Download presentation
Presentation is loading. Please wait.
1
Decision making and Organization Management
CPM/PERT Critical Path Method Project Evaluation Review Technique Pongsa Pornchaiwiseskul, Faculty of Economics, Chulalongkorn University Pongsa Pornchaiwiseskul, Faculty of Economics, Chulalongkorn University
2
Decision making and Organization Management
CPM/PERT Tools for Project Management Minimum Project Duration Scheduling Time-cost Trade-offs Resoruce Leveling (not to be discussed) Pongsa Pornchaiwiseskul, Faculty of Economics, Chulalongkorn University Pongsa Pornchaiwiseskul, Faculty of Economics, Chulalongkorn University
3
Decision making and Organization Management
Critical Path Method Network-based (to be seen why) An LP Problem but much more simple that it can be solved by hand Deterministic (all the parameters are known or assumed with certainty) Pongsa Pornchaiwiseskul, Faculty of Economics, Chulalongkorn University Pongsa Pornchaiwiseskul, Faculty of Economics, Chulalongkorn University
4
Project Evaluation Review Technique
Decision making and Organization Management Project Evaluation Review Technique Extension of CPM Probability Concept is added to CPM Good for a project which has never been done before. Some uncertainty involved Pongsa Pornchaiwiseskul, Faculty of Economics, Chulalongkorn University Pongsa Pornchaiwiseskul, Faculty of Economics, Chulalongkorn University
5
Decision making and Organization Management
PROJECTS There are many activities. Each activity takes time. Some activities (successors) cannot start until the other activities (predecessors) finish. Can be represented by a directed network Examples are construction, scientific project and thesis Pongsa Pornchaiwiseskul, Faculty of Economics, Chulalongkorn University Pongsa Pornchaiwiseskul, Faculty of Economics, Chulalongkorn University
6
Activity-on-Node (AoN)
Decision making and Organization Management Activity-on-Node (AoN) Act. A Act. B Act. C Act. D Pongsa Pornchaiwiseskul, Faculty of Economics, Chulalongkorn University Pongsa Pornchaiwiseskul, Faculty of Economics, Chulalongkorn University
7
Activity-on-Arc (AoA)
Decision making and Organization Management Activity-on-Arc (AoA) activity A activity B activity C S F activity D Pongsa Pornchaiwiseskul, Faculty of Economics, Chulalongkorn University Pongsa Pornchaiwiseskul, Faculty of Economics, Chulalongkorn University
8
Decision making and Organization Management
EXAMPLE OF CPM Activity Time Predecessors DIG FOUND DIG POURB FOUND JOISTS FOUND WALLS FOUND RAFTERS WALLS, POURB FLOOR JOISTS ROUGH FLOOR ROOF RAFTERS, JOISTS FINISH ROUGH, ROOF SCAPE POURB, WALLS Pongsa Pornchaiwiseskul, Faculty of Economics, Chulalongkorn University Pongsa Pornchaiwiseskul, Faculty of Economics, Chulalongkorn University
9
MINIMUM PROJECT DURATION
Decision making and Organization Management MINIMUM PROJECT DURATION Network Method by hand by computer programs,e.g., Microsoft Project (not to be discussed) Solving its corresponding LP problem by computer or by hand Pongsa Pornchaiwiseskul, Faculty of Economics, Chulalongkorn University Pongsa Pornchaiwiseskul, Faculty of Economics, Chulalongkorn University
10
Decision making and Organization Management
Network Method by Hand Determine Longest route between start and end Performed in two steps. Forward Pass(from start to end) Backward Pass (from end back to start) Pongsa Pornchaiwiseskul, Faculty of Economics, Chulalongkorn University Pongsa Pornchaiwiseskul, Faculty of Economics, Chulalongkorn University
11
Decision making and Organization Management
FORWARD PASS (1) The project starts at time zero (2) Every starting activity has an Earliest Start(ES) at zero (3) Earliest Finish(EF) of an activity is ES + activity time EFj = ESj + Dj (4) For an activity j w/ predecessors, ESj = max{ its predecessors’ EF} Pongsa Pornchaiwiseskul, Faculty of Economics, Chulalongkorn University Pongsa Pornchaiwiseskul, Faculty of Economics, Chulalongkorn University
12
Decision making and Organization Management
FORWARD PASS (cont’d) (5) The minimum project duration (T) T = max{EF of activities w/o successors} Note that 1) The project can earliest finish at time T 2) It can finish later than time T but not before Pongsa Pornchaiwiseskul, Faculty of Economics, Chulalongkorn University Pongsa Pornchaiwiseskul, Faculty of Economics, Chulalongkorn University
13
Decision making and Organization Management
BACKWARD PASS (1) The project finishes at time T (2) All the activities w/o successors can Latest Finish(LF) at time T. Their LF = T (3) Latest Start(LS) of an activity j is its LF minus activity duration (D),I.e., LSj = LFj - Dj (4) LF of an activity w/ successors = min {LS of its successors} Pongsa Pornchaiwiseskul, Faculty of Economics, Chulalongkorn University Pongsa Pornchaiwiseskul, Faculty of Economics, Chulalongkorn University
14
Decision making and Organization Management
AoN Representation JOISTS(3) FLOOR(4) ROUGH(6) DIG(3) FOUND(4) POURB(2) RAFTERS(3) ROOF(7) FINISH(5) WALLS(5) SCAPE(2) Pongsa Pornchaiwiseskul, Faculty of Economics, Chulalongkorn University Pongsa Pornchaiwiseskul, Faculty of Economics, Chulalongkorn University
15
Decision making and Organization Management
AON Legend ES EF ACTIVITY (D) LS LF Pongsa Pornchaiwiseskul, Faculty of Economics, Chulalongkorn University Pongsa Pornchaiwiseskul, Faculty of Economics, Chulalongkorn University
16
Decision making and Organization Management
AoN Representation 7 10 10 14 14 20 JOISTS(3) FLOOR(4) ROUGH(6) 9 12 12 16 16 22 3 3 7 7 9 12 15 15 22 22 27 DIG(3) FOUND(4) POURB(2) RAFTERS(3) ROOF(7) FINISH(5) 3 3 7 10 12 12 15 15 22 22 27 7 12 12 14 WALLS(5) SCAPE(2) 7 12 25 27 Pongsa Pornchaiwiseskul, Faculty of Economics, Chulalongkorn University Pongsa Pornchaiwiseskul, Faculty of Economics, Chulalongkorn University
17
Decision making and Organization Management
AoA Representation FLOOR 4 ROUGH 6 D F H JOISTS 3 FINSIH 5 ROOF 7 DIG 3 FOUND 4 A B C G I POURB 2 RAFTERS 3 WALLS 5 SCAPE 2 E Pongsa Pornchaiwiseskul, Faculty of Economics, Chulalongkorn University Pongsa Pornchaiwiseskul, Faculty of Economics, Chulalongkorn University
18
Decision making and Organization Management
RESULT Activity Time Predecessors ES EF LS LF DIG FOUND DIG POURB FOUND JOISTS FOUND WALLS FOUND RAFTERS WALLS, POURB FLOOR JOISTS ROUGH FLOOR ROOF RAFTERS, JOISTS FINISH ROUGH, ROOF SCAPE POURB, WALLS Pongsa Pornchaiwiseskul, Faculty of Economics, Chulalongkorn University Pongsa Pornchaiwiseskul, Faculty of Economics, Chulalongkorn University
19
Decision making and Organization Management
LP Representation MAX 3DIG+4FOUND+2POURB+3JOISTS+5WALLS +3RAFTERS+4FLOOR+6ROUGH+7ROOF+5FINISH +2SCAPE SUBJECT TO 2) DIG <=1 3) FOUND - DIG = 0 4) JOISTS + POURB + WALLS - FOUND =0 Pongsa Pornchaiwiseskul, Faculty of Economics, Chulalongkorn University Pongsa Pornchaiwiseskul, Faculty of Economics, Chulalongkorn University
20
LP Representation(cont’d)
Decision making and Organization Management LP Representation(cont’d) 5) FLOOR + DUMMY - JOISTS =0 6) RAFTERS + SCAPE - POURB - WALLS = 0 7) ROUGH - FLOOR = 0 8) ROOF - RAFTERS - DUMMY = 0 9) FINISH - ROUGH - ROOF = 0 END Pongsa Pornchaiwiseskul, Faculty of Economics, Chulalongkorn University Pongsa Pornchaiwiseskul, Faculty of Economics, Chulalongkorn University
21
Decision making and Organization Management
SCHEDULING WITH BAR CHART Activity DIG FOUND POURB JOISTS WALLS RAFTERS FLOOR ROUGH ROOF FINISH SCAPE 5 10 15 20 25 Pongsa Pornchaiwiseskul, Faculty of Economics, Chulalongkorn University Pongsa Pornchaiwiseskul, Faculty of Economics, Chulalongkorn University
22
Decision making and Organization Management
CRITICAL ACTIVITIES activities with zero slack. slack = LS -ES or = LF - EF critical activities form a Critical Path Pongsa Pornchaiwiseskul, Faculty of Economics, Chulalongkorn University Pongsa Pornchaiwiseskul, Faculty of Economics, Chulalongkorn University
23
Decision making and Organization Management
TIME COST TRADE-OFFS Choose to shorten the critical activity with lowest cost until the activity becomes non-critical. Pongsa Pornchaiwiseskul, Faculty of Economics, Chulalongkorn University Pongsa Pornchaiwiseskul, Faculty of Economics, Chulalongkorn University
24
Decision making and Organization Management
CRASHING THE PROJECT Decrease the project duration by shortening the activities. Activity Normal Duration Max. Crash $/day DIG JOIST WALLS FINISH Pongsa Pornchaiwiseskul, Faculty of Economics, Chulalongkorn University Pongsa Pornchaiwiseskul, Faculty of Economics, Chulalongkorn University
25
Decision making and Organization Management
UNCERTAINTY Activity duration could be uncertain A - optimistic time estimate B - pessimistic time estimate M - most likely time estimate (mode) Pongsa Pornchaiwiseskul, Faculty of Economics, Chulalongkorn University Pongsa Pornchaiwiseskul, Faculty of Economics, Chulalongkorn University
26
Decision making and Organization Management
DURATION ESTIMATES A M B time Mean D = (A+4M+B)/6 Standard Deviation SD = (B-A)/6 Pongsa Pornchaiwiseskul, Faculty of Economics, Chulalongkorn University Pongsa Pornchaiwiseskul, Faculty of Economics, Chulalongkorn University
27
Decision making and Organization Management
PERT Method Do CPM using its Mean D for the duration of each activity CPM yields the Mean project duration The variance of project duration T Var(T) = sum of Var(D) for all the critical activities in a CP Pongsa Pornchaiwiseskul, Faculty of Economics, Chulalongkorn University Pongsa Pornchaiwiseskul, Faculty of Economics, Chulalongkorn University
28
Decision making and Organization Management
RESULT Activity Time Predecessors ES EF LS LF DIG FOUND DIG POURB FOUND JOISTS FOUND WALLS FOUND RAFTERS WALLS, POURB FLOOR JOISTS ROUGH FLOOR ROOF RAFTERS, JOISTS FINISH ROUGH, ROOF SCAPE POURB, WALLS Pongsa Pornchaiwiseskul, Faculty of Economics, Chulalongkorn University Pongsa Pornchaiwiseskul, Faculty of Economics, Chulalongkorn University
Similar presentations
© 2024 SlidePlayer.com. Inc.
All rights reserved.