aimed at providing an overarching view of: Waste management Energy production and consumption Environment Energy from Waste process There has been a huge demand for visits - in 2015 we had 2,698 visitors.

12 The architecture Designed by Grimshaw architects
Achieved BREEAM Outstanding rated building, making it one of the greenest buildings in the country.

13 How does it work?

14 Process

15 From Waste to Bottom Ash

16 Moving Grate 20/09/ Page 16

17 Reverse acting grate 20/09/ Page 17

18 From Air to Flue Gases Flue Gas Treatment Furnace / Boiler
Reactor (Detail)

19 Cleaning process - bag filters
Bag filters collect the particles from the flue gas 20/09/ I

20 From Water to Steam, then to Electricity and Heat
Steam Turbine

21 Turbine 20/09/ Page 21

22 Energy from Waste Outputs
Cleaned flue gas Lime / Activated Carbon Urea Flue Gas Treatment Bag house filter Waste Combustion Boiler Incineration Bottom Ash 22-27% Turbine Generator Fly ash (APCR) 3-4% Electricity + Heat 23% to 50-60% efficiency

23 Questions? 20/09/ Page 23


Download ppt "Emily Pike Community Liaison Manager, SUEZ"

Similar presentations


Ads by Google