Download presentation
Presentation is loading. Please wait.
Published byPatrick Ball Modified over 6 years ago
1
Acterna Headquarters John M Sekel, EIT Germantown, Maryland
The Pennsylvania State University Architectural Engineering 2003 Senior Thesis Presentation Structural Emphasis
2
Presentation Overview
Existing building Problem statement Proposal Structural re-design Construction considerations Architecture re-design Mechanical considerations Conclusions Structural Option John M Sekel
3
Existing building Project Team Owner: Milestone Industrial, LLC.
Architect: Hickok, Warner, Fox Architects Structural Engineer: Structural Design Group MEP Engineer: Girard Engineering General Contractor: L.F. Jennings Structural Option John M Sekel
4
Existing Building General New corporate campus for Acterna Corporation
Site clearly visible off I-270 outside Washington, D.C. Six story, 187,500 sf office building $10 million construction cost Structural Option John M Sekel
5
Existing Building Structural Composite beam and slab construction
50 ksi wide flange shapes 30’x25’ typical bays 3 ¼” lightweight concrete slab on 2” metal decking Spread footing foundations First floor slab on grade 2 – transfer girders over conference room on level 1 4 – braced frames for lateral stability Structural Option John M Sekel
6
Existing Building Typical framing plan Structural Option John M Sekel
7
Existing Building Mechanical Lighting/Electrical
VAV boxes with electric duct heaters and reheat coils with VFD 2 – cfm VAV A/C units per floor 2 – 350 ton cooling towers Plate and frame heat exchanger Lighting/Electrical 480/277 volt, 3-phase, 4 wire system 4000 amp primary switchboard 2000 amp secondary switchboard 2000 kW emergency generator 2’x4’ Lightolier 277 volt florescent fixtures Structural Option John M Sekel
8
Problem Statement Column lines limit space usage
Design and construction can be coordinated better Etc. Structural Option John M Sekel
9
Proposal Structural design criteria
Eliminate intermediate column line outside of core Long span steel from core to exterior “Stream-line” the structure Design for ease of construction Produce most efficient design Structural Option John M Sekel
10
Proposal Architectural design goals
Reflect structural changes in the façade Open interior spaces, column free areas Produce modern look ?? Structural Option John M Sekel
11
Proposal Construction considerations Mechanical considerations
Reduce construction cost Reduce construction schedule time Integrate building design and construction Mechanical considerations Analyze impact of façade design on system Structural Option John M Sekel
12
Structural depth Framing re-design
New bay size outside of core 30’x50’ 50 ksi wide flange shapes Most readily available 3 ¼” lightweight concrete slab on 2” metal deck 2 hour fire rating Re-size frames for additional gravity load Structural Option John M Sekel
13
Structural Depth New framing plan Structural Option John M Sekel
14
Structural Depth New member sizes Girders Beams Structural Option
Original: W18x35 New design: W24x62 Beams Original: W14x22 New design: W24x55 Structural Option John M Sekel
15
Architectural Breadth
Structural Option John M Sekel
16
Construction Breadth Structural Option John M Sekel
17
Conclusions Structural Option John M Sekel
18
Thank You Structural Option John M Sekel
19
Questions? Structural Option John M Sekel
Similar presentations
© 2024 SlidePlayer.com. Inc.
All rights reserved.