Download presentation
Presentation is loading. Please wait.
1
PROJECT MANAGEMENT WITH CPM/PERT
2
Project Management Project Definition Primarily Management Functions
Consists of a series of tasks (or activities) with following characteristics Starting and ending dates Well-defined objectives Unique endeavor Utilizing resources Primarily Management Functions Planning Organizing Controlling
3
Project Management Functions
PM functions are to manage Cost and time Human resources Communication Contract/procurement Risk
4
Project Management When to use Complex projects Several parallel tasks
Predefined deadlines and milestones must be met Estimate project completion time Difficult to know when project is in trouble Limited and conflicting resources
5
Examples Building a new airport Expanding a plant
Designing a new product Construction projects of all types Maintenance projects R&D projects
6
Project Planning Process
Define project objective(s) Identify activities Establish precedence relationships Make time estimates Determine project completion time Schedule activities Balance resources to meet objective(s)
7
Typical Questions for PM’s
What is the the total time to complete a project? What are the scheduled start and finished dates for each activity? Which activities are critical and must be completed on time to keep the project on schedules? How long can noncritical activities be delayed before they cause a delay in the project completion time? Is there any way to reduce the project completion time? How much money is needed to expedite the project completion time?
8
Project Management Techniques
Critical Path Method (CPM) Developed in 1950’s Planed and control maintenance job of a chemical plant Reduced length of maintenance shutdown by 40% Project Evaluation and Review Technique (PERT) Developed in 1960’s Planed and control the Polaris missile project Speeded up project by 2 years
9
Critical Path Method (CPM)
Graphical method of showing relationship of project activities An activity or task --takes resources and time to complete Precedence relations (some must be completed before others can start) must be constructed Critical Path Method is the longest path through the resulting project network
10
Immediate Predecessor
Precedence Relations Activity Immediate Predecessor Duration (days) A (Start) 8 B A 6 C A 8 Act. Pred. Duration A - 4 B A 3 C A 5 D B, C 2 D A 10 E B,C,D 4
11
Simple Project Network “Activity on Node” AON representation
Successor Precedence relations represented by “arcs” B Predecessor A D E B C D A C Project Network
12
Simple Project Network “Activity on Arc” AOA representation
2 B 6 4 E A C 3 1 4 6 8 D 10 4
13
Activity Start/Finish Times (AON)
Activity Name Early Finish Time Early Start Time ES EF LF LS D Late Start Time Activity Duration Late Finish Time Activity Name Earliest Start Earliest Finish ES LS EF LF Latest Start Latest Finish Activity Time
14
Finding the Critical Path
B C C E A B 4 7 D 6 9 3 A D 4 9 11 4 9 11 4 2 C 4 9 4 9 5
15
Forward Pass 8 B 14 6 8 C 16 A 18 E 22 8 8 4 8 B 4 7 8 D 18 6 9 3 5 10 A D 4 9 11 4 9 11 4 2 C 4 9 4 9 5
16
Backward Pass 8 B 14 12 6 18 8 C 16 A E 8 18 22 10 8 18 18 4 22 8 8 8 D 18 5 8 10 18
17
Finding Activity Slack S =EF-ES = LF-EF
8 B 14 S =18-14=4 14 6 18 S =22-22=0 S =8-8=0 8 C 16 E A 8 18 22 10 8 18 22 8 8 18 4 S =18-16=2 8 D 18 5 Critical Path: Path with zero activity slacks 8 10 18 S =18-18=0
18
Example Consider the following activities of a project
Activity Predecessors Time (wks) A none 4 B none 12 C B 6 D A 16 E. A,C 12 F B 16 G. E,F 10 H. D,G 0
19
Project Network D A Finish Start E C B G F
20
PERT (Program Evaluation and Review Technique)
Similar to Critical Path Method (CPM) Uncertainty in activity duration Provides estimates of project duration probabilities Best used for highly uncertain projects new product development first-time projects R&D projects
21
Dealing with Uncertain Activity Duration
The PERT three-estimate Approach Most likely estimate (m) estimate of the most likely value of duration Optimistic estimate (b) estimate of the duration under the most favorable conditions Pessimistic estimate (a) estimate of duration under the unfavorable conditions
22
A Simple Example Activity Most Optimistic (a) Most Likely (m) Most Pessimistic (b) A 2 8 14 B 3 6 9 C 5 7.5 13 Act. Opt. Likely Pess. A B C 4 5 6 D D 3 10.5 15 E 2.5 11.5 2.5
23
Distribution Assumption
Beta distribution density a m b activity duration Expected Time = a + 4m + b 6 (b - a)2 36 Variance =
24
Expected Duration & Variance
Activity A a + 4m + b 6 = 2+4(8)+14 6 ET = = 8.0 Expected time = (Most Optimistic + 4*Most Likely + Most Pessimistic)/6 Variance = (Most Pessimistic - Most Optimistic)^2/36 (b - a)2 36 = (14-2)2 36 =4 Var =
25
Expected Duration & Variance
Activity Expected Time Variance Critical Path? 8 4 A ? 6 1 B 8 1.77 C Act. E(Time) Var. C.P.? A Yes B No C Yes D Yes 10 4 D ? 4 2.33 E ?
26
Probability of Completion
Probability that a project will be completed by a specified due date Due Date - Expected Completion Date z = Sum of the Variances on the Critical Path Expected Completion Normal Distribution z Due Date z See Appendix 3 (pg. 886) for a table of Normal Distribution probabilities.
27
Completion Probability Example
What is the probability of completing the project within 24 days? = 0.624 z = From a Z-table for standard Normal distributions: z = ( )/sqrt( ) z = 1/1.607 = 0.622 Probability = = 73.24% (An overhead of the Normal distribution table (pg. 886) is needed to work this example.) Probability of completion = = 73.2%
28
Considering Time-Cost Trade-offs
If extra money is spent to expedite the project, what is the least expensive way of attempting to meet the target completion time? Define Normal and crash points Normal point shows the time and cost when an activity is performed in the normal way Crash point shows the time and cost when an activity is fully crashed
29
Time-Cost Relationship
Assumed linear relationship (Crash cost-Normal cost) (Crash time-Normal time) Crash Crash cost/wk= Crash Cost Normal Cost Normal Normal time Crash time
30
Example Time (wk) Cost($1000) Activity Normal Crash Max. Red. Cost/wk
B C D E 8 6 10 4 5 9 3 7 2 1 2/2=1 2/1=2 6/3=2 2/1=2 1/1=1
31
Crashing An Activity
32
Other Project Mgmt Techniques
Resource leveling How to schedule resources (equipment, people) to minimizes Multiple resource scheduling How to schedule resources when activities can require more than one resource type Cash flow and budgeting Combine cash and budget information with project scheduling to track expenditures, project cash flows
33
Problems 1. A project involving the installation of a computer system comprises eight activities. The following table lists immediate predecessors and activity times (in weeks). Activity Immediate Predecessor Time A B C A 2 D B,C 5 E D 4 F E 3 G B, C 9 H F, G 3 Draw a project network. What are the critical activities? What is the expected project completion time? 2. Building a backyard swimming pool consists of nine major activities. The activities, their immediate predecessors, and their time estimates (in days) are shown in the following table. Activity A B C D E F G H I Immediate Pred. - - A,B A,B B C D D,F E,G,H Optimistic Most Probable Pessimistic What is the probability that a project can be completed in 25 or fewer days?
34
3. Consider the following project.
Immediate Time (Weeks) Cost ($1000) Activity Predecessor Normal Crash Normal Crash A B A C B D A E D F C,E Develop a project network. Develop an activity schedule. What are the critical activities and what is the expected project completion time? Assume that the project manager wants to complete the project in 6 months or 26 weeks. What crashing decisions do you recommend to meet the desired completion time at the least cost? Work through the network and attempt to make the crashing decisions by inspection. Develop an activity schedule for the crashed project. What added project cost is required to meet the 6-month completion time?
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.