1 Fort Cherry School District
Financial & Capital Projects Overview

2 OVERVIEW District Finances Prior (Completed) Capital Projects
Proposed Future Capital Projects District Cuts/Additions Bond Outline Comments/Questions

3 Key Components for Funding
Enrollment Local Revenue State Revenue Federal Revenue State Mandates

4 Enrollment

5 Revenues KEY POINTS TO NOTE:
Millage rates have increased steadily since Prior to that, the millage rate was stagnant for 7 years. Main source of revenue is from the State (55%) Fort Cherry remains at 44% funded by local taxpayers.

6 Revenues by source

7 $ amount of Additional Revenue Raised
Millage Rates School Year Millage Rate $ amount of Additional Revenue Raised 123.50 $176,894 $238,316 130.50 $176,072 * $101,388 $211,221 * Reassessment Year

8 Expenditures KEY POINTS TO NOTE:
Expenditures increases are driven primarily by Contractual Staffing costs and Special Ed costs. PSERS Employer rates have increased to 33.43%. That is an increase of 2.64% from 2017/2018. We experienced a 16% increase in 2016/2017.

9 PSERS Public school employees’ RETIREMENT SYSTEM
State pension system for all public school employees Biggest unfunded State Mandate Employees contribute 6%-12% while the District contributes 33% In 2018/2019, the District will pay $2,500,000 in PSERS Contributions (~14% of budget)

10 Contractual Costs vs. Remainder of Budget
EXPENDITURES Contractual Costs vs. Remainder of Budget

11 DEBT SERVICE PAYMENTS

12 facilities Completed Capital Projects
Proposed Capital Improvement Plan (3 Years) Air Ventilation Options Programming Changes Personnel Changes

13 Completed capital projects
Capital Projects completed since 2014 Replacement of Hot Water Boiler Upgraded District’s Water Lines (eliminated use of water tower) Replacement of High School and Elementary Roofs

14 3 YEAR IMPROVEMENT PLAN: 2019-2021

15 2019 Proposed Projects Replace four (4) ovens in Elem Cafeteria ~$16,500 Replace two (2) ovens in HS Cafeteria ~ $8,100 Phase 2 or 3 of upgrading lights to LED (both buildings)~ $45,000 Phase 1 of 3 of updating carpet in Classrooms (both buildings) ~ $66,000 TOTAL COSTS for Year 1 = $135,600

16 2020 Proposed Projects Repair and paint outside canopies (both buildings) ~$375,000 Replace both buildings’ PA Systems ~ $84,800 Phase 3 or 3 of upgrading lights to LED (both buildings)~ $32,000 Phase 2 of 3 of updating carpet in Classrooms (both buildings) ~ $66,000 TOTAL COSTS for Year 2 = $557,800

17 2021 Proposed Projects Phase 3 of 3 of updating carpet in Classrooms (both buildings) ~ $66,000 District parking lots and driveway ~ $250,000 TOTAL COSTS for Year 3 = $316,000

18 Air Ventilation options
THREE OPTIONS FOR AIR VENTILATION: Nothing (Repair as needed out of GF) ~ $0 Repair and replace all unit ventilators in every classroom ~ $700,000 Replace classroom unit ventilators with Hydronic (hot and chilled) unit ventilators ~ $3,250,000

19 Items cut from list due to AC
Projects cut Items cut from list due to AC Locker Room renovation upgrade at High School Office flooring replacement District-owned Van District Salt/Dump Truck replacement District Bread Truck replacement Heating and Lighting upgrades at Pole Barn (maintenance building) Repairs to Chimney at High School Replacement of High School Gymnasium Bleachers

20 Programming & PERSONNEL

21 CHANGES IN PROGRAMMING FROM 2015-PRESENT
Programming changes CHANGES IN PROGRAMMING FROM 2015-PRESENT CUTS ADDITIONS * Alternative Education * New AP Courses / CHS * Home Economics * Restorative Programming * Accelerated Reader (AR) * 1:1 Curriculum at HS * Tech Lit at Elementary * Innovation/Design Lab * Full Time Life Skills (Gr. 7-12th) * STEAM/Makers Space * Elem 8-day rotation

22 CHANGES IN PERSONNEL FROM 2015-PRESENT
Personnel changes CHANGES IN PERSONNEL FROM 2015-PRESENT Eliminated four Administrative positions Eliminated Business Office Employee Eliminated Guidance Consultant Eliminated two IU Aides Eliminated Part Time Social Worker Eliminated HS Guidance Secretary Furloughed Professional Employees Eliminated Professional positions through attrition

23 BUDGET SUPPLEMENTS Implemented Pay to Participate Fee
Implemented Parking Pass Fee at HS

24 Current PROGRAMMING/PERSONNEL (not required per school code)
ELEM HS DISTRICT Math Specialist Guidance Pupil Services Director Vo Ag Transportation Director Nurse AP/CHS Courses Facilities Director Gym Band Food Service Clerk Music Chorus PIMS Accountant Library Art Safety & Security Officer STEAM Technology Technology Dept. Extracurricular Sports

25 Total Cost for 3 year plan
Air Conditioning (Chiller Unit): $3,250,000 Generator: $100,000 Proposed Costs for 3 year plan with AC: $4,359,400

26 Annual bond payments Current Bond payment = $255,000 (1.42% of budget)
(Pay until SY 2034) New Bond Payment: $2,000,000 Bond = $142,000/year (Pay until SY 2041) $4,500,000 Bond = $178,000/year (Pay until SY 2048) TOTAL Bond payment without AC = $397,000 (2.21% of budget) TOTAL Bond payment with AC = $433,000 (2.41% of budget)

27 TIMELINE Determine amount of Bond ~ October 2018
Obtain Bond ~ October 2018 – December 2018 Advertise (RFP) for Summer 2019 Projects Complete Improvement plan ~ June 2019 – August 2021

28 PUBLIC COMMENTS