Download presentation
Presentation is loading. Please wait.
1
PACIFIC TEAM SPRING QUARTER PRESENTATION
2
TEAM MEMBERS Owners TONIE GARZA ARCHITECTBBerkeley PETER DEMIAN
STRUCTURAL ENGINEER Stanford JOHN ENGSTROM CONSTRUCTION MANAGER Stanford Owners ASAKO AKAZAWA APPRENTICE Stanford Robert Alvarado Industry Owner Mr. Kozakai Japan
3
Outline of Presentation
Project Introduction Winter Quarter Alternatives A-E-C Iterations and Resolutions Architectural Review Structural Review Construction Review Collaboration and Group Dynamics
4
A E C Team Dynamics Lessons from Winter Quarter
Be more honest in our interactions Meet more frequently Increase the team’s interaction with the owner
5
A E C Team Dynamics Interaction was more active
Spring Quarter Improvements? Interaction was more active The group met more frequently (at least twice per week) Interactions with the owner were not increased significantly The group developed a better understanding of the disciplines Our individual project decisions were more disciplined based
6
A E C Project Information The Engineering School of Pacific University
Location: Oregon Coast Year: 2010 Square Footage: 30,000 sf. Budget: $5,500,000
7
A E C Site Layout
8
A E C Design Alternatives PROPOSAL 1 - The Saucer
PROPOSAL 2 - The Zig-Zag PROPOSAL 3 - The Bunker PROPOSAL 4 - The Crystal Palace
9
A E C Design Alternatives A E C $4.8M DESIGN ALTERNATIVES Good forms.
PROPOSAL 1 - The Saucer Good forms. Slightly predictable. No clear architectural intent. A DESIGN ALTERNATIVES Simple Frame. Potential problems with columns. E C $4.8M
10
A E C Design Alternatives A C E
PROPOSAL 2 - The Zig-Zag Large beam span in auditorium may pose some significant challenges. Standard grid allows for little variation in building skin. A C Concurrent construction $4.8M E Simple layout due to grid format
11
A E C Design Alternatives A C E DESIGN ALTERNATIES
PROPOSAL 3 - The Bunker A Initial reaction to conceptual beginning. Challenging and intriguing structural system. Exceeds structural budget. $5.9M C E
12
A E C Design Alternatives A C E
PROPOSAL 4 - The Crystal Palace Remains close to conceptual ideas while at the same time addressing programmatic requirements A Best combination of structural and architectural requirements. Presents challenges to all disciplines while staying within the budget. $5.5M C E
13
A E C Proposal Recommendation PROPOSAL 4 - The Crystal Palace
14
A E C The Design
15
1st Floor: Plan & Layout
16
2nd Floor: Plan & Layout
17
3rd Floor: Plan & Layout
18
Programmatic Changes Iteration 1 Iteration 2
19
Circulation vs. Used Space
Iteration 1 Iteration 2
20
Area Designated by Use
21
Privacy/Security Level 3 Level 2 Level 1
22
Atrium Lighting Evening light study Morning light study
23
3D Renderings Building main entry -Evening and afternoon light
24
3D Renderings Northeast façade & Overhangs
25
A E C 100 psf (computer lab) Structural Concept
Concrete - to reflect architectural ‘bunker’ concept PT flat slab, drop panels Shear walls - seismic Zone 3 large spans: span/depth=38 gravity loads: dead 100 psf live 50 psf (office) 100 psf (computer lab) earthquake load: UBC 94 Zone 3 Spectrum
26
A E C Overall Structure
27
A E C Columns / Foundations Columns and Foundations
PROPOSAL 3 - The Bunker Columns and Foundations Columns / Foundations Interior columns circular, 20” diameter, 3% reinforcement, very small moments drop panels 4’ diameter by 8” deep Exterior columns (corners and sides) 24” square, 6% reinforcement drop panels 5’ square by 8” deep Foundations rock - simple footings 4½ ft by 12 in, 0.33% reinforcement
28
A E C Slab 12 in thick PT slab Shear Moment
29
A E C Column Slab Connection
“Chair” to hold tendons PT tendons: 21 in columns stip, 7 in middle stip per span Shear around column necessitates drop panels Shrinkage rebar
30
A E C Shear Wall 4 exterior walls 20” thick by 12’ long
architectural influence: thicker than necessary limit on length of wall shear wall combined with adjacent column. ‘Column’ acts as a column for out-of-plane bending, and as a shear wall boundary element for in-plane bending. Construction consequences: Connection subtleties
31
A E C Shear Wall Detail Rebar to slab
No8 bars at 12in c-c in wall (12ft) No11 bars in ‘minor’ boundary element Column/ Boundary Element Continuos ties ensure both parts act as one component Closed hoops
32
A E C Old Atrium Moment resisting Frames
Complex joint between two different slab systems Roof/ slab interaction Struts for lateral support
33
A E C New Atrium Conceptually: leaning column
Beams tucked away beneath staircase
34
A E C Seismic Analysis
35
A E C Slab Deflections, Vibrations - Problem?
Large spans, large deflections UBC limit: 1 in Max displacement from ‘model’: 2 in Vibrations: more difficult to analyze.
36
A E C Construction Summary Construction Concrete CIP Structure
Rock Excavation Slab Overhangs and Pre-cast Atrium Glass Curtain Wall
37
A E C Site Layout
38
A E C Estimate Cost = $4.9M ($161/sf)
39
A E C Excavation Costs Discovery of Rock on Site significantly increased the unit cost of excavation. This was mitigated by: Reducing floor-to-floor heights and eliminating a submerged 1st level. This reduced the amount of excavation by over half (still need auditorium and large classrooms Ancillary effect was to reduce the size of footings
40
A E C Slab Costs $/sf
41
A E C Schedule Completion September 12, 2012
42
A E C Milestones Exterior Closure May 24, 2012 Superstructure
April 12, 2012 (5.5 Months)
43
A E C MEP Systems Mild Climate
Exposed system important for architecture Standard Design Air Handler, Chiller, Boiler configuration
44
A E C HVAC Distribution A-C Iteration MEP Rooms centrally located
E-C Iteration Holes in the Slab Next to Elevator Shaft
46
A E/ C AEC Interaction E/ C A A E AEC Interaction Atrium Overhangs
Shear Walls
47
AEC Interaction A E/ C Atrium AEC Interaction
48
AEC Interaction E/ C A Overhangs AEC Interaction
49
Shear Walls A E
50
Future Design Proposal
51
Value of Course Architect Cross-Disciplinary Take Home Lesson
Construction Manager focus on work efficiency Engineer assumption about architectural understanding of structure Take Home Lesson The more sketching I do, the more questions E & CM will want answered.
52
Value of Course Engineer Cross-Disciplinary Take Home Lesson
Understanding the importance of structural concept Appreciate the scheduling/financial aspects of CM Take Home Lesson Every structural decision will effect other disciplines
53
Value of Course Construction Manager Cross-Disciplinary
Conceptual architecture is difficult to grasp. 3D Model is essential to facilitate communication Take Home Lesson Design is never complete, it is simply abandoned. Pay attention to the gap between conceptual phase and detail phase
54
The End
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.