EPICS Controls Steve Lewis 13 December 2007
LCLS Total Energy Final Design Review EPICS Controls Steve Lewis 13 December 2007
2
Outline Use of LCLS Standards Top-level Diagrams
Details of Hardware and Software Vacuum not shown Gauges and Ion pumps are LCLS standard Turbo-molecular and scroll pumps are XTOD only Have much in common with K-Spect, Direct Imager Network Infrastructure not shown Identical across all of XTOD and XES Supplied by XES group
3
Block Diagram EPICS Control System (includes PLC)
Compressor and Pulsed Valve On/Off Block Diagram Motor+ Encoder Attenuator Motion Control Motor+ LVDT X,Y Stage Motion Control Selection 2 Position++ Laser Laser Control Trigger Vacuum Pumps+ Gauges Energy Sensor Energy Meter On/Off, Pressure 2 2 2 Energy Temperature Control + Resistance Measurement DC Bias+ Preamplifier 16 16 Energy, Temp Bias, Gain Resistance 16 Signal Trigger Apparatus Digitizer S. Lewis v4
4
Instrumentation S. Lewis v6
5
Consistent Across LCLS and XTOD
Hardware LCLS (or SPEAR) standard VME Crate, CPU, Timing (IOC) Weiner 195 Motorola MVME-6100 Micro-Research PMC-EVR 200 Stepper Motor Control Hytec Industry Pack 8002/8601 Indexer (VME) Hytec SMDS-4B Driver Highland V550 LVDT (VME) Consistent Across LCLS and XTOD
6
Hardware XTOD only Digitizer/Signal Conditioner Energy Meter
ICS-130/121 (VME) Energy Meter Ophir PE-10 Laserstar (serial) Attenuator Optosigma PAT-001 (serial) Temperature Lakeshore 340 (serial)
7
Consistent Across LCLS and XTOD
Software LCLS standard Device drivers Hytec Stepper Motor (VME) Highland LVDT (VME) EVR Timing (VME) Serial Device-level GUI elements All other tools and utilities Archiver Trend Graph Save/Restore Automation Sequencer Alarm Handling MATLAB Consistent Across LCLS and XTOD
8
Software XTOD Only ICS Digitizer/Signal Conditioner
Vendor: VxWorks driver and support library XTOD/XES: EPICS ‘device support’ Automation Sequences Waveform Processing In IOC MATLAB Attenuator and Lakeshore Temperature Controller Serial protocol description (using LCLS template) “Interesting” part
9
Costs and Effort All controllers, cables, racks, and auxiliary equipment are itemized Effort for unit testing and commissioning included in overall accounting Hardware Cost = $35K