Projects currently Under Construction Lewisville High School Renovation and Rebuild Lewisville High School Auditorium Westside Aquatics Center Flower Mound High School 9 th Grade Campus Flower Mound High School Athletic Fields Marcus High School 9 th Grade Campus
3
Lewisville H.S. Renovation and Rebuild Project Contractor: Balfour Beatty Construction Architect: SHW Group Project started: September, 2010 Project completion: November, 2013
4
Contractor: Balfour Beatty Construction Architect: SHW Group Project started: November, 2012 Project completion: November, 2013 Lewisville High School Auditorium Purdue
5
Lewisville High School Auditorium
8
Contractor: Adolfson and Peterson Construction Architect: SHW Group Project started: November, 2012 Project completion: November, 2013 Westside Aquatics Center
12
Contractor: Satterfield & Pontikes Construction Architect: PBK Project started : May, 2013 Project completion: Fall, 2014 Flower Mound H.S. 9 th Grade Campus
15
Flower Mound H.S. Sports Package Contractor: Satterfield & Pontikes Construction Architect: PBK Project started: May, 2013 Project completion: Fall, 2013
16
Marcus H.S. 9 th Grade Campus Contractor: Satterfield & Pontikes Construction Architect: PBK Project started : May, 2013 Project completion: Fall, 2014
17
Marcus H.S. 9 th Grade Campus
19
Projects Pending Construction Camey Elementary School Open Bids: September, 2013 Board Approval: October, 2013 Start Construction: October, 2013 Substantial completion: November, 2014 Griffin Middle School Open Bids: November, 2013 Board Approval: December, 2013 Start Construction: December, 2013 Substantial Completion: June, 2015
20
Construction Schedule: Project to start: Fall, 2013 Project Completion: Fall, 2014 Main Entry Camey Elementary Rebuild
23
Griffin Middle School Rebuild Construction Schedule: Project to start: Fall, 2013 Project Completion: June, 2015
24
Griffin Middle School Rebuild
25
Projects Currently Under Warranty: Marcus HS Athletic Package Under Warranty until April 2014
26
Contractor: Pogue Construction Architect: PBK Project under warranty until April, 2014 Marcus High School Athletic Package