1 AGA Workshop: Resource Management and Work Forecasting
Super Crew Process Will New Leak Survey Technologies Change How We Think of Resource Management? AGA Workshop: Resource Management and Work Forecasting

2 Topics for Discussion PG&E-Application of Advanced Leak Detection:
The Super Crew Process Resource Model(s) Benefits Challenges

3 PG&E Company Profile Gas Pipeline Key Statistics
Pacific Gas and Electric Company, incorporated in California in 1905, is one of the largest combination natural gas and electric utilities in the United States. The company provides natural gas and electricity to approximately 15 million people throughout a 70,000-square-mile service area in northern and central California. Service area stretches from Eureka in the north to Bakersfield in the south, and from the Pacific Ocean in the west to the Sierra Nevada in the east. Gas Pipeline Key Statistics 5,800 miles of gas DOT transmission pipeline 6,750 miles of pipeline > 60 psig Approx. 84,000 miles of gas distribution pipe 4.3 million natural gas customer accounts. Deliver 970 BCF/year (2.6 BCF/daily average)

4 Advanced Leak Detection ~Defining the Opportunity
Picarro Surveyor™, a very Powerful Mobile Leak Detection instrument 1,000 times more sensitive (PPB) Fast & Efficient – mobile / computer application (flight) Distinguishes between natural occurring methane to pipeline gas Finds more gas leaks Pinpoints “Hard-to-Locate” leaks Job Planning efficiency Post Disaster pipe evaluations Remote monitoring of survey from computer Redefining the way we view leak detection & correction protocols To be completed by Tim.

5 Mobile Picarro Unit Anemometer – measures wind speed and direction
GPS antenna – accurate to sub 60cm Inlet tube – stainless steel tube where the sample is drawn from Analyzer – cavity ring down spectrometer allows detection of methane at PPB level as well as gas sample analysis Mobile kit – contains power supply, pumps, filters, and GPS equipment allowing analyzer to be used anywhere

6 Launching a breakthrough Leak Management Process
January 2012 Livermore Test March 2012 Las Vegas April 2012 Sacramento Side-by-Side Test 2013 Mission Division Pilot Re-engineer leak mgmt. process Deployment 2014 February-April 2012 Side-by-Side Test Diablo

7 Leak Indication Display
Peak bubbles appear as Analyzer algorithm detects a peak of methane concentration.

8 Results

9 Super Crew Process

10 Super Crew Survey

11 Resourcing the Effort: San Jose (Example)

12 Resourcing the Effort: San Jose (Example)
Traditional Model Leak Survey Services (Per Day) 640 avg Personnel 8 Time Length 8 Months Leak Repair Number of Repairs 105 Personnel 5 Crews Time Length 6 Months **SUPPORT RESOURCES NOT INCLUDED ABOVE

13 Resourcing the Effort: San Jose (Example)

14 Resourcing the Effort: San Jose (Example)
Traditional Model Super Crew Model Leak Survey Services (Per Day) 640 avg Personnel 8 Time Length 8 Months Leak Repair Number of Repairs 105 Personnel 5 Crews Time Length 6 Months Leak Survey Services (Per Day) 1,500 avg Personnel 15 Time Length 14 Days Leak Repair Number of Repairs 105 Personnel 16 Crews Time Length 1 Week **SUPPORT RESOURCES NOT INCLUDED ABOVE

15 Challenges Balancing of Work (Super Crew vs. Local)
Capacity/Schedule (Pre, During, Post Super Crew) Embed Resources vs. Resource Locally Contractual Issues LOA Division vs. General Construction Timing Support Resources Communications

16 Resourcing Models Super Crew Local Division*

17 Benefits of Super Crew Model
Increased Safety Known Work Plan Bundling of Work (including other work types) Creating Capacity Gained strong political and regulatory support Grassroots approach to customer satisfaction

18 Bundling of Leak Repairs
Data-driven audit trails remove human error and streamline compliance process

19 Bundling Other Work Types

20 QUESTIONS? Video

21 Manager, Asset & Resource: Super Crew
Thank You Contact Information Hugh Adamo Manager, Asset & Resource: Super Crew Tel: