BOND PROGRAM- Door Lock & Building Access
District Citizen’s Oversight Committee June 8, 2018
2
AGENDA I. Introductions II. Current Progress Interior Lock Example
Execution Strategy Phase I Phase II Active Design & Construction Projects AGENDA
3
CURRENT PROGRESS BOND PROGRAM- DOOR LOCK & BLDG. ACCESS
Research & Development – COMPLETE Active Shooter Response Guidelines (Best Practices) Industry Standards (Manufacturer, Architects) Division of the State Architect (DSA) College Facility Directors Sheriff’s Department
4
CURRENT PROGRESS, CONT. BOND PROGRAM- DOOR LOCK & BLDG. ACCESS
2. Chancellor’s Directive No. 185 – DOOR HARDWARE/ LOCKING DEVICES- COMPLETE Performance Requirement (Form, Fit & Function) Multiple Door Hardware Sets Acceptable
5
INTERIOR CLASSROOM LOCK SAMPLE
BOND PROGRAM- DOOR LOCK & BLDG. ACCESS For Reference Only
6
INTERIOR CLASSROOM PANIC BAR SAMPLE
BOND PROGRAM- DOOR LOCK & BLDG. ACCESS For Reference Only
7
CURRENT PROGRESS, CONT. BOND PROGRAM- DOOR LOCK & BLDG. ACCESS
3. Preliminary Door Inventory – COMPLETE As-Built/Record Drawings Building Information Models (BIM) Total Classroom Door Count: 3,300 Doors (e.g., Classrooms, Lecture Halls, Studios, Labs)
8
CURRENT PROGRESS, CONT. BOND PROGRAM- DOOR LOCK & BLDG. ACCESS
4. Field Verifications– In Progress Validate Quantity, Type, Condition & Location of All Doors/ Locks Identify Doors that Require Modifications
9
EXECUTION STRATEGY BOND PROGRAM- DOOR LOCK & BLDG. ACCESS Phase I
Lock Replacement “Not Requiring” Door Modifications Phase II Lock Replacement “Requiring” Door Modifications Electronic Access Control (Exterior Doors)
10
PHASE I – DOOR LOCK REPLACEMENT
BOND PROGRAM- DOOR LOCK & BLDG. ACCESS Timeline Estimated Budget: $2.8M (Rough Order Magnitude) Completion Schedule: Design – Fall 2018 Installation – Winter 2018/Spring 2019 GOAL: Install 70% of ALL Classroom Door Locks by April 2019 $1,100 per 2,500 Doors for design, installation, labor and hardware, DSA
11
PHASE II – DOOR LOCK REPLACEMENT & BLDG. ACCESS
BOND PROGRAM- DOOR LOCK & BLDG. ACCESS Timeline Completion Schedule: Define Scope and Establish Budget- Summer 2018 Design – Fall 2018 to Spring 2019 Installation – Fall 2019
12
BOND PROGRAM- DOOR LOCK & BLDG. ACCESS
ACTIVE DESIGN & CONSTRUCTION PROJECTS Projects in Design: Directing Architects to Revise Plans Projects in Construction: Evaluating Potential Change
13
QUESTIONS