Download presentation
Presentation is loading. Please wait.
1
OCPS SCHOOL SITE SELECTION PROCESS
1
2
SITE SELECTION ADVANCED PLANNING (AP) SITE ASSESSMENT MEETING (SAM)
OCPS PLANNING & GOV. RELATIONS (CHAIR) ORANGE COUNTY PLANNING DEPT. OCPS FACILITIES PLANNING OCPS REAL ESTATE ENGINEERING CONSTRUCTION MGT. OCPS CURRICULUM OCPS STUDENT TRANSPORTATION OCPS PUPIL ASSIGNMENT SITE ASSESSMENT MEETING (SAM) OCPS PLANNING OCPS Real Estate OCPS FACILITIES PLANNING CONSULTANTS ARCHITECTS ENGINEERS ENVIRONMENTAL LEGAL COUNSEL 2
3
10 YEAR CIP MODIFIED > FISCAL > COVE > OCPS BOARD APPROVAL
OCPS REAL ESTATE IDENTIFIES AVAILABLE SITES SAM EVALUATES ENGINEERING ISSUES AP REVIEWS RECOMMENDATIONS APPROVES / REJECTS SITES SCHOOL BOARD APPROVAL CLOSING 3
4
Elementary School Target Zones
5
Elementary Schools Target Zone
6
Middle School Target Zones
7
High School Target Zones
7
8
High School Target Zone
9
58 Criteria: Land Use DRI restrictions PD restrictions Future Land Use
Overlay zones Current zoning Is DRI, PD, FLU or Zoning change required Is Special Exception required Compatible land use Capacity Enhancement Agreement Impact Fee Credit Site reviewed by local government Community meeting 9
10
58 Criteria: State/Local Guidelines
Adequate roads Within 300 feet of overhead high voltage transmission lines Adjacent to water and waste water treatment plants Within 1/4 mile of an active landfill Within 100 year flood plain Hazardous pedestrian access road Minimum acreage Flight path Archeological sites Within 100 feet from gas transmission lines Adjacent to rail lines High capacity fiber optics on site Adjacent to parks Code violations 90 day notice of intent Determination of consistency 10
11
58 Criteria: Architectural & Engineering
Preliminary site analysis Concept site plan Drainage Fill on site Joint use planning 11
12
58 Criteria: Agreements & Legal
Purchase Donation Reservation Easements Joint use Title Policy Closing documents 12
13
58 Criteria: Due Diligence
Appraisal Survey showing 100 year flood plain & easements Phase I environmental Phase II environmental (If required) Wetlands determination Wetlands delineation SJRWMD & Army Corps of Engineers Approvals Bi-Racial Committee Geotechnical Endangered species Water line verification Sewer line verification Traffic study 13
14
58 Criteria: OCPS Approvals
Advance Planning Committee Site Assessment Meeting (SAM) Report to COVE School Board 14
15
OCPS DEVELOPMENT REVIEW PROCESS
15
16
GOVERNMENTAL RELATIONS DEVELOPMENT REVIEW OCPS FACILITIES &
ZONING OCPS PLANNING & GOVERNMENTAL RELATIONS DEVELOPMENT REVIEW OCPS FACILITIES & ENGINEERS/ARCHITECTS OCPS ENGINEERS PREPARE DEV. PLAN OC DRC PD & LAND USE PLAN SPEC. EXCEPTION REVIEW COMMUNITY MEETING (OC Attends) P & Z HEARING/BZA BCC HEARING 16
17
OCPS SCHOOLS & SITES IN RURAL SETTLEMENTS
17
18
OCPS Schools & Sites Northwest Rural Settlements
18
19
OCPS Schools & Sites Northwest Rural Settlements
19
20
OCPS Schools & Sites Northwest Rural Settlements
20
21
OCPS STUDENTS NORTHWEST RURAL SETTLEMENTS
STUDENTS INSIDE RURAL SETTLEMENTS STUDENTS OUTSIDE RURAL
22
OCPS Schools & Sites North Central Rural Settlements
22
23
OCPS STUDENTS NORTHCENTRAL RURAL SETTLEMENTS
STUDENTS INSIDE RURAL SETTLEMENTS STUDENTS OUTSIDE RURAL
24
OCPS Schools & Sites West Rural Settlements
24
25
OCPS STUDENTS WEST RURAL SETTLEMENTS
STUDENTS INSIDE RURAL SETTLEMENTS STUDENTS OUTSIDE RURAL
26
OCPS Schools & Sites West Central Rural Settlements
26
27
OCPS Schools & Sites West Central Rural Settlements
27
28
OCPS STUDENTS NORTHCENTRAL RURAL SETTLEMENTS
STUDENTS INSIDE RURAL SETTLEMENTS STUDENTS OUTSIDE RURAL
29
OCPS Schools & Sites East Rural Settlements
29
30
OCPS Schools & Sites East Rural Settlements
30
31
OCPS Schools & Sites East Rural Settlements
31
32
OCPS Schools & Sites East Rural Settlements
32
33
OCPS STUDENTS EAST RURAL SETTLEMENTS
STUDENTS INSIDE RURAL SETTLEMENTS STUDENTS OUTSIDE RURAL
34
OCPS Schools & Sites Southeast Rural Settlements
34
35
OCPS STUDENTS SOUTHEAST RURAL SETTLMENTS
STUDENTS INSIDE RURAL SETTLEMENTS STUDENTS OUTSIDE RURAL
36
OCPS Schools & Sites Rural Settlements
Conclusion Site Selection Limited by Relief Area School Board Targets Unutilized Land School Board Utilizes an Extensive Criteria Review and County Staff is involved at various stages of the process School Board Selection Consistent with School Siting Ordinance Rural Settlement Impacts on Schools Impact of Disallowing Schools in Rural Settlements 36
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.