Download presentation
Presentation is loading. Please wait.
1
Designers’ Manual Appendix Contents
Training Session for LGIs June 20, 2018
2
Appendix 1: AGENDAS A31 Agenda for Pre-Design Conference A32 Program Phase Meeting Agenda A34 Schematic Design Phase Meeting Agenda A36 Design Development Phase Meeting Agenda A38 Construction Document Phase Meeting Agenda
3
Appendix 1: AGENDAS (continued)
A52 Pre-Bid Conference Agenda A62 Pre-Construction Conference Agenda A64 Construction Progress Meeting Agenda A66 Substantial Completion Meeting Agenda A68 Final Inspection Meeting Agenda
4
Appendix 1: CHECKLISTS C32 Schematic Design Phase Document Checklist C34 Design Development Phase Document Checklist C36 Construction Document Phase Document Checklist C38 Bid Document Submittal Checklist
5
Appendix 1: CHECKLISTS (continued)
C42 Standard Document Instructions and Checklist C44 Stormwater Review Plan Checklist C62 Stormwater Site Audit Checklist C72 Project Closeout Checklist
6
Appendix 1: FORMS F22 Designers Agreement Information F23 Attestation F32 Designer's Cost Estimate F54 Bid Tab
7
Appendix 1: FORMS (continued)
F62 Pre-Construction Data Sheet F64 Request for Proposal F66 Proposal Recommendation F68 Report of Final Inspection
8
Appendix 1: FORMS (continued)
F72 Certificate of Substantial Completion F74 Stormwater As-Built Certification F78 Advertisement of Final Payment F79 Report of One-Year Corrective Inspection SBC-25 Project Information
9
Appendix 2: STANDARD BIDDING AND CONSTRUCTION DOCUMENTS
Invitation to Bid Instructions to Bidders Information Available to Bidders Asbestos Survey Information Available to Bidders Geotechnical Information Available to Bidders
10
Appendix 2: STANDARD DOCS (continued)
Bid Form Construction Bid Envelope Agreement Contract Bond Three Year Roof Bond
11
Appendix 2: STANDARD DOCS (continued)
General Conditions marker for AIA A General Conditions of the Contract for Construction (in AIA Contract Documents Site) Supplementary Conditions (??) Supplementary Conditions: State Wages (??) Supplementary Conditions: Federal Wages
12
Appendix 2: STANDARD DOCS (continued)
General Requirements Allowances List of Allowances Unit Prices List of Unit Prices Alternates Product Substitution Procedures Product Substitution Request Form
13
Appendix 2: STANDARD DOCS (continued)
Contract Modification Procedures Weather Delays Weather Delay Report Form for Amendment, Change Order, or Directive Form for Price Summary Form for Price of Work Form for Price of Time
14
Appendix 2: STANDARD DOCS (continued)
Retainage Escrow Initiation Schedule of Values Progress Payment Procedures Project Meetings Administrative Logs Visitor Log
15
Appendix 2: STANDARD DOCS (continued)
Construction Progress Documentation Basic Regulatory Requirements Temporary Facilities and Controls Temporary Storm Water Pollution Control Product Requirements
16
Appendix 2: STANDARD DOCS (continued)
Closeout Procedures Closeout Submittals Closeout Submittals Data Binder Receipt Report of Subcontractors and Suppliers Demonstration and Training Demonstration and Training Verification
17
Appendix 2: STANDARD DOCS (continued)
HPBr HPBr Contractor Requirements Commissioning Performance Testing Identification Form Performance Testing Procedures Form Functional Performance Test Certification
18
Appendix 2: STANDARD DOCS (continued)
Total Roofing System Warranty Twenty Year Total Metal Roofing System Warranty Mechanical & Control Systems Commissioning Sensor Point Calibration Check Sheet
19
Appendix 2: STANDARD DOCS (continued)
Terminal Box Point Calibration Check Sheet Electrical & Lighting Systems Commissioning Panelboard Check Sheet Power Circuit Check Sheet Generator Testing Procedures Form Generator Testing Findings Form Lighting Check Sheet
20
Appendix 3: SYSTEM OR CAMPUS SPECIVIC GUIDELINES AND REQUIREMENTS
Campus Design Guidelines SBC Approved Proprietary Standards IT Requirements System or Campus Storm Water Requirements, SWPPP System or Campus Commissioning Record Documents Requirements, Formats Campus Flow Charts
21
Appendix 3: PROPRIETARY SPECIFICATIONS
In general, campus specific specifications should be considered guidelines, for use by the Designer to prepare specifications to assure consistency with the design and contract documents. All proprietary items must have approval by the OSA in advance of bidding, or must be developed into competitive bid items, or as performance specifications.
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.