Download presentation
Presentation is loading. Please wait.
1
CLAS12 First Experiment Workshop Report
Latifa Elouadrhiri Jefferson Lab For more details about the workshop CLAS Collaboration Jefferson Lab June 14, 2017
2
Outline KPP – Data Calibration/Analysis Status and Plans
Engineering Run Configuration Hardware Status DAQ, Electronics and Trigger: CLAS12 Commissioning with Cosmics Online & Monitoring Slow Control Offline: Simulation, Event Reconstruction & Calibration ( See Talks by Veronique and Raffaella) Path Forward to Physics
3
KPP – Data Calibration/Analysis Status
KPP – Run Period Feb. 3 – Feb. 6, Data taking with the full detector readout: SVT, CTOF, 1 sector DC, 6 sectors FTOF & ECAL Calibration still in Progress to be completed in August (see Raffaella’s talk) KPP data processing (
4
KPP – Analysis Note in Preparation
Our Goal for the Engineering Run is to Perform quasi-online calibration Work will be done with Calcom and Ken Hicks (ACE)
5
CLAS12 Hall B Equipment MM CND FT RICH Total # of channels: 111832
Forward Detector (FD) TORUS magnet HT Cherenkov Counter Drift chamber system LT Cherenkov Counter Forward ToF System Pre-shower calorimeter E.M. calorimeter Forward Tagger RICH detector Central Detector (CD) Solenoid magnet Silicon Vertex Tracker Central Time-of-Flight Central Neutron Det. - MicroMegas Beamline Photon Tagger Shielding Cryo Target Moller polarimeter Polarized Targets MM CND FT RICH Total # of channels:
6
Detector System All baseline equipment commissioned with beam, repairs of the PCAL/EC scheduled this summer once the solenoid is installed DC gas system completed and commissioning all six sectors including trigger is underway Micromegas and SVT integration completed and commissioning is underway FT Ready for installation in July RICH being assembled at JLab and installation planned in September.
7
Target and Moller Polarimeter
Design completed all parts in hand Pressure system analysis complete Assembly scheduled in July Installation scheduled in August Moller Polarimeter Measurement of target polarization completed Data analysis in progress Still to be done: Prepare target for beam Work with helicity signals as well as exercising the whole software
8
CLAS12 DAQ/Trigger Electronics installed (and was used for KPP): ECAL, PCAL, FTOF, LTCC, DC, HTCC, CTOF, SVT Online computer cluster is 100% complete and operational Networking is 100% complete and operational DAQ software is operational Need to add scalers for Faraday Cup, helicity etc Trigger simulations and algorithm developed, cluster finding for PCAL, improved energy correction for both ECAL and PCAL (underway), HTCC, DC segment finder, DC road finder implemented Trigger simulation studies for both CLAS12 and FT triggers are underway.
9
Online Computing hardware is available for most online tasks (runtime databases, messaging system, communication with EPICS etc) There is no designated ‘online farm’ for data processing in real time, two hot-swap DAQ servers can be used as temporary solution Some work still needed for process monitoring and control, CLAS event display, data collection from different sources (DAQ, EPICS, scalers etc) Runtime database (transformation to RCDB) Slow control excellent progress on track for the engineering run
10
CLAS12 FD Full Chain Commissioning
Goals: check all drift chamber channels in 6 sectors fix bad channels, connectors measure DC efficiencies in all regions and sectors with tracks, determine DC HV & thresholds DC alignments with straight tracks (Torus field OFF) Fix all bad channels in PCAL/EC & FTOF FTOF calibration (no RF available) EC/PCAL Calibration calibration documentation for team training Detector Configuration in place All EC + PCAL operational in 6 sectors FTOF 1a, 1b operational in 6 sectors DC R1, R2, R3 operational in 6 sectors (Noise in DC R2 being fixed) DAQ & Trigger Trigger-1: Pixel trigger in EC all 6 sectors Trigger-2: Cluster trigger in EC all 6 sectors Trigger-3: DC R3 - Segment Track Trigger-4: DC R1-R2-R3 full track DAQ readout, all sectors, all channels
11
DC Noise Work (from B.Raydo)
Turbo pump was moved (was already planned work luckily) Dramatic improvement on noise see next slide for noise rates before & after R2 DCRB modules were modified to improve power supply noise return path see next slides for noise rates before & after Currently can run at -45mV thresholds for R2 (lower for R1 & R3) R1 & R3 DCRB modules are planned for modified in June Since R1 & R3 DCRB contribute noise to R2 we expect a noticeable noise improvement on R2 after all DCRB modification complete See final slides which shows expected R2 noise when all DCRB modification complete (R1 and R3 crates were off for this measurement
12
DC-R2 Noise Before Improvement
13
Expected DC-R2 Noise After Improvement
14
Preparations for Fall Runs
Complete KPP data calibration Cosmic ray test with full complement of forward detectors Checkout all 18 drift chambers (all 6 sectors) for noise levels Measure tracking efficiencies for minimum ionizing particles Test special triggers for engineering run and physics runs Calorimeter pixel triggers for cosmic ray calibration of calorimeters and 6/5 superlayer reconstruction Tracking triggers in DCs (DCRB) and hits in FTOF, PCAL and EC Train reconstruction software on real events in all 6 sectors and 3 regions Plan on internal “Ready for Science” review in September Status of all detectors, calibrations, reconstruction, particle ID, … Full event reconstruction in FD and CD and correlations Acceptances for several reactions, impact of background occupancies “Online” calibration procedures Documentation Identified lead teams 11/9/2018
15
Analysis Committee of Experts (ACE)
ACE members: K. Hicks (chair), D. Ireland, K. Joo, S.Kuhn, S. Niccolai, E. Pasyuk, L. Weinstein Goals of the committee as defined by CLAS chair, (Formed on the recommendation of the common tools committee) Guide the development of analysis algorithms (after calibrations) PID, momentum corrections, backgrounds, fiducial cuts, etc. Higher level analysis: kinematic fitting, PWA (if applicable) Standardize the algorithms and software Etc. Draft Report of the ACE Committee completed: the document outlines the recommended procedures for data analysis from the CLAS12 detector. Will work in collaborative effort with Software Clacom and ACE to prepare for the September science review
16
Timeline TASK 2016 2017 SIMULATION RECONSTRUCTION CALIBRATION
FD & Trigger commissioning in progress Full Chain test With cosmics TASK 2016 2017 Oct. Nov. Dec. Jan. Feb. Mar. Apr. May June July Aug. Sept SIMULATION RECONSTRUCTION CALIBRATION EXP. SCHEDULE New release with full central detector Ready for Physics Ready for KPP Hall B Science review KPP Run Engineering Run Second Calibration Challenge First Calibration Challenge
17
Mailing list clas12_first_exp & biweekly meeting, Wednesdays at 8:30
Looking forward to successful engineering run and the start of physics with CLAS12! Mailing list clas12_first_exp & biweekly meeting, Wednesdays at 8:30
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.