1 Southwest LRT Project Craig Lamothe, AICP Senior Project Manager
2011 MN State Planning Conference September 29, 2011

2 Twin Cities Transit System Profile
Today’s Topics Twin Cities Transit System Profile Previous Regional New Starts Projects Hiawatha LRT Northstar Commuter Rail Central Corridor LRT Federal New Starts Program Primer Southwest LRT Project Alternative Analysis Phase Recap Preliminary Engineering Phase Preview

3 Twin Cities Ridership

4 Metro Transit Ridership (2010)

5 Peer Comparison: 2009 System Ridership

6 Peer Comparison: Ridership per Capita

7 Buses Artic Buses: 163 Standard 40’ Buses: 735 Hybrid Buses: 97
Metro Transit Fleet Buses Artic Buses: 163 Standard 40’ Buses: 735 Hybrid Buses: 97 Light Rail 27 cars Commuter Rail 18 Passenger Cars 6 Locomotives

8 2030 Transitway System

9 Project Cost: $715.3 million
Hiawatha LRT (Blue Line) 12 miles 19 Stations Project Cost: $715.3 million 2011 Annual Operating Budget: $26.7 million Avg. Weekday Ridership (Aug ‘11): 35,069 2010 Total Annual Ridership: 10,500,000

10 Project Cost: $320 million 2011 Annual Operating Budget: $17.0 million
Northstar Commuter Rail 40 miles 6 stations Project Cost: $320 million 2011 Annual Operating Budget: $17.0 million Avg. Weekday Ridership (Aug. ‘11) 2,696 2010 Total Annual Ridership: 710,400

11 2015 Est. Operating budget: $25.4 million 18 new stations
Central Corridor LRT (Green Line) 11 miles 2015 Est. Operating budget: $25.4 million 18 new stations Projected weekday ridership: Over 40,000 by 2030 $957 million

12 New Starts Overview Systems Planning Alternatives Analysis Select LPA,
Full Funding Grant Agreement Alternatives Analysis Final Design Commitment of Non-Federal Funding, Construction Plans, ROW Acquisition, Before-After Data Collection Plan, FTA Evaluation for FFGA, Begin Negotiations Proj Mgmt Over-sight Construction Preliminary Engineering Complete NEPA Process Refinement of Financial Plan Select LPA, MPO Action PMP FTA Decision on entry into PE FTA Decision on entry into FD Systems Planning

13 Evaluate the mode and alignment options for a particular corridor
Alternatives Analysis (AA) Phase Evaluate the mode and alignment options for a particular corridor Benefits, costs and impacts of transportation options Complete with the selection of the locally preferred alternative (LPA) and adoption of the LPA into the region’s long range transportation plan

14 Consider design options to refine LPA and complete the NEPA process
Preliminary Engineering (PE) Phase Consider design options to refine LPA and complete the NEPA process Hone the estimates of project cost, benefits, impacts and schedule Finalize management plans Demonstrate technical capabilities to develop the project Commit local funding sources

15 Final Design (FD) Phase
Prepare final construction plans, contract packages, detailed specifications and bid documents

16 New Starts Evaluation Process

17 Peer “New Starts” Projects
July 2011 Status P N Pending FFGA New FFGA E Existing FFGA E Seattle, WA St. Paul- Minneapolis N Portland, OR E Hartford, CT P Sacramento, CA New York, NY E E Salt Lake City, UT P E N. Virginia-Dulles, VA E P San Francisco N E E Denver, CO N San Jose, CA Dallas, TX E E P Houston, TX Orlando, FL Honolulu, HI P P

18 Peer “New Starts” PE Projects
September 2011 Status Minneapolis,- St. Paul, MN Vancouver, WA Pawtucket, RI Portland, OR Sacramento, CA San Jose, CA Salt Lake City, UT Los Angeles, CA Charlotte, NC Los Angeles, CA Houston, TX Honolulu, HI

19 SWLRT: Historical Timeline
Alternatives Analysis LPA Selected LPA Amended into TPP MC requests to Enter PE FTA approves Entry into PE Nov. 4, 2009 May 26, 2010 Aug. 31, 2010 Sept. 2, 2011

20 SWLRT: AA Phase Transit Technology Review
Identification of Alignments and Stations Initial Set of Alternatives No Build Enhanced Bus Build Alternatives (BRT & LRT)

21 Est. Project Cost: $1.25 billion
SWLRT: Locally Preferred Alternative (LPA) 15 miles 17 new stations Est. Project Cost: $1.25 billion

22 $30.6M in Local Funds Committed to Date
SWLRT: Project Budget $375 million $625 million $125 million $125 million $30.6M in Local Funds Committed to Date

23 Preliminary Engineering Final Design Construction Revenue Operations
SWLRT: Anticipated Schedule Preliminary Engineering Final Design Construction Revenue Operations 2018

24 Procurement of Engineering Services Complete 30% Design
SWLRT: PE Phase Procurement of Engineering Services Complete 30% Design Procurement of Environmental Services Complete Final Environmental Impact Statement Establishment of a Project Office Secure Municipal Consent from 5 Cities

25 For Further Information and Updates
Mark Fuhrmann, Program Director – New Starts Rail Projects Chris Weyer, Project Director - Southwest LRT