Bond Construction Update Citizens Oversight Committee Long Beach Community College District April 21, 2008 BUILDING TOMORROW TODAY Cordoba Corporation
2
Agenda Completed Construction Projects Current & Upcoming Construction Projects South Quad Complex Structure LAC Central Plant Structure LAC Learning Resources Center – Structure LAC Building A, Student Services Retrofit PCC Central Plant PCC Learning Resources Center PCC Industrial Tech Phase 1 PCC MDAB (Multi-Disciplinary Administration Building) Q & A
3
Construction Progress
4
Completed Construction Projects PCC Industrial Technology Center Phase 2 – 7/07 PCC Central Plant Utilities, LAC Central Plant & SQC Utilities – 6/07 LAC/LRC Interim – 5/07 East Campus Demo – 12/06 LAC Mens Gym Façade Replacement (FEMA & Insurance Funded) – 8/06 LAC/LRC Utilities – 6/06 PCC CDC – 4/06 Mens Gym Boiler Replacement – 4/06 LAC Athletic Field – 3/06 District Facilities & Warehouse Complex – 1/06 Various Projects – Completed in 2006 & 2007
5
LAC Facility Site Plan l i b e r a l a r t s
6
Current and Upcoming Construction Projects Part of Infrastructure Master Plan Improvements Awarded to Siemens on DBOM Contract Construction 82% Complete Completion Anticipated Summer 2008 LAC Central Plant – Structure
7
Current and Upcoming Construction Projects Construction 55% Complete Combined into Single Construction Phase Completion Anticipated December 2008 LAC/Learning Resources Center – Structure
8
Current and Upcoming Construction Projects Construction Approx. 52% Complete Additional Modern Classrooms, Multi-purpose Rm., Offices, etc. Shifts Campus Center South of Carson off Lew Davis Completion Anticipated December 2008 South Quad Complex Structure (Bid Pkg. #3)
9
Current and Upcoming Construction Projects Martinez Architects received Board Approval as the Architect of Record Contract was negotiated/signed and Notice to Proceed was issued Programming work began on April 10, 2008 LAC Building A – Student Services Retrofit
10
PCC Facility Site Plan p a c i f i c c o a s t
11
Current and Upcoming Construction Projects Part of Infrastructure Master Plan Improvements Early Utility Package Construction Complete DBOM Contract Awarded to Siemens; Finalizing Value Engineering Negotiations Construction Approximately 36% Complete Completion Anticipated Summer 2008 PCC Central Plant
12
Current and Upcoming Construction Projects Construction 78% Complete Modern Facility with Computer Lab and Multimedia New Facility Bridge to Bldg. EE Completion Anticipated July/August 2008 PCC Learning Resources Center
13
Current and Upcoming Construction Projects Replaces Existing Antiquated Structures Construction is 12% Complete Modern Facility Houses Machine Tool and Welding Departments New Northern Face of the Campus Completion Anticipated Spring 2009 PCC Industrial Technology Center Phase 1
14
Current and Upcoming Construction Projects Programming is completed and submitted to the State for Approval Schematic Design was completed in February 2008 PCC MDAB (Multi-Disciplinary Academic Building)
15
QUESTIONS & ANSWERS Prepared by Bond Management Team April 21, 2008 BUILDING TOMORROW TODAY Cordoba Corporation