2K CB FDR Conclusion: Project Summary, Procurement Plan / Status
Joe Matalevich LCLS-II 2 K Cold Box FDR March 28, 2018
2
Project Summary Implement redesign decision
Updated and comprehensive analyses performed Focused design effort to complete detailed design Procurement strategy developed to achieve earliest delivery Solicit early feedback: RFI JLab to procure multiple long lead items PRR & RFP prior to FDR LCLS-II 2 K CBX FDR, Mar 28, 2018
3
Procurement Plan - GFE Long lead items to be provided as Government Furnished Equipment (GFE) RFI information helped confirm that furnishing Top Plate Assembly will provide significant reduction in ultimate delivery date Cold Compressors Cryogenic Control Valves Female bayonets Flow meter venturis Top Plate Weldment Assembly LCLS-II 2 K CBX FDR, Mar 28, 2018
4
Procurement Plan LCLS-II 2 K CBX FDR, Mar 28, 2018
5
Procurement Plan LCLS-II 2 K CBX FDR, Mar 28, 2018
6
Procurement Plan – Current Status
Drawings Completed 28 Feb PRR Held Mar RFP released for Solicitation 7 Mar Vendor Questions Due 28 Mar Bids Due Apr Anticipated Award Early July Anticipated Delivery June 2019 Expectation is that remaining funds in 2K CB WBS is adequate for procuring 2 cold boxes LCLS-II 2 K CBX FDR, Mar 28, 2018
7
Thank you for your time today.
Conclusion Thank you for your time today. Questions? LCLS-II 2 K CBX FDR, Mar 28, 2018