Goals and Objectives FDOT Goals Improve transportation safety.
Reduce congestion and delays. Acquire (own) the most technically comprehensive ITS software. Establish a software standard at TMCs throughout the State of Florida. Reduce multiple TMC software development, maintenance, and update costs. SunGuide software goals: Flexible and expandable to match individual TMC needs. Respond to traffic incidents in a rapid, accurate, and effective manner. SunGuide Software: Status Update March 10, 2004
3
Project Web Site http://sunguide.datasys.swri.edu
SunGuide Software: Status Update March 10, 2004
4
SunGuideSM Software Architecture
Robust Extensible Flexible Scalable Configurable Proven SunGuide Software: Status Update March 10, 2004
5
Release-Oriented Development Approach
Release Release 2a Release 2b not in scope SunGuide Software: Status Update March 10, 2004
6
Scope of SunGuideSM Effort
Release 1: Core software framework: Database Process viewer Status logger User interface Map DMS subsystem, drivers for: NTCIP Florida MIB Mark IV version 2.5 CCTV subsystem, drivers for: NTCIP camera support IP-Video support (tentative) Video Wall Traffic Detection, driver for: RTMS (tentative) Microloops (tentative) Incident management subsystem Release 2a: Core software framework upgrade Center-to-Center FDOT Central office configuration Ramp metering DMS subsystem, drivers: Trailblazers (tentative) RWIS Archive data HAR Web server Emergency evacuation Release 2b: Inventory and maintenance SunGuide Software: Status Update March 10, 2004
7
Executive Handler SunGuide Software: Status Update March 10, 2004
8
Executive Handler - continued
SunGuide Software: Status Update March 10, 2004
9
Browser Based User Interface
SunGuide Software: Status Update March 10, 2004
10
Center-to-Center Infrastructure
SunGuide Software: Status Update March 10, 2004
11
High Level Schedule Software Releases
Release 1 – September 2004: District 4 Release 2a – August 2005: District 6 Release 2b – November 2005: Statewide Short-term deployments: District 4 Broward County RTMC District 6 Miami RTMC SunGuide Software: Status Update March 10, 2004
12
Schedule Status Current schedule is posted to project web site
Functional threads that can be demonstrated: Support processes (executive, logging) Data Bus GUI / Map DMS: Subsystem master process Mark IV NTCIP CCTV: PTZ control using SunGuide protocol driver TSS: Device simulators SunGuide Software: Status Update March 10, 2004
13
SwRI SunGuideSM Labs SunGuide Software: Status Update March 10, 2004
14
SwRI SunGuideSM Labs – con’t
SunGuide Software: Status Update March 10, 2004
15
Southwest Research Institute
Questions? Contact Information: Steve Dellenback (210) Southwest Research Institute P.O. Drawer 28510 San Antonio, Texas 78228 SunGuide Software: Status Update March 10, 2004
Similar presentations
© 2024 SlidePlayer.com. Inc.
All rights reserved.