Construction Start Date: May 4, 2009 Architect: FGM Architects – OFallon, IL Civil : Hoelscher Engineering – Fairview Heights, IL Mechanical / Plumbing: Cover Engineering – Alton, IL Electrical: Solutions AEC – St. Louis, MO General Contractor: R.W. Boeker – Hamel, IL STAUNTON TRACK AND CONCESSION BUILDING 2009 FGM ARCHITECTS #08-0850.01
2
Construction Photo Date: May 6, 2009 STAUNTON TRACK AND CONCESSION BUILDING 2009 FGM ARCHITECTS #08-0850.01
3
Construction Photo Date: June 7, 2009 STAUNTON TRACK AND CONCESSION BUILDING 2009 FGM ARCHITECTS #08-0850.01
4
Construction Photo Date: June 22, 2009 STAUNTON TRACK AND CONCESSION BUILDING 2009 FGM ARCHITECTS #08-0850.01
5
Construction Photo Date: June 29, 2009 STAUNTON TRACK AND CONCESSION BUILDING 2009 FGM ARCHITECTS #08-0850.01
6
Construction Photo Date: July 7, 2009 STAUNTON TRACK AND CONCESSION BUILDING 2009 FGM ARCHITECTS #08-0850.01
7
Construction Photo Date: July 13, 2009 STAUNTON TRACK AND CONCESSION BUILDING 2009 FGM ARCHITECTS #08-0850.01
8
Construction Photo Date: July 20, 2009 STAUNTON TRACK AND CONCESSION BUILDING 2009 FGM ARCHITECTS #08-0850.01
9
Construction Photo Date: July 27, 2009 STAUNTON TRACK AND CONCESSION BUILDING 2009 FGM ARCHITECTS #08-0850.01
10
Construction Photo Date: Aug 10, 2009 STAUNTON TRACK AND CONCESSION BUILDING 2009 FGM ARCHITECTS #08-0850.01
11
Construction Photo Date: Aug 11, 2009 STAUNTON TRACK AND CONCESSION BUILDING 2009 FGM ARCHITECTS #08-0850.01
12
Construction Photo Date: Aug 17, 2009 STAUNTON TRACK AND CONCESSION BUILDING 2009 FGM ARCHITECTS #08-0850.01
13
Construction Photo Date: Aug 24, 2009 STAUNTON TRACK AND CONCESSION BUILDING 2009 FGM ARCHITECTS #08-0850.01
14
Construction Photo Date: Oct 7, 2009 STAUNTON TRACK AND CONCESSION BUILDING 2009 FGM ARCHITECTS #08-0850.01
15
Construction Photo Date: Oct 7, 2009 STAUNTON TRACK AND CONCESSION BUILDING 2009 FGM ARCHITECTS #08-0850.01
16
Construction Photo Date: Oct 7, 2009 STAUNTON TRACK AND CONCESSION BUILDING 2009 FGM ARCHITECTS #08-0850.01
17
Concession Building Construction Photo Date: July 20, 2009 STAUNTON TRACK AND CONCESSION BUILDING 2009 FGM ARCHITECTS #08-0850.01
18
Concession Building Construction Photo Date: July 27, 2009 STAUNTON TRACK AND CONCESSION BUILDING 2009 FGM ARCHITECTS #08-0850.01
19
Concession Building Construction Photo Date: Aug 10, 2009 STAUNTON TRACK AND CONCESSION BUILDING 2009 FGM ARCHITECTS #08-0850.01
20
Concession Building Construction Photo Date: Aug 17, 2009 STAUNTON TRACK AND CONCESSION BUILDING 2009 FGM ARCHITECTS #08-0850.01
21
Concession Building Construction Photo Date: Oct 7, 2009 STAUNTON TRACK AND CONCESSION BUILDING 2009 FGM ARCHITECTS #08-0850.01
22
Construction Start Date: May 4, 2009 Architect: FGM Architects – OFallon, IL Civil : Hoelscher Engineering – Fairview Heights, IL Mechanical / Plumbing: Cover Engineering – Alton, IL Electrical: Solutions AEC – St. Louis, MO General Contractor: R.W. Boeker – Hamel, IL STAUNTON TRACK AND CONCESSION BUILDING 2009 FGM ARCHITECTS #08-0850.01