Water Reclamation Plant Feasibility Study Update
Self introduction Introduce any board members in the audience Thank them for the opportunity to provide an update June 25, 2014 Water Reclamation Plant Feasibility Study Update
2
Initial Project Considerations
Permits/ Institutional Agreements Plant Location Plant Location Environmental Impacts/ Benefits Technical Feasibility Community Concerns & Input Project Feasibility?
3
Project Decision Update
May June July August September October Site Selection Required Infrastructure Potential Uses Treatment Requirements Potential Partnerships Complimentary/Secondary Uses Costs and Financing Draft Report/Summary Final Report Continuous Outreach
4
Focusing on Sterling Site
5
Infrastructure Requirements
6
Criteria for System Improvements
Available Flow Near-Term EDU Availability Maximizing Cost-Effectiveness Coordination with Other Infrastructure Treated Recycled Water Pipelines Potable Water System Improvements City Infrastructure Improvements
7
Plan for Potential Development
Complete immediate projects to increase system capacity Projects to be constructed in FY Project Type Length Cost Pedly Bypass 15 inch 3,600 ft $1.3 Million Warm Creek Crossing 24 inch 1,200 ft $700,000 Church St. Extension 600 ft $300,000
8
Project Decision Timeline
May June July August September October Site Selection Required Infrastructure Potential Uses Treatment Requirements Potential Partnerships Complimentary/Secondary Uses Costs and Financing Draft Report/Summary Final Report Continuous Outreach Next Special Meeting: Wednesday, July 23, 2014 7:00 pm
9
Questions?
10
Contact Us wwstudy@eastvalley. org eastvalley
Contact Us eastvalley.org/wwstudy | (909)