The race towards 43rd ASECAP Study & Information Days 2015
Robert M. Nowak – Autostrada Wielkopolska SA II President Epic Sana Hotel 27-29 May 2015
2
Background (2007-2009) 106 km A2 Motorway - TEN corridor
Within AWSA Concession contract Higly required stretch But low traffic projections 4 years of negotiations ( ) UEFA decision re „EURO2012” in 2007 Different remuneration schemes proposed by state advisors - unbankable
3
Background (2007-2009) 106 km A2 Motorway - TEN corridor
Within AWSA Concession contract Higly required stretch But low traffic projections 4 years of negotiations ( ) UEFA decision re „EURO2012” in 2007 Different remuneration schemes proposed by state advisors - unbankable
4
However……. The race towards EURO 2012
Differences in approach, many years of ineffective negotiations EURO 2012 on top of the political agenda 2008 switch from full traffic risk into availability scheme Negative impact of economic turmoil following the LB collapse 1 more year of negotiations to reach the financial close Need to set up new SPV and transfer concession rights Necessity to combine open and closed tolling systems However…….
5
Yes, we can……………….. Managing the risk despite diversity
Lack of time improved negotiations Political courage of the decision makers to revisit the risk profile Strong support from EIB 3 months of negotations with Lenders – Financial Close June 2009 Biggest toll motorway project 2009/2011: ca. 1,5 bilion € overall project cost ca. 1,3 bilion € construction cost turn key contract ca. 1 bilion € EIB, ca. 0,4 € bilion commercial banks ca. 0,2 € bilion junior funds including equity Commencement of works - July 2009 Completion of works – November 2011 Commencement of tolling – May 2012
6
The power of commitment
Strong determination of the concessionaire and belief in the project Flexibility of the government towards slightly different risk profile Teams working to achieve one common goal Project executed : Six months ahead of the tolling commencement deadline Within the budget No events of bancruptcy of construction partners
7
The only fast clearing system between SPVs in Europe
Unique clearing system allows the immediate distribution of the toll revenue among two concessionaires (AWSA and AWSA II): No monthly phasing No mutual set-off No impact on final user No double receipts Transparency towards Ministry of Infrastructure
8
Finally ….. This challenge made them happy……
9
Finally ….. This challenge made them happy……
22 June 2012, Gdańsk Ergo Arena Germany 4 : 2 Greece
10
Thank you Questions please