Facilities Improvements and Bond Construction Update Facilities Advisory Committee Long Beach Community College District December 2, 2008 EDUCATE ENGAGE EMPOWER 1
2
Agenda Completed Construction Projects PCC Learning Resource Center LAC Central Plant Current & Upcoming Construction Projects LAC South Quad Complex LAC Learning Resource Center LAC Building A, Student Services Retrofit LAC Math Technology Building LAC Parking Structure LAC Infrastructure Improvements – Phase 3 PCC Central Plant PCC Industrial Tech Phase 1 PCC MDAB (Multi-Disciplinary Academic Building) PCC Building C Retrofit District Wide Building Needs Assessment Projects Toilet Improvement Projects Quick-Start Projects ADA Projects Lighting Projects Classroom Improvement Projects Recently Completed Facilities Improvements Important Ongoing Initiatives Planned Phasing of Future Projects Q & A 2
3
Completed Construction Projects Construction Complete Modern Facility with Computer Lab and Multimedia Stand alone Data Center. Provides District IT redundancy Bridge to building E Design elements move towards energy efficiencies Ribbon cutting held 9/17/08 PCC Learning Resource Center – Measure E 2002 3
4
Completed Construction Projects Central Plant equipment, Public Safety, & Field House for Athletics Final FF&E installation underway Plant ready for operation and awaiting completion of LRC & SQC Construction Complete Anticipated startup 12/05/08 LAC Central Plant – Measure E 2002 4
5
Current and Upcoming Construction Projects Construction approx. 89% Complete Space includes Approx. 68,000 ASF 32 modern classrooms and labs 38 faculty offices Executive office Multipurpose room State of the art Board Room Substantial completion anticipated 1/09 South Quad Complex – Measure E 2002 5
6
Current and Upcoming Construction Projects Construction 91% Complete Adds 10,000 ASF to existing building Substantial Completion Anticipated January 2009 LAC/Learning Resource Center – Measure E 2002 6
7
Current and Upcoming Construction Projects Design Development to be submitted this month Adds 4,000 ASF to existing building Will house A&R, Counseling, Health Services, Cashier, Transfer Ctr., etc. Estimated start of construction 7/09 LAC Building A – Student Services Retrofit Measure E 2008 7
8
Current and Upcoming Construction Projects Completed Schematic Design (June 2008) Currently in Design Development phase Will house Math and Culinary Arts instructional program as well as Reprographics Estimated start of construction 2011 LAC Math Technology Building – Measure E 2008 8
9
Current and Upcoming Construction Projects Planning initiated for approximately 900 Vehicles To be procured under Design Build Delivery method To be located Southeast corner of Lot J adjacent to the Verizon building Photovoltaic Electrical Generation Array on top level of structure Anticipated start of construction 2009 LAC Parking Structure – Measure E 2008 9 Proposed Parking Structure Loc. Proposed Math Technology Bldg. Lot J Verizon Bldg.
10
Current and Upcoming Construction Projects LAC Infrastructure Improvements – Phase 3 Measure E 2008 Planning underway with engineers Completes chilled water lines to North side of campus Includes other major utility upgrades; Reclaimed Water, Domestic Water, Data, etc. Existing building HVAC systems to be upgraded in synch with infrastructure improvements Coordinated with modernization and quick start projects 10
11
Current and Upcoming Construction Projects Houses Central Plant equipment and Maintenance and Operations facility Construction Approximately 99% Complete Currently provides chilled water to the PCC LRC PCC Central Plant – Measure E 2002 11
12
Current and Upcoming Construction Projects Modern facility houses Welding Department and other trade programs Construction is 45% complete Replaces existing antiquated structures New Northern face of the campus Completion anticipated summer 2009 PCC Industrial Technology Center Phase 1 Measure E 2002 12
13
Current and Upcoming Construction Projects 90% construction documents submitted Swing space planning completed 9/2008, construction of swing space starts Spring 2009 Anticipated start of MDAB construction Summer 2009 To be completed in two phases PCC MDAB (Multi-Disciplinary Academic Building) Measure E 2002 13
14
Current and Upcoming Construction Projects To be designed by Hill Partnership Architects Houses the Fitness Center, Gymnasium, Weight Room, and Faculty and Staff Offices Swing space to be located on PCC Campus (TBD) To be completed concurrently with MDAB project Anticipated start of construction Spring 2010 PCC Building C Retrofit - Measure E 2008 14
15
Current and Upcoming Construction Projects Toilet Improvement Projects Quick-Start Projects ADA Projects District Wide Building Needs Assessment Project Measure E 2008 15
16
Current and Upcoming Construction Projects Lighting Projects Classroom Improvement Projects District Wide Building Needs Assessment Projects Measure E 2008 16
17
Recently Completed Facilities Improvements 17 Replaced existing boilers, pumps, expansion tanks and common flue with new equipment via helicopter lift. A newly upgraded design reflecting a mechanical engineered system was installed improving the efficiency of the boilers. Completed 10/2008 Building B and E Boiler Replacement
18
Recently Completed Facilities Improvements 18 Additional Facilities Improvements LAC upgrades: Veterans Stadium scoreboard and PA system upgrade Building K upgrades – Exterior door paint, room 111 floor refinishing PCC upgrades: Building AA – Built wall for information desk, installed carpet, and power upgrades Building BB – Carpet and window blind installation Building CC – Installed fans in gym Building DD – Carpet and window blind installation Building EE – Window blind installation Building MM – Exterior paint, replaced doors and awnings, re- glazed windows, and replaced fascia boards
19
Important Ongoing Initiatives Master Landscape Project District Wide Energy Efficiency Improvements Electronic Marquee Signage Wayfaring and Building Signage Campus Lighting Improvements 19 LBCCD Coming Advancements
20
Planned Phasing of Future Projects 20 Currently Planned Schedule 2008-09 Parking Structure – Design/Build concept Anticipate awarding bid Spring 2009 Moving Warehouse from PCC to Alteon Building at LAC – TBD Moving LAC Building A into Swing Space – Spring 2009 Install portables at PCC for Swing Space – Spring 2009 LAC/PCC Building Needs Assessment Projects Bathroom Improvement Projects Quick-Start Projects Lighting Projects Classroom Improvement Projects Infrastructure Projects Submit FPP for M/N Project at LAC and MM Project at PCC and submit IPP for P Building at LAC Finalize Master Landscaping and Signage plans Marquee signage anticipated to be installed March 2009
21
Planned Phasing of Future Projects 21 2009-10 Begin construction of Building A at LAC Anticipating July 2009 start Begin construction of Buildings CC, DD, and EE at PCC Anticipating July/August 2009 start Begin Schematic Design for Buildings C and F at LAC Submit plans to DSA no later than March 2010 Begin Master Landscaping and Signage Initiatives Continue District Wide Energy Efficiency Improvements Phase IIA Lighting Upgrades, HVAC Upgrades, Control upgrades, Pool Cover, Roof replacement, etc Phase IIB Upcoming advancements include connecting current buildings to Central Plant infrastructure Currently Planned Schedule
22
Planned Phasing of Future Projects 22 2010-11 Anticipated Construction completion of Building A at LAC – January 2011 Submit plans to DSA for Math/Technology Building at LAC Move Buildings C and F programs into Swing Space (M/N Building) and begin construction – Spring 2011 Construction completion of Buildings CC, DD and EE at PCC Begin construction of Buildings AA and BB at PCC Anticipating January/February 2011 start Currently Planned Schedule
23
Planned Phasing of Future Projects 23 2011-12 Begin construction of Math/Technology Building at LAC Submit plans to DSA for M/N Building at LAC 2012-13 Anticipated Construction completion of Buildings C and F at LAC – December 2012 Anticipated Construction completion of Math/Technology Building at LAC – December 2012 Begin construction of Buildings M/N at LAC – January 2013 Anticipated Construction completion of Buildings AA and BB at PCC – June 2013 Currently Planned Schedule
24
QUESTIONS & ANSWERS EDUCATE ENGAGE EMPOWER 24