Download presentation
Presentation is loading. Please wait.
1
Equipment Costing CAPEX
Sieder-Chapter 16 Review CH EN 5253 Terry A. Ring
2
Design I Coverage Time Value of Money Capital Costs Operating Costs
Profitability Analysis Reading Materials
3
6/10th scale up/down Factor
Used for scaling the total capital cost for a chemical plant of a different size Cost2/Cost1 = (Capacity2/Capacity1)0.6 0.6 - Accounts for economy-of-scale
4
Cost Estimate Methods Order of Magnitude Estimate
Method of Hill Marshall Swift for I/Ibase Six Tenths Rule for Production Capacity CTCI-2 (I)=CTCI-1 (Ibase)*(I/Ibase)* (Capacity2/Capacity1)0.6 Study Estimate (±35%) Method of Lang CTCI=1.05*fL-TCI ∑ (Ii/Ibase-i) Cp-i Lang factors for different types of Plants Solids -3.10, Solids&Fluids 3.62, Fluids 4.73 Sum over all major equipment Preliminary Estimate (±20%) – use this method in CHEN 5253 Method of Guthrie Bare module cost, CBM=Cp-base(I/Ibase)[FBM+(FdFpFm-1)] d= design factor, p = pressure factor, m =materials factor Quote Estimate
5
Accounting for Inflation
Cost to purchase = Base Cost*(I/Ibase) Base Cost, CB, = Historical price at Io I is a Cost Index at present time Chemical Engineering, CE, Plant Cost Index Ibase=567 (<2013>) for your equations in Sieder’s 4th Ed. Marshall and Swift (MS) Equipment Cost Index Nelson-Farrar (NF) Refinery Construction Cost Index Engineering News-Record (ENR) Construction Cost Index Cp(I) = Cp(Ibase)*(I/Ibase) Cp(Ibase)=FT*Fm*Cbase(Ibase) (Hill Method) FT= Type factor Fm= Materials factor
7
Purchase Costs for Equipment
Size Factor, S, depends on type of equipment Cp(Ibase)= A + b* (S)n Ibase= 567 (2013 average) Cp(Ibase)=exp(Ao+A1[lnS]+A2[lnS]2+…) Ibase = 567 (2013 average)
13
Installation Factors
14
Materials Factor The materials factor is different for different pieces of equipment
15
Compressors Compressor types (Ibase=394)
Centrifugal, CB=exp{ [ln(PC)]} Reciprocating, CB=exp{ [ln(PC)]} Screw, CB=exp{ [ln(PC)]} Size factor is the power consumed, PC=PB/ηC CP=FDriveFMatCB FDrive =1 (electric motor), 1.15 (steam), 1.25 (gas turbine) FMat = 1.0 Carbon steel, 2.5 SS, 5.0 Nickel Alloy CBM=FBM*∑CP FBM = 2.15
16
Heat Exchangers Types of Heat exchangers (Ibase=394)
Floating, CB=exp{ [ln(A)] [ln(A)]2} Fixed Head, CB=exp{ [ln(A)] [ln(A)]2} U-tube, CB=exp{ [ln(A)] [ln(A)]2} Kettle, CB=exp{ [ln(A)] [ln(A)]2} Thermosiphon, CB= Double pipe, CB=exp{ [ln(A)]} Size Factor is HX area, A CP=FpFMatFLCB Pressure Factor, Fp= (P(psig)/100) (P(psig)/100)2 Not for double pipe Materials Factor, Fmat=a+(A/100)b, a & b from Table 22.25 a≥1.0 note error in Table Tube Length Factor FL= 1.25 for 8 ft, 1.0 for 20 ft. on a sliding scale CBM = FBM*CP, FBM=3.17 (S&T), 1.80 (DP), 2.17 (Fin/Fan)
17
Fired Heaters Size Factor is the heat duty, Q
CB=exp{ [ln(Q)]} (Ibase=394) CP=FPFMatCB FP= (P(psig)\500) (P/500)2 Fmat=1.4 Cr-Mo alloy steel, 1.7 for stainless steel CBM = FBM*CP, FBM=2.19
18
Pressure Vessels Storage Tanks Distillation Towers Absorber Towers
Tray Packed Absorber Towers Stripping Towers
19
Pressure Vessels Storage Tanks Distillation Towers Absorber Towers
Tray Packed Absorber Towers Stripping Towers
20
Pressure Vessels Sizing Factor is the weight of steel, W
Horizontal Vessels, 1,000<W<920,00 lb CB=exp{ [ln(W)] [ln(W)]2} (Ibase=394) Vertical Vessels, 4,200<W<1,000,00 lb CB=exp{ [ln(W)] [ln(W)]2} (Ibase=394) Add Platform Costs, Horizontal, 3<Di<12 ft CPL=1580(Di) (Ibase=394) Vertical, 3<Di<21 ft CPL=258.1(Di)0.7396(L) (Ibase=394) Weight, W=π(Di+ts)(L+0.8Di)tsρs C=FMCB+CPL FM= materials factor Installation, etc, FBM=4.16 (V), 3.05 (H) CBM=FBM*∑CP
21
Hoop Stress Calc for thickness, ts
Design Pressure is function of operating pressure, Po For Po> 1,000psig use Pd=1.1Po For Po< 1,000psig but not for vacuum Pd=exp{ [ln(Po)] [ln(Po)]2} Thickness (Hoop Stress Calculation) ts= PdDi/(2SE-1.2 Pd) S = max allowable stress for steel is f(T) E = weld efficiency (fraction) Minimum wall thickness for given diameters May add extra thickness for wind stresses, corrosion Different calculation for vacuum vessels Also account for leakage when vacuum vessel is used
22
Distillation Towers Pressure vessel with plates or packing and additional nozzels and manholes Tray Cost CT=NTFNTFTTFTMCBT NT= no. trays FNT= 1 for NT>20 otherwise FNT=2.25/(1.0414NT) FTT = tray type, 1.0 sieve, 1.87 bubble cap FTM= Materials, f(D) Carbon Steel FTM=1.0 316 SS FTM= Di Installation, etc, FBM=4.16 CBM=FBM*∑CP
23
Packed Distillation Column
Pressure vessel with platforms plus packing Packing Cost basis is volume of packing, VP C=VpCPK+CDR CPK= is installed cost per unit volume Distributors cost, CDR
24
Absorbers/Strippers Pressure Vessel Separate costs for blowers
plus platforms plus packing Separate costs for blowers Separate costs for motors On blowers On mixers On pumps
25
Plant Location Factor FISF From T&S Book
26
Do Not Forget Utility Plants
27
Total Capital Investment
28
Conclusions 0.6th rule Factored Estimate of Major Equipment
Installation Factor Peripheral equipment, foundations, piping, etc Biggest Mistakes Forget Utility Plants No Off Sites No Electrical Substation No Natural Gas Connection Neglecting Major Equipment
Similar presentations
© 2024 SlidePlayer.com. Inc.
All rights reserved.