SgTPP Unit No.5 (1X660MW) & Mini Ash Pond BkTPP Unit No.6 (1X660MW)

Similar presentations


Presentation on theme: "SgTPP Unit No.5 (1X660MW) & Mini Ash Pond BkTPP Unit No.6 (1X660MW)"— Presentation transcript:

1 NEW PROJECTS AND R&M ACTIVITIES ENVISAGED FOR WBPDCL FOR COMMING 5 YEARS(2016-2020)
SgTPP Unit No.5 (1X660MW) & Mini Ash Pond BkTPP Unit No.6 (1X660MW) STPS Unit No. 7 (1X660MW) R&M PROJECTS: KTPS Unit No. 1,2 &3 BTPS Unit No. 1,2,3 & 4 INSTALLATION OF NEW WAGON TIPPLER KTPS, STPS & BkTPP RETROFITTING OF ALL POWER PLANTS DUE TO ENVIRONMENT NOTIFICATION-2015 22 September 2018

2 Sagardighi Thermal Power Project
22 September 2018

3 Sagardighi Thermal Power Project, Phase-II Extension Units 3 & 4 (2X500MW)
SALIENT FEATURES: Initial Approved Project Cost: Rs.5340Crs. Revised estimated project cost: Rs.6030Crs. Increase in Cost: Rs.690Crs.(Loan-Rs. 483Cr, Equity-Rs.207Cr) Project Cost incurred so far 3898Crs. Projects Start Date : Project completion Date: Unit No.3 Coal synchronization achieved on 16th Dec 2015 Unit No. 3 COD expected by End June, 2016 Followings are the future milestone for completion of unit no.4 Boiler light up: Feb 2016 Oil Synchronisation: April, 2016 Coal Synchronisation: June,2016 COD : Oct,2016 22 September 2018

4 SgTPP Unit No.5 (1X660MW) Approval : 1x500MW GoWB approval is available Land Available: 30Acres Additional land required: Not required, 30acres will accommodate BTG, NDCT and Chimney. Proposed Unit size: 1X660MW –Super critical unit, CEA only permitting super critical units in 13th plan. Estimated Project Cost: 3630Cr. Project financing: 70:30 70% loan from financial institution like PFC, SBI-Rs.2541Crs. 30% Govt. equity –Rs. 1089Crs. Level of readiness : DPR for one additional 500MW already available (DCPL-May 2013), DPR for 1X660MW under preparation. Completion period: 42 months from zero date 22 September 2018

5 CONSTRUCTION OF MINI ASH POND AT SGTPP
Land Available: 33 Acres Capacity: 10 lac MT( 10 months generated ash of unit no.1to 5) Estimated Cost: Rs. 75Crores Fund Availability: to be tied up Average ht of Ash Pond: 12Meters Project completion period: 18 Months Level of readiness: Design Basis Report available –M/s Astha (July, 2015) Ash Water recirculation system: Consultancy award by 22 September 2018

6 Bakreswar Thermal Power Project
22 September 2018

7 BkTPP Unit No.6 (1X660MW) Approval : To be obtained from GoWB
Land required: 90 acres Land Available: 90 acres Additional land: Not required Proposed Unit size: 1X660MW –Super critical unit, CEA only permitting super critical units in 13th plan. Estimated Project Cost: 3350Cr. Project financing: 70:30 70% loan from financial institution like PFC, SBI-Rs.2345Crs. 30% Govt. equity- Rs. 1005Crs. Level of readiness : DPR already available (Lahmeyer-March 2014) Completion period: 42 months from zero date 22 September 2018

8 INSTALLATION OF NEW WAGON TIPPLER AT BkTPS
Salient features : BkTPS is having one WT and two Track Hopper Single route for simultaneous unloading create route congestion Plant is suffering high detention time for unloading wagon and causing huge demurrage charge. No. of NBox wagon is increasing compare to BOBR wagons. Proposed augmentation at CHP: Rota side WT, Side arm charger, Crusher House and associated conveying system Capacity: 800TPH New WT can unload NBox wagon per hour DPR is under preparation Cost of WT, Side arm charger, Crusher house and conveyor System-Rs. 120Crs.(approx) Cost of Railway infrastructure: 18.5Crs. Total Cost of installation is Rs. 140Crs.(approx) Fund Availability: to be tied up 22 September 2018

9 Santhaldih Thermal Power Project
22 September 2018

10 STPS Unit No.7 (1X660MW) Approval : To be obtained from GoWB
Land Available: 230Acres( After dismantling of unit 1 to 4) Additional land: 100Acres for Ash Pond Proposed Unit size: 1X660MW –Super critical unit, CEA only permitting super critical units in 13th plan. Estimated Project Cost: 3350Cr. Project financing: 70:30 70% loan from financial institution like PFC, SBI-Rs.2345Crs. 30% Govt. equity-Rs.1005Crs. Level of readiness : DPR for two additional 800MW already available (Lahmeyer-April 2011), DPR for 1X660MW to be prepared. Completion period: 42 months from zero date 22 September 2018

11 INSTALLATION OF NEW WAGON TIPPLER AT STPS
Salient features : STPS is having only one Track Hopper There is no option for unloading Nbox wagon tippler. Railway is insisting to receive NBox wagon. Unloading time of BOBR wagon is higher due to over size coal and big stone, shales. Proposed augmentation at CHP: Rota side WT, Side arm charger, Crusher House and associated conveying system Capacity: 800TPH New WT can unload NBox wagon per hour Over size coal can be handled by this new WT. Cost only for WT and associated system: 108.7Crs. Cost of Railway infrastructure: 15Crs. Total Cost: 123.7Crs. Fund Availability: to be tied up 22 September 2018

12 Kolaghat Thermal Power Station
22 September 2018

13 Renovation and Modernisation of KTPS stage-I unit No.1,2&3
Why R&M of Stage-I: Unit 1, 2 &3 were commissioned between 1984 to 1990 Stage-I units were designed for SPM level 750mg/nm3 Now actual stack emission is to the tune of 1000 to 1500mg/Nm3 CPCB has been asking WBPDCL since 2011 to reduce emission level to the tune of 100mg/Nm3 WBPDCL has submitted a BG amounting 25Lakhs as guarantee for implementation of up gradation programme of ESP. Accordingly WBPDCL submitted an action plan for implementation of up gradation of ESP. Completion of up gradation of all the three units by March 2017. 22 September 2018

14 Renovation and Modernisation of KTPS stage-I unit No.1,2&3
Why R&M of Stage-I: Salient features of modified notification for environment protection Amendment rule-2015 Units installed before has to achieve the following – SPM level-100mg/Nm3, Sox Emission -600mg/Nm3 Nox emission- 600mg/Nm3 Stage-I units are installed with 5 mills capacity each 26MT/Hrs. Stage-I units are designed to fire coal of GCV to the range 3800 to 4400kCal/Kg Presently KTPS is firing coal to the range of 3400kCal/Kg Load is restricted to maximum 140MW per unit firing of all 5 mills. For getting full load with worse coal around 150MT/hrs coal firing is required. Therefore to mitigate the above mentioned point DPR for R&M of KTPS stage-I has been prepared by M/s Steag 22 September 2018

15 Renovation and Modernisation of KTPS stage-I unit No.1,2&3
Salient features of R&M of KTPS are : System to be upgraded Cost Rs. in Crs. ESP 260 Milling System along with Coal piping, Coal feeders, PA fan, ID fan and associated ducting 394 Ash Handling system 97 Total 751 Anticipated cost of installation of FGD and NOX control 300 1051 Execution period: 9 months per Unit Financial mode: Tie up for External Aid 22 September 2018

16 Renovation and Modernisation of KTPS stage-I unit No.1, 2 & 3
: Finance Dept. GoWB go ahead clearance given for R&M of three unit of KTPS : Kfw informed GoWB that they are supporting for financial assistance to WBPDCL through DEA for R&M works : Accordingly WBPDCL contracted kfw for sanctioning loan for executing the R&M works : In 146th Board meeting WBPDCL Board approved for R&M projects of KTPS : kfw sanctioned 80 Million Euro loan only for KTPS Unit No.3 R&M works : GoWB informed GoI that the decision to go for R&M of KTSPS is put on hold until the completion of R&M of BTPS unit no.5 22 September 2018

17 INSTALLATION OF NEW WAGON TIPPLER AT KTPS
Salient features : KTPS is having two WT and one Track Hopper WTs are 30 years old and can unload only 8-10 wagons per hour. Plant is suffering high detention time for unloading Nbox wagon and causing huge demurrage charge. Yearly demurrage charge is Rs Crs.(( ) Charge paid due to manual unloading is Rs. 5.8Crs.( ) Proposed augmentation at CHP: Rota side WT, Side arm charger, Crusher House, associated conveying system Capacity: 800TPH New WT can unload NBox wagon per hour Cost only for WT and associated system: 119.3Crs. Cost of Railway infrastructure:12.53 Crs Total Cost: Crs. Pay Back period: 7 Years. Fund Availability: to be tied up 22 September 2018

18 Bandel Thermal Power Station

19 R&M of BTPS Stage-I Unit No.1, 2, 3 & 4
BTPS unit No. 1 to 4 were commissioned way back in the year 1965/66. Original capacity was 82.5MW each In the year 2006 CEA de-rated the units and the revised capacity was declared as 60MW each The units were designed to fire coal of GCV 5175kcal/Kg to achieve full load Now a days average GCV of coal being fired is around 4000kcal/Kg It is very difficult to load the machines beyond 45MW No. of Mills per unit is 3 with capacity 19.5MT/hr All the units have completed more than 3 lac running hours Day to day problem faced are mill gear box mis -alignment and boiler tube failure 22 September 2018

20 R&M of BTPS Stage-I Unit No.1, 2, 3 & 4
After dismantling unit no 1 to 4, land available will be only 3.7 Acres. This land can accommodate 1X210MW unit with NDCT 13th Plan onwards CEA is approving only supercritical unit that is 660MW and above. Which is not feasible in BTPS due to land constraints To under take RLA studies of unit 1 to 4 as World Bank fund to the tune of 1Cr is already available and being undertaken. After completion of RLA studies, modification to be undertaken so that the units can run smoothly till the balance residual life. After completion of the balance life units are to be dismantle and land will be available for some other infrastructure use only 22 September 2018

21 Fund Availability: to be tied up
RETROFITTING OF ALL POWER PLANTS DUE TO ENVIRONMENT NOTIFICATION-2015 Sl. No. Environment protection Amendment rule-2015 Item Unit installed before Unit installed in-between to 1 SPM 100mg/Nm3 50mg/Nm3 2 So2 600mg/Nm3 600mg/Nm3 <500MW 200mg/Nm3>=500MW 3 Nox 300mg/Nm3 4 Mercury 0.03mg/Nm3>500MW 0.03mg/Nm3 Sl.No. Power Station Norms applicable Work to be done Approximate Estimated cost(Rs. in Crs.) 1 KTPS Unit 1 to 6 Unit installed before ESP and Ash handling plant (unit 4 to 6) FGD and NOx control 300 800 2 STPS unit no.5 &6 Unit installed in-between to 450 3 BkTPP unit No. 1 to 3 625 4 BkTPP unit No. 3 to 4 5 SgTPP Unit No. 1 to 4 600 Total Estimated cost of retrofitting 2775 Fund Availability: to be tied up

22 GOVT. EQUITY AND LOAN REQUIREMENT
Sl. No. Plant Item Total Cost(in Rs. Cr) Loan(in Rs. in Cr.) 70% of Total Govt. Fund required (Rs. in Crs.) 30% of Total 1 SgTPP Additional cost for unit no.3 & 4 690 483 = 309 Unit No.5 3630 2541 1089 2 BkTPP Unit No.6 3350 2345 1005 3 STPS Unit No.7 Total 11020 7714 3408 Total govt. equity requirement is Rs Cr. Total Loan requirement is Rs Cr.

23 GOVT. EQUITY/WBPDCL FUND REQUIREMENT
Sl. No. Plant Work to be done Fund required (Rs. in Crs.) 1 KTPS R&M of unit 1 to 3(ESP & Ash) 357 Installation of WT 132 2 SgTPP Mini Ash Pond 75 3 BkTPP 140 4 STPS 124 5 Total 828 6 KTPS U #1 to 6 ESP and Ash handling plant(unit 4 to 6) FGD and NOx control 300 800 7 STPS U #5 &6 450 8 BkTPP U# 1 to 5 625 9 SgTPP U#1 to 4 600 10 2775 Total Fund Required(5+10) 3603 Total Govt. Equity required for new Units 3408 Total Loan required for New Units 7714 Grand Total Fund required 14725

24 Thank You 22 September 2018