Tramways in Norway Nordic Rail 6 October 2015 Ove Skovdahl
Senior Advisor Rejlers Norge AS/ Division Railconsult
2
The speaker Railway Engineer 1985 (M.Sc.C.Eng. M.M.)
30 years Railway Experience Infrastructure, Traffic Control, Safety, HR, ICT, Management. Railconsult AS/ Rejlers Norge AS 2008- Bybanen Bergen: Procurement of LRT Operations Light Rail Stavanger: Senior Advisor to Project Director Oslo : Coordinating tram on metro preparations Grenland and Nedre Glomma: Feasibility Studies Visits to 54 European Tramway Cities….
3
Rejlers norge AS Rejlers is a Nordic group offering engineering consultancy services to customers in the fields of Building and property, Energy, Industry and Infrastructure. Rejlers Norge AS Divison Railconsult is Rejlers’ Norwegian Rail Unit We are 25 highly competent rail consultants with a range of expertise from pre-studies and planning to design, construction, project planning and project management. Our focus is sustainable rail based transport
4
Outline of presentation
General Challenges Oslo Trondheim Bergen Stavanger Grenland Nedre Glomma Conclusion
5
Geography Population structure and topography not ideal for PT, except Oslo and Bergen Areas. We still have some rural roads to improve (replacing car ferries) No significant road traffic congestion challenges (except Oslo Area) But still; increasing public and political interest for PT improvements Oslo Area Population expected to increase by next 15 years – Increasing mobility concern…
6
Outside the Oslo Area People who never travel by Public Transport; have limited (no) personal PT experience: Public Sector responsibles for area development and transport sectors Politicians at all levels (State, County, Municipality) Healthy Norwegian electors age years Leading to car oriented area development and unattractive PT Low PT share lead to low PT share (5%) Public Transport = Transport for the disabled
7
Roles & responsibilities (i)
Ministry: National, Regional and Local Passenger Rail Transport; Quality Contract with NSB AS for most railbound passenger traffic One line tendered in 2005 Airport Express Train Commercial Freight traffic: Open access; 6 operators Railway Reform announced 2015 Tendering all lines from 2017.
8
Roles & responsibilities (iI)
Counties (19): Regional and local bus, tram, metro and boat PT; infrastructure and operations Tendering process as the norm Exception: Quality Contracts for Oslo Tram and Metro.
9
OSLO RAIL NETWORK
10
Oslo tramways Network 131 km 6 lines
11
Oslo tramways extensions 2016-21
12
Oslo pt organisation
13
Oslo Tram Rolling Stock
SL79 ( ) - 40 units SL95 ( ) –32 units Renewal procurement process initialised 2005. Concept Choice Study 2013 – recommend replacing complete tram fleet.
14
Oslo Tram Rolling Stock
Discussions between PTA and Rolling Stock Owner about procurement responsibility for new trams June 2015 Political decision; buying 87 new trams, first delivery 2019. September 2015 Political decision: Sporveien Oslo AS (the tram operating company) given responsibility for procurement
15
trondheim Population 190.000 University City
One Tram Line: Gråkallbanen
16
Trondheim tram history
Inaugurated 1901/ 1924 From 3 to 2 lines in the 1960es From 2 to one line in 1983 Purchase of 11 new trams in 1984 building new depot in 1984 Closure of last line in 1988 Not possible to sell trams – combination gauge / car body width Reopening by enthusiasts in 1990 Operated by Veolia (now Boreal) since 2005
17
Trondheim Proposals and Challenges
New light rail system being studied from time to time Area development/ City sprawl during the previous 50 years do not favour PT - and particularly not Light Rail. 2010 Rambøll Light Rail Study
18
Bergen light rail 2010 Bergen-Nesttun 10 km 2013 Nesttun-Rådal 13 km
2016/17 Rådal-Flesland Airport Stadler Variobahn ( units) Length: 32 – 42 m Frequency 4 min peak pass / day (2014) Bergen population
19
Bergen organisation
20
Bergen future network City Centre Alignment discussions…..
21
stavanger Oil Capital of Norway Stavanger Area (Nord-Jæren):
Three municipalities; inhabitants, increasing to by 2025 Light Rail Project : Connecting 3 city centres with main work place/ industry area at Forus
22
Stavanger Light Rail project
County Masterplan1999; LRT as regional PT backbone County Council Decision 2010; prioritising LRT (as opposed to busway system). Light rail office owned by county and (3) municipalities. Alignment planning County Council Decision Dec 2012, prioritising BRT (as opposed to LRT) Light Rail Office closed March 2013. BRT under development (El?)
23
Grenland Light Rail Porsgrunn-Skien Twin Cities Population 100.000
Tram-Train idea kept warm by enthusiasts since 2006. Feasibility Study 2008 Low initiating investments (using existing tracks) LRT could support InterCity Rail development LRT recommended in regional transport plan (long term). No decisions yet. Skien Porsgrunn
24
Nedre glomma light rail
Fredrikstad-Sarpsborg Twin Cities Population Tram-Train idea by enthusiasts Feasibility Study 2014 Partly new tracks Partly using existing rail line – Mulhouse model Serving New Hospital LRT could support InterCity Rail development No decisions yet. Glommabanen
25
conclusion Norway is not very well designed for Public Transport
Except Oslo and Bergen Tramways operating well in Oslo, Trondheim and Bergen Extensions are planned in Oslo and Bergen. Stavanger will get a modern BRT LRT could be developed in more cities in the future If major PT modal share increase
26
Visit our stand! Questions? Ove Skovdahl Rejlers AS / Railconsult