1 MONTHLY STATUS REPORT– May 2013
Title Slide MONTHLY STATUS REPORT– May 2013 LOS ALAMITOS UNIFIED SCHOOL DISTRICT Los Alamitos High School Track Modernization Project May 21, Los Alamitos, California

2 ACTIVITY SUMMARY ON TIME AND ON BUDGET General Site Conditions
Executive Summary ACTIVITY SUMMARY General Site Conditions Mobilization of Site Complete Initial Surveying Complete Storm-water Pollution Prevention Plan Implemented Demolition Complete Soil Extraction Complete Grading and Compaction 90% Complete Concrete Retaining Curb at Parking Lot 95% Complete ON TIME AND ON BUDGET

3 ACTIVITY SUMMARY Track – Start of Construction
Progress 21 ACTIVITY SUMMARY Track – Start of Construction Track – After First Day of Construction Track Prior to Construction

4 ACTIVITY SUMMARY Demolition Complete Dust Mitigation
Progress 21 ACTIVITY SUMMARY Demolition Complete Dust Mitigation Typical Equipment on Project

5 ACTIVITY SUMMARY Storm-water Pollution Prevention On-Going
Progress 21 ACTIVITY SUMMARY Storm-water Pollution Prevention On-Going Hay Tubes at Perimeter of Site Crushed Rock at Entry – Dust Mitigation

6 ACTIVITY SUMMARY Site Leveling 90% Complete Laser Leveler on Blade
Progress 21 ACTIVITY SUMMARY Site Leveling 90% Complete Laser Leveler on Blade Laser Leveling Equipment

7 ACTIVITY SUMMARY Concrete Curb at Parking Lot 95% Complete
Progress 21 ACTIVITY SUMMARY Concrete Curb at Parking Lot 95% Complete Formwork for New Concrete Curb Curb at Parking Lot Saw-Cut

8 ACTIVITY SUMMARY Soil Excavation/Compaction 90% Complete
Progress 21 ACTIVITY SUMMARY Soil Excavation/Compaction 90% Complete Current “Track” Current “Track”

9 SCHEDULE General Site Conditions
Begin Electrical and Timing Conduit Installation Begin Main Drain Tie-In Begin Installation of Site Curbing Begin Installation of Trench Drains Begin Installation of Fence Posts

10 Questions QUESTIONS?

11 Thank you THANK YOU!