Download presentation
Presentation is loading. Please wait.
Published byCharleen Alexander Modified over 6 years ago
1
Pinole-Hercules Water Pollution Control Plant Upgrade Project
Update to Pinole-Hercules Wastewater Subcommittee March 2, 2017 Pinole-Hercules Water Pollution Control Plant Upgrade Project
2
Headworks and Grit Removal
The base and walls of the new headworks structure have been poured and the synthetic coating is being installed and sealed. The grit structure base is completed and the wall elevations are being formed and poured. Work for these structures is 32% complete
3
Influent Pipe The influent sewer from both Pinole and Hercules have been excavated and are under construction.
4
Electrical Work in Progress
The Electrical building slab has been poured and is ready for masonry wall construction to begin
5
The solids handling facilities
The walls for the new solids handing building and sludge thickener are now being constructed.
6
Site prior to start of construction
7
Project south end in February 2017
Influent sewer New electrical building Grit structure Headworks structure
8
Project north end in February 2017
Solids handling facility Gravity sludge thickener
9
Original schedule and cost breakdown
Substantial Completion Final Completion
10
Progress/Payments Billings for Work through January 2017 total $10,409,656
11
Baseline Overview of Schedule Work Activities
Pre-construction Construction Permits Headworks and Solids Handling Secondary Treatment Secondary Clarifier 1 and Chlorine Contact Basin Facility Start-up Submit Shutdown Requests Civil/Site Work, Yard pipe, Ductbank Temporary Bypass Piping and Pumping Temporary Bypass Piping and Pumping Testing and Commissioning Prepare Submittals Headworks and Grit Facilities Aeration Basins Yard Piping and Ductbanks Demobilization period Submittal Review and Approval Primary Clarifiers 1 & 2 RAS/WAS Pumping Station Chlorine Contact Basin Material Fabrication and Delivery Electrical Building Secondary Clarifier 2 Public Works Building Outfall Pipeline Blower Building Sodium Hydroxide Area Influent Sewer Primary Clarifier 3 Digester Gas Burner Solids Handling Facility Maintenance Building Secondary Clarifier 1 Testing and Commissioning Testing and Commissioning Miscellaneous site work
12
Current Status of Work Activities
Pre-construction Construction Permits Headworks and Solids Handling Secondary Treatment Secondary Clarifier 1 and Chlorine Contact Basin Facility Start-up Submit Shutdown Requests Civil/Site Work, Yard pipe, Ductbank Temporary Bypass Piping and Pumping Temporary Bypass Piping and Pumping Testing and Commissioning Prepare Submittals Headworks and Grit Facilities Aeration Basins Yard Piping and Ductbanks Demobilization period Submittal Review and Approval Electrical Building RAS/WAS Pumping Station Chlorine Contact Basin Material Fabrication and Delivery Outfall Pipeline Secondary Clarifier 2 Public Works Building Influent Sewer Blower Building Sodium Hydroxide Area Solids Handling Facility Primary Clarifier 3 Digester Gas Burner Work in Progress Primary Clarifiers 1 & 2 Completed Testing and Commissioning Maintenance Building Secondary Clarifier 1 Testing and Commissioning Miscellaneous site work
13
Change Orders Executed To Date
Number Subject Cost 1 Temporary Public Restrooms and Wash Station during construction $ 21,271.00 2 New AC Road along the Northeast Side of the Plant for Continued County Access $ 32,363.00 3 Credit for Deleting Two Duck Bill Check Valves at Aeration Basins $(12,018.00) 4 Revised Davis Bacon wage determination $ 5 Concrete Scanning for Existing Primary Clarifiers $ 2,320.00 6 Headworks - Concrete Fillets and Fills Modifications $ 22,893.60 7 RTU Modifications to Control Plant Instrumentation $ 21,621.00 8 Replace Carbon Steel Low Pressure Air Piping with Stainless Steel $ 77,431.00 9 Install Polymer System Progressive Cavity Pumps in-Lieu of Specified Peristaltic Pumps $ 3,299.00 10 Relocate Headworks and Ferric Chloride Storage Facilities 11 Re-route natural gas line around MH-1 $ (1,705.00) TOTAL CHANGE ORDERS TO DATE $167,475.60 Executed change orders total 1.6 percent of work completed to date
14
Potential Change Order Requests Currently In Review
Number Subject 1 Demolish and Replace Approximately 50 feet of Existing Asbestos Cement 24-inch Effluent line 2 Reroute Existing Utilities at Surge Tank 3 Remove and Dispose Asbestos Cement Pipe at Mixed Liquor Flow Split Box Area 4 Add Electric Hoist at Influent Pumps 5 Credit for Deletion of Headworks Water Stop and Influent Pump Pads 6 Credit for Deletion of Grit Handling Water Stop 7 Influent pump piping and hatch modifications 8 Credit for switch from precision cut to split face block on building 9 Guard rail modifications at headworks and aeration basin 10 Electrical conduit and wire modifications
15
Schedule Actual Notice to Proceed Substantial Completion Date
May 11, 2016 Substantial Completion Date October 28, 2018 Final Completion Date December 26, 2018
Similar presentations
© 2024 SlidePlayer.com. Inc.
All rights reserved.