Healthwatch Portsmouth Board meeting 17 October 2018
Presentation by Mark Young, Head of Estates, Solent NHS Trust
3
Portsmouth Community Care Estates Plans
Mark Young Portsmouth Community Care Estates Plans Head of Estates 17 october 2018 Phase 2 Update
4
The Portsmouth Community Care Programme was conceived in 2014
Its purpose was to: “Remodel the accommodation at St Mary’s and St James’ health campuses in Portsmouth into a long term and sustainable configuration, whilst modernising and improving patient care by moving resources away from maintaining expensive and outdated real estate into front line patient care.” An Outline Business Case (OBC) for the programme as a whole was approved in March 2014 This envisaged the works in two phases The Final Business Case (FBC) for Phase 1 was approved in July 2014 Phase 1 was completed July 2015 – on time and within budget. The Phase 2 FBC was approved in November 2016 STP Funding for Phase 2 was granted in April 2018 Following Mobilisation, Phase 2 works started in July 2018 Phase 2 is on track for completion in October 2019. Background & Overview
5
Phase 1: Overview Key enabler for Phase 2 Cost £4m
Released some land at St James for disposal, with a capital receipt of £6m. Included a large number of service relocations away from St James to facilitate Phase 2 Utilised underused space within the Solent Estate Did not include major capital works such as that in Phase 2 Did not realise major revenue savings as voids at St Mary’s and St James not addressed Phase 1: Overview
6
Child Development Centre
Langstone Kestrel St James’ Main Building Turner The Limes The Orchards Kite Baytrees Falcon Hse Fairoak Yew House The Beeches Child Development Centre Legend Phase 1 Disposals Retained at end Phase 1 Hatched area sold under Phase 1 Phase 1: Overview
7
Phase 1: Remaining Void on Completion
St James – total Voids = 6,875 m2 St Mary’s B Block – total voids = 1,960 m2 Phase 1: Remaining Void on Completion
8
Phase 2: Overview Phase 2 Headline Capital Cost £10.3m
Funded by STP bid, awarded April 2018 Programme Start April 2018 Programme Completion October 2019 Benefits of Phase 2 Capital receipt for NHS Property Services through the sale of the St James Site Elimination of void space at St Mary’s Community Health Campus Estimated revenue savings of c£3m per annum for the Health System in Portsmouth The creation of state of the art, modern consulting facilities that will serve the local community for the next 20 years Phase 2: Overview
9
Phase 2: Overview Phase 2 Disposal Projects 5 Key Dependencies 18
The Objective of Phase 2 is to vacate the St James site in order to allow its future disposal by NHSPS to realise a capital receipt for NHSPS and revenue savings for the CCG and the Trust. Solent Retain Langstone Kestrel St James’ Main Building Turner The Limes The Orchards Kite Baytrees Falcon Hse Projects Key Dependencies 18 Phase 2 Disposal Phase 2: Overview
10
Phase 2: Major Projects Project Description Capital Sum £k (Gross)
Block B Refurbishment of Ground, First and Second Floors (1F and 2F currently void) of Block B at St Mary’s to create state of the art bookable consulting rooms and supporting hot desking to accommodate services being relocated away from the St James Site. 8,119 Block C Refurbishment of existing void space within Block C at St Mary’s to create a training facilities for the Learning and Development Team who currently deliver training in the St James Main building. 1,506 Junior Doctors Re-provision of the Juniors Doctor’s Mess located in the St James Main Building. Completed Nov 2017 St James Infrastructure and ICT Infrastructure and ICT modifications to enable the buildings which will remain at St James(the Limes, the Orchards and Falcon House), to function independently of the St James main building 1,169 Wayfinding Upgrade the existing site signage and Wayfinding to reflect the changes to the estate identified above. 70 Phase 2: Major Projects
11
Phase 2: Further Projects & Dependencies
Title Commentary 1. Relocation of PRRT – Rapid Response Team Included within Block B 2. Civic Reconfig Brunel 2nd Floor Portsmouth City Council project 3. Civic Reconfig Brunel 3rd Floor 4. Catering Central Production Unit sits in St James Main Building 6. Kestrel relocation – PCC Project 7. Medicines Management Included within St James Works – relocate to Orchards 8. Relocate OPMH 10 pers Admin team from St James 9. Wessex Deanery – part of Block C Scheme Included within Block C 10. Relocate ICT out of Block C to Pompey Centre 11. Room Booking – inc in Block B Scope 12. Falcon House Infrastructure – inc in St James Inf Included within St James Infrastructure and ICT 13. Domestics and Porters Scoping on going – relocate to Orchards or Limes 14. Security Main security hub relocates to St Marys 15. Car Parking In line with new Trust Parking Policy 16. St Marys Facilities Office 17. Telephony Migration Complete 18. Other Non Solent Occupants NHS Property Services to manage 19. Kestrel Data Centre – non Solent Servers Solent to provide coordination and facilitation Phase 2: Further Projects & Dependencies
12
Phase 2: Further Programme
13
Phase 2: Ground Floor Views
Ground Floor Waiting External Entrance View Phase 2: Ground Floor Views
14
Phase 2: First Floor Views
First Floor Waiting Phase 2: First Floor Views
15
Phase 2: Second Floor Views
Second Floor Office Space Phase 2: Second Floor Views
16
Phase 2 & Future: Integrated Systems
Second Floor Office Space Access Control Multi-site Printing Standardised Design Flexible Storage Pro-active Building Management Phase 2 & Future: Integrated Systems