1
PROGRESS REPORT As of September 22, 2011
2
I.Project StatusProject Status II.S-CurveS-Curve III.Revised Construction ScheduleRevised Construction Schedule IV.Manpower ProfileManpower Profile V.Monthly ReportMonthly Report VI.Progress Photos: – Earthworks Earthworks – Barge Pier Construction Barge Pier Construction – Seawall Construction Seawall Construction
3
* Based on approved Construction Schedule version September 1, 2011. SCHEDULEPLANNEDACTUALVARIANCE ORIGINAL64.38%29.16%-35.22% REVISED*18.47%29.16%10.69% (Original) Time Elapsed / Duration (Days): 169 / 306 = 55.23% (Revised) Time Elapsed / Duration (Days): 169 / 334 = 50.90%
4
ACTUAL, 3.79% (as of June 23, 2011)
6
BLUE SHEET COVERING THE BACKFILL MATERIALS STOCKPILING OF STONES SCREENING OF EXCAVATED MATERIALS
7
INSTALLED WIREMESH AND INITIAL SHOTCRETING OF WEATHERED SLOPE SURFACE COMPACTION FDT OF COMPACTED AREA
8
GEOTEXTILE LINER INSTALLATION DREDGING WORKS GEOTEXTILE LINER INSTALLATION AND STONE LAYING GEOTEXTILE LINER INSTALLATION
9
DREDGING FOR SEAWALL GEOTEXTILE LINER INSTALLATION STONES FILLING (10-100 KG)
10
2-TON CONCRETE ARMOR INSTALLATION STONES FILLING (300-500 KG)
11
2-TON CONCRETE ARMOR INSTALLATION HAULING OF PRE-CAST RC WALL
12
INSTALLATION OF PRE-CAST RC WALL LEAN CONCRETE POURING SURFACE PREPARATION PRIOR TO LEAN CONCRETE POURING INSTALLATION OF PRE-CAST RC WALL
13
CONSTRUCTION OF SEAWALL GAP CONCRETE CYLINDER SAMPLING CONSTRUCTION SEAWALL SEGMENT CONSTRUCTION OF SEAWALL GAP
14
-END- THANK YOU