Wendover Renovation Presentation 2011-2012
2
Presentation Overview Renovation Stages Before Now After How you will be affected Questions/Concerns
3
Story Behind this School This school was built in 1970 as a temporary school and was designed to last only twenty years. So, in 1990 it should have been demolished and rebuilt. But now, in 2012, it is being renovated.
4
Lets get on to the stages…
5
Renovation Stages - Before Front Side of Wendover Water DamageBoarded Windows
6
Renovation Stages - Before No Central Air Conditioning Over the years, there has been a couple air conditioners added on to the building that mostly cool down rooms that dont have windows.
7
Renovation Stages - Before Other parts of the building that are damaged.
8
Renovation Stages - Before
10
Renovation Stages – Before
11
Renovation Stages - Now These pictures show a general idea of what is going on now. The ceiling tiles were removed during Christmas break. Since they are gone, it will be slightly colder in the hallways.
12
Renovation Stages - Now During the time period of the renovation, the equipment and trailers are going to be stored on the football field. It is still to be decided whether or not the football teams will be consolidated into one team next year.
13
Overview
14
Renovation Stages - Now PHASE 1 – *Cafeteria* and Band Room (December 2011 – August 2012)
15
Renovation Stages - Now PHASE 1 – *Cafeteria* and Band Room (December 2011 – August 2012)
16
Renovation Stages - After
17
Renovation Stages - Now PHASE 1 – Cafeteria and *Band Room* (December 2011 – August 2012)
18
Renovation Stages - Now PHASE 1 – Cafeteria and *Band Room* (December 2011 – August 2012)
19
Renovation Stages - After Along with the cafeteria and the band room, there will be a server room where the old instrument storage room used to be. Also there will be an electrical room where the old weight room used to be.
20
Renovation Stages - After PHASE 2 – Kitchen and Storage ( April 2012 – August 2012)
21
Renovation Stages - After PHASE 2 – Kitchen and Storage ( April 2012 – August 2012)
22
Renovation Stages - After PHASE 3 – 8 th Grade Hallway and Courtyard B (May 2012 – August 2012) The new 8 th grade hallway will be where rooms 127 and 128 are now. Also, Courtyard B will be between the 7 th grade hallway and the 8 th grade hallway. Also, there will be the new TV Studio where room 100 is now.
23
Renovation Stages - After PHASE 4 – * 6 th Grade Hallway, Courtyard A,* Art Rooms, Chorus Room and Music Room (September 2012- December 2012)
24
Renovation Stages - After PHASE 4 – 6 th Grade Hallway, Courtyard A, *Art Rooms, Chorus Room and Music Room* (September 2012-December 2012)
25
Renovation Stages - After PHASE 5 – *7 th Grade Hallway*, Library, Health Room, Computer Lab (January 2013 – May 2013)
26
Renovation Stages - After PHASE 5 – 7 th Grade Hallway, *Library, Health Room, Computer Lab* (January 2013 – May 2013)
27
Renovation Stages - After PHASE 6 – FCS, Computer Lab, Gym (March 2013 – August 2013)
28
Renovation Stages - After PHASE 7 – Hallways and Entrance (June 2013 – August 2013)
29
Renovation Stages - After PHASE 8 – Admin Offices and Auditorium (June 2013 – November 2013)
30
By the end of November 2013, this school will be complete.
31
How You Will Be Affected On the first week of May, lunches will be moved into the front side of the gym. Also in May, the classes in the back hallway will be moved into the auditorium.