Children, Youth and Families, Department ENTERPRISE PROVIDER INFORMATION CONSTITUENT SERVICES (EPICS) MASTER PROJECT Project Closeout September 26, 2018 Presenters: Irene Luettgen, CYFD CIO Melissa Barela, PMO Program Manager Raymond Vigil, ECS Information Governance, Bureau Chief
2
PROJECT GOAL Original Enterprise Provider Information Constituent Services (EPICS), a multi- year project consolidating CYFD systems to a state-of-the-art, enterprise, web-based system. Revised (Change approved at the April 2016 PCC) The EPICS project evolved from the original vision of a single comprehensive system to replace Family Automated Client Tracking System (FACTS) and standalone systems to a more modular, service- oriented approach. Over the course of the project, the EPICS scope was reduced to focus primarily on the Early Childhood Services (ECS) program.
3
PROJECT OVERVIEW Phase Deliverables In Production
Phase 1 – Provider Management Child and Adult Care Food Program (CACFP) Background Check for ECS November 2013 Phase 2 – Client Management Foundational Client and Staff components Human Resources August 2014 Phase 3 – Service Management Background Check for Human Resources and Protective Services Domestic Violence Juvenile Community Corrections Contracts Tracking November 2015 Phase 3 – Race to the Top “Am I Eligible?” Survey Phase 1 January 2017 Child Care Phase 1 Pre-K EPICS Payments through Share April 2017 Child Care Phase 2 “Am I Eligible?” Online Application and Referral Phase 2 June 2018
4
PROJECT OVERVIEW - Continued
Phase Deliverables In Production Phase 3 – Summer Food Summer Food Service Program February 2018 Phase 4 – FACTS Juvenile Justice Service (JJS) In FY16 partial C2 funding received for the first year development of this two year project. Development was suspended due to lack of funding. FY17 C-2 funding was not appropriated for year two. N/A Digital Services (Change Request approved remaining C2 funding) Adoption/Foster Dashboard Law Enforcement Portal May 2017 Investigator’s Dashboard Statewide Central Intake Dashboard June 2018 Phase 5 – FACTS Protective Services (PS) This phase was not certified as funding was not available. A FY18 C2 request for Modernization Planning, needed to support PS and JJS and develop the RFP for a PS Modular system, was not approved.
5
BENEFITS The EPICS system provides a mechanism through which we can deliver services in more streamlined and efficient ways to improve outcomes for the children and families of New Mexico. Am I Eligible “Am I Eligible?” Food Nutrition Bureau Pre-Kindergarten Supports Rural Areas After Hours Access 103 of 150 Applications Processed Sponsor Access 100% Share Integration Weeks Reduced to Days Improves Child Readiness Early Detection Teacher Pre/Post Assessments Early childhood accountability, integrity, child safety and outcomes Policy driven outcomes Child Care Services Auto-Determination Background Check Integration Sex Offender Cross Check 100% Share Integration Answer the critical questions Policy Decisions Understanding the population we serve
6
BUDGET Total Appropriations (FY12 – FY18): $19,827,334
Actual Project Cost: $19,111,731 Total Under Budget: $715,603
7
PROJECT TIMELINE
8
“All deliverables met the requirements.”
IV&V - RESPEC Performed IV&V on the EPICS Master Project from April 2016 through June 2018. All reports (10 reports) indicated GREEN for Overall Project status. “Those objectives were all met, and functionality was moved to production in a series of phases during the last two years. The project team was able to track schedule, scope and budget successfully during that extended period, although there was turnover in staff and contractor resources. This is a major accomplishment in getting these efforts completed.” “All deliverables met the requirements.” - Joel Matek, RESPEC
9
LESSONS LEARNED Activity Recommendation for Improvement
Project Planning Define the full project vision in the planning phase in order to estimate entire project costs and timeline. Project Management Establish PMO and an IT Governance framework early on in a project to improve scope, schedule, budget, change, risk and issues management. Staffing Create a formal strategy, plan and manage for effective knowledge transfer and staffing supporting transition from contractors to internal staff. Requirements Gathering Include all stakeholders earlier to reduce the need for reengineering later. Include detailed reporting requirements earlier, ensuring solutions meet minimal viable reporting needs and estimates include reporting development. IV &V Timing Initiate IV&V earlier and right-fit IV&V services to improve areas such as quality review.
10
Requesting Approval for EPICS Master Project Closeout Thank You!