CMBG Performance Indicator Working Group
Lloyd Hancock, CMBG Steering Committee November 12, 2018 Cleveland 2005
2
CM PI Working Group Beth Kernes Krause, Cooper Station
Keith Reinsmith, Susquehanna NPP Rai Osborne, SONGS Peter Davidson & Hans Braul, Bruce NPP David Weber, Columbia Station Gary Scarfo, Fermi Plant Lloyd Hancock, Facilitator November 12, 2018 Cleveland 2005
3
CM PI Working Group Charter
Requested at 2004 CMBG Conducted Numerous Conference Calls and s Picked 5 “Easy” Indicators Developed Consensus Definitions Collected Data November 12, 2018 Cleveland 2005
4
CM Simplified Process Model
5
CM PI Working Group PIs Selected
Temp Mods (quantity & age) Mod Package Closure Times Critical Document (FCI) Backlog Avoidable Field Changes for Mods % of CM CRs to Total CRs November 12, 2018 Cleveland 2005
7
CM PI Working Group Lessons Learned
Terminology Difficult to Agree On Collecting Data Very Time Consuming if Reporting System(s) not set up Entire Exercise Was Learning Experience November 12, 2018 Cleveland 2005