ACCOMPLISHMENT REPORT
ENGR. ALFE Y. JACOBE, P.I.C.E.
2
CY 2017 BASIC EDUCATION FACILITIES FUND (BEFF) CONSTRUCTION OF CLASSROOMS
3
Recommended Building Type Total Construction Cost
CY 2017 NEW CONSTRUCTION School ID School Name Recommended Building Type Total No. of Classrooms Total Construction Cost BATCH 109777 Bagong Bayan Elementary School 4STY16CL 16 38,132,332.96 BATCH 10 301505 Col. Lauro D. Dizon Memorial National High School 4STY20CL 20 42,323,895.04 109751 Col. Lauro P. Dizon Elementary School 3STY6CL 6 14,466,608.87 109759 Dapdapan Elementary School 4STY12CL 12 32,569,121.58 109768 Del Remedio Elementary School 32,792,996.60 109793 Don Enrique Bautista Elementary 42,771,645.04 109794 Fernando A. Quisumbing Elementary School 3STY9CL 9 25,354,996.64
4
Recommended Building Type Total Construction Cost
CY 2017 NEW CONSTRUCTION School ID School Name Recommended Building Type Total No. of Classrooms Total Construction Cost BATCH 109750 Guadalupe Elementary School 3STY6CL 6 14,242,733.87 BATCH 10 109774 Margarita Lopez Laurel Memorial School 109761 Placido Escudero Memorial School 4STY16CL 16 37,759,207.96 109773 Prudencia D. Fule Memorial Elementary School 3STY12CL 12 30,319,095.34 109769 San Crispin Elementary School 2STY4CL 4 9,526,945.70 109797 San Gregorio ES 4STY8CL 8 17,713,748.27 BATCH 10 301503 San Cristobal National High School 4STY12CL 12 32,419,871.58 109754 San Gabriel Elementary School 17,937,623.27
5
Recommended Building Type Total Construction Cost
CY 2017 NEW CONSTRUCTION School ID School Name Recommended Building Type Total No. of Classrooms Total Construction Cost BATCH 109799 San Isidro Elementary School 3STY9CL 9 26,026,621.64 BATCH 10 109764 San Jose Elementary School 4STY12CL 12 32,494,496.58 308602 San Jose National High School 4STY LAB 4 17,223,022.82 109790 San Lucas II Elementary School 4STY16CL 16 37,759,207.96 109755 San Miguel Elementary School 37,833,832.96 308605 San Pablo City Science High School 342575 SAN PABLO CITY SENIOR HIGH SCHOOL (STAND ALONE) 2STY4CL 9,228,445.70 2STY LAB 17,039,166.31
6
Recommended Building Type Total Construction Cost
CY 2017 NEW CONSTRUCTION School ID School Name Recommended Building Type Total No. of Classrooms Total Construction Cost BATCH 342575 SAN PABLO CITY SENIOR HIGH SCHOOL (STAND ALONE) UNIQUE WORKSHOP (7X22.5) 2 5,074,500.00 BATCH 10 109783 San Roque Elementary School 4STY16CL 16 38,206,957.96 109784 Santiago I Elementary School 4STY8CL 8 17,713,748.27 109775 Sta. Filomena Integrated School 37,983,082.96 109758 Stmo. Rosario Elementary School 4STY12CL 12 32,718,371.58 109808 San Diego ES 4STY20CL 20 42,547,770.04 109811 Sta. Catalina ES 3STY12CL 30,468,345.34
7
TOTAL NO. OF CLASSROOMS: 338 TOTAL PROJECT COST: PHP 840,246,482.29
CY 2017 NEW CONSTRUCTION TOTAL NO. OF CLASSROOMS: 338 TOTAL PROJECT COST: PHP 840,246,482.29
8
CY 2018 BASIC EDUCATION FACILITIES FUND (BEFF) CONSTRUCTION OF CLASSROOMS
9
Recommended Building Type
CY 2018 NEW CONSTRUCTION School ID School Name Recommended Building Type Total No. of Classrooms TOTAL 152 Dolores National High School 4STRY-20CL 20 109762 Platon ElementarySchool 3STRY-9CL 9 109771 San Marcos Elementary School 4STRY-16CL 16 109776 Sta. Maria Magdalena Elementary School 3STRY-6CL 6 109782 Major Juan Eseo Elementary School 109785 Sta. Monica Elementary School 4STRY-12CL 12 109788 C.M. Azcarate Elementary School 109796 San Antonio II Elementary School 3STRY-12CL 109802 Sta. Ana Elementary School 109803 Antonia Manuel Magcase Elementary School 4STRY-8CL 8 109806 Guerilla Elementary School 109809 San Lorenzo Elementary School 301504 San Pablo City National High School 4STRY-20CL 20 301505 Col. Lauro D. Dizon Memorial National High School
10
THANK YOU