Project Scheduling Tools
2
1. Sequencing There are four possible sequencing modes in MS Project. Suppose B follows A. FS: Finish Start – Start B after A is completed SS: Start Start – Start A and B at same time FF: Finish Finish – Finish A and B at same time SF: Start Finish – Start A after B is completed Lags are delays between work on activities
3
FS Sequence - Traditional
B E.g. Sand and Paint A Lag B E.g. Sprinklers and Landscape
4
SS Sequence A E.g. Plant Lawn and Flowers A
B A E.g. Drywall: Hang and Tape Lag B
5
FF Sequence A E.g. Olympics B A Lag E.g. Olympics B
6
SF Sequence A E.g. Not Practical B A B E.g. Ocean Cruise Lag
7
2. Activity Uncertainty PERT assumptions (Richard Schonberger and Ken Mac Crimmon Beta distribution assumption PERT approximation formula for mean and variance Estimates of a, m, and b Errors of above up to 30%, but tend to cancel Worse problem is merge event bias (probability near-critical path becomes critical) – estimates consistently optimistic
8
Example 2.1 B,2 A,1 D,1 C,3 Critical path is ACD but ABD is near critical. Criticality index: probability path critical.
9
Use Simulation or Monte Carlo Analysis
Generate random numbers (electronic, formulas, tables, books) i.e. 28 • Convert to random probabilities i.e What is probability of probability? • Convert random probability to random variate. Follows distribution of say actual activity time.
10
Finding Random Variates, Problem 2.1
B C PMF CDF Mean – Mean Mean Mean Random probability of .28 gives B random variate of 1; .46 gives C value of 3.
11
Simulation of Problem 2.1 RN B(2) RN C(3) Length Path
ACD ABD ACD ACD ACD Expected length = 5.8 > 5 (merge event bias) Criticality index of ACD = 0.8 or 80%
12
Project Simulation Simulation includes
GERT – Graphical Evaluation and Review Technique Crystal Ball – Copy comes with text Probabilistic branching from node – B may follow A Probabilistic times for activities – various distributions Flexibility in node realization – activity time can = 0 Looping permitted – rework Critique of Simulation – R. Schonberger recommends intensive critical path scrutiny
13
3. Limited Resource Scheduling
Resources include labor, material, equipment, space, and money Money versus time tradeoffs Methods Crashing – How to shorten activities – cost penalties Resource loading – amount of resource needed per period. Resource leveling or balancing – evening out resource use, reacting to limited resources Simulation programs can help level