Bond Construction Update Citizens Oversight Committee Long Beach Community College District April 21, 2008 BUILDING TOMORROW TODAY Cordoba Corporation.

Similar presentations


Presentation on theme: "Bond Construction Update Citizens Oversight Committee Long Beach Community College District April 21, 2008 BUILDING TOMORROW TODAY Cordoba Corporation."— Presentation transcript:

1 Bond Construction Update Citizens Oversight Committee Long Beach Community College District April 21, 2008 BUILDING TOMORROW TODAY Cordoba Corporation

2 Agenda Completed Construction Projects Current & Upcoming Construction Projects South Quad Complex Structure LAC Central Plant Structure LAC Learning Resources Center – Structure LAC Building A, Student Services Retrofit PCC Central Plant PCC Learning Resources Center PCC Industrial Tech Phase 1 PCC MDAB (Multi-Disciplinary Administration Building) Q & A

3 Construction Progress

4 Completed Construction Projects PCC Industrial Technology Center Phase 2 – 7/07 PCC Central Plant Utilities, LAC Central Plant & SQC Utilities – 6/07 LAC/LRC Interim – 5/07 East Campus Demo – 12/06 LAC Mens Gym Façade Replacement (FEMA & Insurance Funded) – 8/06 LAC/LRC Utilities – 6/06 PCC CDC – 4/06 Mens Gym Boiler Replacement – 4/06 LAC Athletic Field – 3/06 District Facilities & Warehouse Complex – 1/06 Various Projects – Completed in 2006 & 2007

5 LAC Facility Site Plan l i b e r a l a r t s

6 Current and Upcoming Construction Projects Part of Infrastructure Master Plan Improvements Awarded to Siemens on DBOM Contract Construction 82% Complete Completion Anticipated Summer 2008 LAC Central Plant – Structure

7 Current and Upcoming Construction Projects Construction 55% Complete Combined into Single Construction Phase Completion Anticipated December 2008 LAC/Learning Resources Center – Structure

8 Current and Upcoming Construction Projects Construction Approx. 52% Complete Additional Modern Classrooms, Multi-purpose Rm., Offices, etc. Shifts Campus Center South of Carson off Lew Davis Completion Anticipated December 2008 South Quad Complex Structure (Bid Pkg. #3)

9 Current and Upcoming Construction Projects Martinez Architects received Board Approval as the Architect of Record Contract was negotiated/signed and Notice to Proceed was issued Programming work began on April 10, 2008 LAC Building A – Student Services Retrofit

10 PCC Facility Site Plan p a c i f i c c o a s t

11 Current and Upcoming Construction Projects Part of Infrastructure Master Plan Improvements Early Utility Package Construction Complete DBOM Contract Awarded to Siemens; Finalizing Value Engineering Negotiations Construction Approximately 36% Complete Completion Anticipated Summer 2008 PCC Central Plant

12 Current and Upcoming Construction Projects Construction 78% Complete Modern Facility with Computer Lab and Multimedia New Facility Bridge to Bldg. EE Completion Anticipated July/August 2008 PCC Learning Resources Center

13 Current and Upcoming Construction Projects Replaces Existing Antiquated Structures Construction is 12% Complete Modern Facility Houses Machine Tool and Welding Departments New Northern Face of the Campus Completion Anticipated Spring 2009 PCC Industrial Technology Center Phase 1

14 Current and Upcoming Construction Projects Programming is completed and submitted to the State for Approval Schematic Design was completed in February 2008 PCC MDAB (Multi-Disciplinary Academic Building)

15 QUESTIONS & ANSWERS Prepared by Bond Management Team April 21, 2008 BUILDING TOMORROW TODAY Cordoba Corporation


Download ppt "Bond Construction Update Citizens Oversight Committee Long Beach Community College District April 21, 2008 BUILDING TOMORROW TODAY Cordoba Corporation."