1 FSS Vehicle Shelving Systems
Managers Delivery Programs Support May 7, 2008

2 FSS Vehicle Shelving Systems
Requirements Total system weight: 275 pounds or less. Tray/Parcel Volume: 7 mail trays, 2 residual trays, 2 saturation trays, 7 FSS street trays, 12 parcels. Increase mail tray and stowage capacity Provide improved efficiency for loading and access of the mail and for disposition of the empty trays Improve tray and parcel organization Improve efficiency of moving mail from the cargo area to the front work area Operation intuitive for carriers Meet ergonomic requirements

3 FSS Shelving Background
FSS Vehicle Shelving Systems FSS Shelving Background Supplier Conference on FSS shelving systems Jan. 2007 Solicitation Issued Mar. 2007 Proposals Evaluated Apr. 2007 Prototype Build Jun. 2007 Unit Cost Reassessed Aug. 2007 2nd Prototype Evaluated Oct Prototype Contract Award Nov. 2007 100 Field Eval Unit Installation Feb. 2008

4 FSS Vehicle Shelving Systems
No System

5 FSS Vehicle Shelving Systems
System A

6 FSS Vehicle Shelving Systems
System B

7 FSS Vehicle Shelving Systems
System C

8 Field Carrier Evaluation – Reston and Fairfax POs
FSS Vehicle Shelving Systems Field Carrier Evaluation – Reston and Fairfax POs Approx. 60 carriers used the three systems from March 10-April 19 Each carrier utilizes one system for two weeks. Survey and interviewed follow at the end of each usage Unofficial Official Results System A: Some carriers did like the system, some did not. System B: Almost all of carriers did not like the system System C: Majority of carriers like the system.

9 System Evaluation The final system will be selected based on:
FSS Vehicle Shelving Systems System Evaluation The final system will be selected based on: Carrier Survey Durability Test System Interaction Study Repair/Maintenance Time and Ease of Installation

10 Cycle Durability Test Mar. 8 – Apr.30
FSS Vehicle Shelving Systems Next Steps Cycle Durability Test Mar. 8 – Apr.30 Road Durability Test Mar.10 – Apr.15 Production Cost Submission Apr. 15 Selection for Crash Test May 15 Crash Test Completed Jun. 15 Contract Award for 18,000 units Jul. 15 First Article Inspection Sep. 1 Delivery Oct. 1/08 – Oct. 1/10