1 PROJECT NO. T-841017.80 SE Adams Street - SE 29th Street to SE 33rd Terrace

2 Project Contacts Contractor – Kansas Heavy Construction, LLC Project Manager – Matt Gripka – (913) Project Superintendent – Jeff Gragg – (913) City of Topeka Project Manager - Robert Bidwell, PE – David Bevens - Community Information Manager – Construction Inspection – City of Topeka Ed Schraeder - Construction Manager –

3 Project Scope of Work Replace existing 8”+ concrete pavement and curb & gutter with new 10” Concrete Pavement and curb & gutter on an aggregate base including driveways (to the sidewalk) and sidewalk ramps at the intersections. Replace deteriorated storm sewer inlets and inlet tops. Replace existing corrugated metal storm sewer pipes with reinforced concrete pipe. Replace and upgrade traffic signals and sidewalk ramps at the 29th and Adams intersection

4 Project Phasing Road to be closed to thru traffic. Thru traffic will be carried on signed detour. Area adjacent to the Post Office will be constructed in phases to allow access to the Post Office from 29th and Adams during construction at all times. Properties abutting Adams between SE 31st to SE 33rd will be carried to side streets on one lane access roads to SE 31st Street, SE Golf Park Boulevard or SE 33rd Street. Access roads are from mid-block each direction

5 Project Detour Route

6 Phasing at Post Office

7 Project Bus Detour Route
Regular route to 29th & Adams (temporary bus stop) West on 29th to Freemont South on Freemont to Golf Park East on Golf Park to Colfax (Avondale-temporary bus stop) North on Colfax to 31st West on 31st to Freemont North on Freemont to 29th East on 29th Back onto normal route

8 During Construction Properties that abut Adams Street will have temporary mailboxes relocated to a central location as per the Post Master. Permanent mailboxes will be reinstalled after completion of the work. Trash containers will be pick up weekly by the Contractor and taken to a location for disposal by the trash hauling companies. Make sure the cans are out when they are usually to be picked up. If there is a problem or concern, seek out the Contractor’s superintendent or the project inspector first.

9 Project Schedule The current schedule for the project is;
May 29, 2018 – Start work November 9, 2018 – Project to be complete

10 THANK YOU FOR COMING TODAY!
QUESTIONS ?