Initial Discussion For $200 Mil General Obligation Bonds
2
Operations Assessment
Categorized All facilities were categorized into 6 groups Targeted the worst elementary schools in each District Standardization Models 3 standard models for Pre K - 5 and Pre K - 8 were developed utilizing current best practices 1 standard model for Career Magnet High School Estimates for all models were prepared reflecting current market conditions Logistics Assess the potential method of delivery Identification of potential sites with available land to build new schools Demographics Assess the facility for under or over utilization Identification of population areas of high or low student densities Educational Multiple career pathways to graduation and developing a Career Magnet Program Expanding the Pre K program Overall Methodology Operations Assessment
3
Categories for All Facilities
Total Replacement Historical Renovation with Partial Replacement Major Renovation with Partial Replacement Major Renovation Upgrades Needed Minor Improvements
4
School By Categories Total Replacement Airline Park Birney Bridgedale
Ellis Fisher George Cox Green Park Gretna Park Harris Elem Hart Hazel Park Hearst Keller Live Oak Marrero Middle McDonogh 26 St. Ville Washington Historical Butler Dolhonde Douglass Gretna #2 Harahan Haynes Metairie Academy Riverdale Middle Partial Replacement Clancy East Jefferson Estelle Marrero Academy Pitre Thibodeaux Wall West Jefferson Woods Major Renovation Bissonet Plaza Bonnabel High Helen Cox Cuillier Center Ehret Ellender Greenlawn Harris Middle Jefferson Elem Livaudais Matas Pittman Riverdale High Riviere Schneckenburger Strehle Thomas Jefferson Truman Westbank Community Woodland West Worley Upgrades Needed Adams Alexander Audubon Boudreaux Chateau Estates Cherbonnier Deckbar Ford Gretna Middle Higgins Janet John Martyn Kerner King Meisler Roosevelt Solis Minor Improvements Collins Grand Isle Lincoln Ruppel Taylor Terrytown School By Categories
5
COST Impact of School models
School Model Type Number of Students Square Footage Cost for Each New Facility* Pre K - 5 Large 91,095 $27 Mil Pre K - 8 110,275 $33 Mil Pre K - 8 Large 136,976 $41 Mil Magnet High 163,779 $58 Mil * Inclusive of Technology and FF&E Costs
6
Impact on School operations
New School Minimal impact Replacement/Historical Renovation School Relocation of school for years Phased Replacement School Disruption to operations for years from moving students around campus Partial Replacement School Utilizing some temporary facilities for years Renovated School Minor disruption to operations for years
7
Sites with available land to build new Facilities without Impact
West Bank Lafitte / LaRose Westminster Rillieux Marrero Middle East Bank Loyola Hazel Park Riverdale Middle
8
West Bank
9
East Bank
10
Phase One $200 Million New Harvey School New Westminster School
Pre K - 8 Will alleviate overcrowding and transportation concerns in the south of Harvey Johnson Gretna Park can then become a swing school for other projects New Westminster School Build school inside of attendance zone After renovation of Butler, Thibodeaux can become a swing school Replacement of Washington Elementary Eliminates the need to bus middle school students to Riverdale Begins to alleviate overcrowding in the middle of the East bank New Loyola School Available in area of highest density of students Will become swing school to address high enrollment concerns New Career Magnet High School Full Day $58 Mil 9 - 12 Career Pathways that address JEDCO’s Edge 20/20 Vision Full core class load Acquisition and Logistics $10 Mil Purchase 4 tracts of land for Harvey, Westminster, Washington, and new Career Magnet High School Projects Renovate Johnson Gretna Park for swing school Phase One $200 Million
11
Replacement Pre K-8 Washington Elem Site $33 Mil New Magnet High Elmwood $58 Mil
12
Phase Two $200 Million Replacement of Hazel Park
$30 Mil Pre K - 5 Replaces old outdated facility Alleviates pressure in the middle of the East Bank Historical Renovation of Butler Elementary $23 Mil Pre K - 5 Thibodeaux would be moved into Butler Thibodeaux can become a swing school for other projects Renovations to Ford / Cherbonnier $28 Mil Ford / Cherbonnier Pre K - 8 Allows for the consolidation of Strehle and Ford with repurposing of Strehle Allows for the consolidation of Live Oak and Cherbonnier with repurposing of Live Oak Replacement of Ellis Elementary $30 Mil Pre K - 5 Temporarily to be housed at Martyn Replacement Hart / Mc26 Elementary Allows for the repurposing of Hart To be temporarily housed at Johnson Gretna Park Historical Renovation of Dolhonde Elementary $23 Mil Pre K - 5 Alleviates the pressure in the middle of the East Bank with a larger capacity school To be temporarily housed at Martyn Replacement of Hearst Elementary Alleviates the pressure in the middle of the East Bank To be housed in the Loyola site Logistics $6 Mil Swing Schools Renovation of Deckbar to allow Martyn to move permanently to Deckbar Martyn Becomes swing school for Dolhonde and Ellis Phase Two $200 Million
13
Replacement Pre K-5 Ellis Elem $30 Mil Replacement Pre K-5
Hazel Park Elem $30 Mil Phase Two $200 Million 4 Replacement Pre K-5 2 Renovated Pre K-5 Schools 2 Renovated Pre K-8 Schools Renovation Pre K-8 Ford / Cherbonnier $28 Mil
14
Phase Three $200 Million Replacement St. Ville Elementary
Pre K - 8 Will alleviate overcrowding in the middle of the Westbank allowing the repurposing of Douglass Johnson Gretna Park to be utilized as the swing school Historical Renovation of Harahan Elementary $19 Mil Pre K - 5 Replaces old outdated facility To be housed in the old Hazel Park Replacement of Fisher High School $42 Mil 6 - 12 Provides storm protection for the school Phased construction students moved around campus Replacement of Marrero Middle Convert school to Pre K - 8 Marrero site big enough to build on site Replacement of Birney Elementary $33 Mil To be housed in the Loyola site Partial Replacement of Riverdale Middle $30 Mil 6 - 8 Phase Three $200 Million
15
Renovation Pre K-5 Harahan Elem $19 Mil
16
Phase Four $200 Million Renovation of Wall Elementary
$23 Mil Pre K - 5 Convert school to Pre K - 8 To be temporarily housed at Marrero Replacement of Harris Elementary $36 Mil Pre K - 5 Replaces old outdated facility To be temporarily housed at Thibodeaux Renovation of Green Park Elementary To be housed at Hazel Park Renovation of Vic Pitre Elementary $23 Mil Pre K - 5 Replacement of George Cox To be temporarily housed at Harvey Renovation of Jefferson Elementary To be temporarily housed at Martyn New School on Lafitte / LaRose Hwy Accommodates growth in the south No impact Phase Four $200 Million
17
Renovation Pre K-5 Green Park Elem $23 Mil Replacement Pre K-5 Harris Elem $36 Mil New Pre K-5 Lafitte / La Rose site $36 Mil
18
At least 8 School Facilities could be repurposed during this process