2
Project Overview Roundabout proposed at US 41 and Gulfstream Ave
Fruitville Rd Roundabout proposed at US 41 and Gulfstream Ave PD&E and design phases underway Identified in LRTP as a Multimodal Emphasis Project 1st St Project Location Cocoanut Ave Gulfstream Ave Main St
3
Proposed Roundabout Network in Sarasota
14th St 10th St Project Location Fruitville Rd Main St Gulfstream Ave Ringling Blvd Orange Ave
4
Purpose and Need City of Sarasota Downtown Masterplan (2001) and Connecting Downtown to the Bayfront Study (2010) recommended roundabouts to help eliminate the barrier of existing high-speed traffic on US 41 between Downtown and the Bayfront Roundabout proposed to slow traffic and create a more comfortable environment for pedestrians and bicyclists Roundabout designed to provide operational and traffic benefits to the intersection
5
Proposed Roundabout at US 41 and Gulfstream Ave
VUE CHASE MARINA ONE GULFSTREAM AVE BAYFRONT PARK N.T.S.
6
Pedestrian Hybrid Beacons Proposed at Crosswalks
7
Public Involvement Public meetings held: Interactive displays:
March 28, 2017 March 27, 2018 Interactive displays: Table top with toy cars Walkable roundabout floormat Pedestrian educational video Traffic simulations
8
Project Status/Schedule
PD&E phase - ongoing and expected to be completed by Summer 2018 Design phase - plans production ongoing and expected to be completed by Summer 2019 Construction phase – partially funded but expected to begin late 2019
9
Contact Information Walter Breuggeman, PE FDOT Project Manager (863) Michael Garau, PE Consultant Deputy Project Manager (407) Project Website:
10
Questions/Comments