1 3D Project Status Report
Maria Girone, CERN IT on behalf of the LCG 3D project LHCC Comprehensive Review 19th-20th Nov 2007

2 Introduction Set up a distributed database infrastructure for the WLCG (according to the WLGC MoU) RAC as building-block architecture Several 8-node clusters at Tier0 Typically 2-node clusters at Tier1 Oracle streams replication used to form a database backbone between. In production since April ‘07 Tier0 and 10 Tier1 sites ATLAS and LHCb Online and offline at Tier0 ATLAS, CMS and LHCb Frontier/SQUID from Fermilab for distributing and caching database data via a web protocol is used by CMS Database services listed among the critical services by the experiments

3 Building Block- Database Clusters
Tier 0: all networking and storage redundant Scalability and high availability achieved Storage and CPU scale independently Maintenance operations w/o down-time!

4 Oracle Streams ASGC TRIUMF New or updated data are detected and queued for transmission to destination databases Database changes captured from the redo-log and propagated asynchronously as Logical Change Records (LCRs) All changes are queued until successful application at all destinations need to control change rate at the source in order to minimise the replication latency 2GB/day user data to Tier 1 can be sustained with the current DB setups

5 Downstream Capture & Network Optimisations
Downstream Database Capture to de-couple Tier0 production databases from Tier1 or network problems is in place for ATLAS and LHCb TCP and Oracle protocol optimisations yielded significant throughput improvements (almost factor 10)

6 Frontier/Squid Numerous significant performance improvements since CSA’06 experiment data model frontier client/server software CORAL integration CMS is confident that possible cache coherency issues can be avoided by Cache expiration windows for data and meta-data Policy implemented by the client applications Successfully used also in CSA’07 database queries encoded as URL requests and the corresponding query results transferred as html pages. The use of http and html enables the use of standard web cache servers such as SQUID Experiment data model resulting sometimes in too many queries addressed but CMS changing the data model Problems seen recently for POOL-ORA caching container meta-data

7 Streams Replication Operation
Streams procedures included in the Oracle Tier0 physics database service team Optimized the redo log retention on downstream database to allow for sufficient re- synchronisation window without recall from tape (for 5 days) Preparing a review of the most recurrent problems for the WLCG Service Reliability Workshop, Nov 2007 Will be the input for further automation of service procedures

8 Some Issues Several bugs reported to Oracle fixed or being fixed
CERN openlab has set an excellent ground! Some user-defined types not supported by streams Reformatting is done with filtering rules LFC has been hit by a known Oracle bug as it was running on on a older instant client version Syncronization with the AA instant client established Set up read-only replicas on other 5 sites together with code change to support user ACLs Automate more the split-merge procedure when one site has to be dropped/re-syncronized Progress in Oracle 11g but we need a stop-gap solution Implement failover for the downstream capture component ACL

9 Streams problems Workarounds found for all the open bugs:
Capture process is aborted with error ORA-01280: Fatal LogMiner Fixed in patches and related to the capture process and the logminer Bug SQL apply degrades with larger transactions Fixed applying patch Bug STREAMS 5000 LCR limit is causing unnecessary FLOW CONTROL at apply site Fixed applying patch Bug recyclebin=on; after child table dropped:ORA on parent Metalink note Fixed on and 11g APPLY gets stuck: APPLY SERVER WAITING FOR EVENT Generic performance issue on RAC Fixed by applying patches for the fix for <bug: > and One off/Patch of OEM agent blocks Streams processes Fixed applying patch Workarounds found for all the open bugs: ORA-600 [KWQBMCRCPTS101] after dropping Propagation job ORA after table is dropped when there are two streams setups between the same source and destination databases ORA-00600: [KWQPCBK179], memory leak from propagation job Observed after applying the fix patch For the non-fixed problems: ORA-600 [KWQBMCRCPTS101] after dropping Propagation job ORA after table is dropped when there are two streams setups between the same source and destination databases we have developed and implemented a workaround for each problem ORA-00600: [KWQPCBK179], memory leak from propagation job this is not a critical problem 9

10 Service Levels and Policies
DB Service level according to WLCG MoU need more production experience to confirm manpower coverage at all T1 sites piquet service being set-up at Tier 0 to replace existing 24x7 (best effort) service streams interventions for now 8x5 Criticality of this service rated by most experiments (ATLAS, CMS and LHCb) as “very high” or “high” Proposals from CERN Tier 0 have been accepted also by the collaborating Tier 1 sites Backup and Recovery RMAN based backups mandatory, data retention period 1 month security patch frequency and application procedure database software upgrade procedure patch validation window

11 Database & Streams Monitoring
Monitoring and diagnostics has been extended and integrated in the experiments’ dashboards Weekly/monthly database and replication performance summary has been added extensive data and plots about replication activity, server usage, server availability available form the 3D wiki site (html or pdf) summary plot with LCR rates during last week is show on the 3D home page and could be referenced/included into other dashboard pages Complemented by weekly Tier 0 database usage reports which are in use already since more than one year

12 Integration with WLCG Procedures and Tools
3D monitoring and alerting has been integrated with WLCG procedures and tools dedicated workshop at SARA in March focussing on this Interventions announced according to the established WLCG procedures eg EGEE broadcasts, GOCDB entries To help reporting to the various coordination meetings we collect all 3D intervention plans also on the 3D wiki Web based registration will be replaced as soon as a common intervention registry is in production

13 Intervention & Streams Reports
A factor 5 improvement in apply speed by tuning of filtering rules

14 Tier 1 DB Scalability Tests
The experiments have started to evaluate/confirm also the estimated size of the server resources at Tier 1 number of DB nodes CPUs memory, network and storage configuration Need realistic work-load which now becomes available as experiment s/w frameworks approach complete coverage of their detectors ATLAS conducted two larger tests with ATHENA jobs against IN2P3 (shared solaris server) and CNAF (Linux) Total throughput of several thousand jobs/h achieved with some 50 concurrent test jobs per Tier 1 LHCb s/w framework integration done and scalability tests starting as well Lower throughput requirements assumed than for ATLAS Tests with several hundred concurrent jobs in progress

15 Database Resource Requests
Experiment resource requests for T1 unchanged since more than one year 2 (3) node DB cluster for LHCb (ATLAS) fibre channel based shared storage 2 squid nodes for CMS standard worker node with local storage Setup shown to sustain replication throughput required for conditions data (1.7 GB/d ATLAS) ATLAS has switched to production with the Tier1 sites LHCb requested read-only LFC replicas at all 6 Tier1 sites as for conditions Successful replication tests for LFC between CERN and CNAF Updated requests for LHC startup have been collected at the WLCG workshop at CHEP’07 No major h/w extension requested at that time

16 Online-Offline Replication
Oracle Streams used by ATLAS, CMS and LHCb Joint effort with ATLAS on replication of PVSS data between online and offline required to allow detector groups to analyse detailed PVSS logs without adverse impact on online database Significantly higher rates required than for COOL based conditions, which have been confirmed in extensive tests some 6 GB of user data per day Oracle Streams seems an appropriate technology also for this area

17 Backup & Recovery Exercise
Organised a dedicated database workshop at CNAF in June 2007 on recovery exercise show that database implementation and procedures at each site are working show that coordination and re-synchronisation after a site recovery works show that replication procedures continue unaffected while some other sites are under recovery Exercise well appreciated by all participants several set-up problems haven been resolved during this hands on activity with all sites present six sites have now successfully completed a full local recovery and re-synchronisation remaining sites will be scheduled shortly after the Service Reliability Workshop

18 More Details LCG 3D wiki Recent LCG 3D workshops
interventions, performance summaries Recent LCG 3D workshops Monitoring and Service Procedures SARA Backup and Recovery CNAF LGC Service Reliability Workshop w=standard&confId=20080

19 Approved by the MB on 13.03.07 TAGS at volunteer Tier-1 sites
(BNL, TRIUMF, ...)

20 Updated Request from ATLAS
Not yet approved. May need funding discussion ATLAS provides more info at Year Total (TB) TAGS (TB) COOL (TB) PVSS etc. (TB) 2007 6.4 1.0 0.4 5 2008 14.5 5.6 0.9 8 2009 27.3 13.7 1.6 12 2010 46.8 27.5 2.9 16.4 20

21 Approved by the MB on

22 Summary The LCG 3D project has setup a world-wide distributed database infrastructure for LHC Close collaboration between LHC experiments and LCG sites with more than 100 DB nodes at CERN + several tens of nodes at Tier 1 sites this is one of the largest distributed database deployments world-wide Large scale experiment tests have validated the experiment resource requests implemented by the sites Backup & recovery tests have been performed to validate the operational procedures for error recovery Regular monitoring of the database and streams performance is available to the experiments and sites Tier 0+1 ready for experiment ramp-up to LHC production. Next steps: Replication of ATLAS Muon calibrations back to CERN Test as part of CCRC’08 Started testing 11gR1 features. Production deployment plan for 11gR2 by end of 2008