Background The Accounts and Audit Regulations 2003 place a legal requirement on the LA and Schools to close the accounts (we have to meet their deadline) Schools’ figures have to be added to KCC’s accounts earlier To ensure we could meet the deadline for we ran a pilot with 16 schools in PILOT – 16 schools volunteers Successful pilot last year
3
How did it go 2017 – 18? Deadlines UIFSM Bank Statements
Late or not received Deadlines - Only 10 schools missed the deadline Reached our consolidation deadline a day early UIFSM - Not so many queries Guidance on Kelsi Ledger code report sent in with year end accounts – helped us identify issues NOTE : UIFSM - Final figure should be: Statement of account at year end This year’s adjustment Affect of last year’s adjustment Bank statements – Siobhan met NAT West and agreed statements up to 18th to arrive by 21st Mar Online banking More regular statements
4
Positives Able to start preparing next year’s 3 Year Budget Plan sooner Able to take Easter holiday off! Ran pretty smoothly Not that different really Some of the feedback so far
5
Negatives OLD year open 26–29 March
Your concern – couldn’t work in FMS6 for these days Our concern – risk of further transactions in the OLD year after submission to SFS Salary Reports Not having time to make usual checks and reconciling within BPS No time to deal with payroll queries prior to submitting accounts OLD year open for 4 days Can work in the NEW year but we advise no bank reconciliation until AFTER submitting accounts Doing it BEFORE submission can cause a problem with the unpresented listing submitted to us Changes could be made after submission in error Not aware of any incidents …… as yet! Schools MUST match what we submit to the DfE If there are issues they have to be corrected in Schools accounts this year before year end We’ll pick them up with six month returns March salary - Can still be input in FMS6 as usual (cash book journal) as costs have come out of bank a/c Run usual payroll rec through BPS AFTER submission Contact payroll provider as usual with queries and raise YE adjustments if necessary (for over / underpayments etc.)
6
Closedown Deadline Date
Timings for this year Most important date Closedown Deadline Date Monday 25 March 2019 2 days later than last year More time for payroll reconciliation if necessary
7
more timings for this year…..
From 1 February 2019 Carry out FMS6 Health Check 1 March 2019 Edukent March Direct Debit notification 18 March 2019 Edukent second March DD notification ** TBC Receive March Statement of Account notification Statement of Account (March advances) Capital Matrix and YE Revenue Analysis forms on Kelsi 1 Feb - Health Check pack will be ed Sept 2018 Contact helpdesk if necessary We are looking at ways to improve / speed up this process develop an excel ‘tool’ for schools to use alongside pack 1 Mar – as usual 18 Mar - ** Edukent – second notification – TBC by Edukent nearer the time Advances will be in bank a/c’s on 20 March 2019 Cap Matrix etc. – we have to wait for March figures for lookup
8
Closedown deadline for 2019
still timings…….. 20 March 2019 Advances will be in bank 21 March 2019 Receive Bank Statements from NAT West 25 March 2019 Payday – may need to contact individual payroll providers earlier for reports Closedown deadline for 2019 20 March – about normal 21 Mar – Statements – hopefully! 25 March Payday - should have received payroll reports 21/22 March DEADLINE – Earlier If possible then that’s fine with us!
9
….and more…. 26 – 29 March 2019 FMS6 OLD year still open – cannot be closed until 1 April Ensure nobody processes items in the OLD year after submitting accounts to SFS 26 – 29 March OLD year open for four days Reminder !! Gap between submission and end of March Procedure for disabling passwords will be in closedown pack if necessary – as last year We will be able to contact schools prior to holidays!
10
a bit more... From 1 – 7 April 2019 Run a Preliminary Closure in FMS6 After checking the current figures match those submitted Can be done before receiving Oracle report from us FMS6 – continue as usual in the new year But – Final Closure cannot be run until AFTER Oracle Report has been received and checked Process March VAT as usual Prelim full details in closedown pack for checking FMS6 figures against those submitted Also details on how to check Oracle outturn report After running prelim Still need to make sure that nothing is input into the OLD year in period 13 until FINAL closure is run During this time we will still be able to contact schools prior to holidays!
11
and finally….. Easter Holiday 8 – 22 April 2019
(Good Friday 19 April 2019) No actual date for these next two! Sending you Oracle Outturn Report Then….Final Closure of 2018 – 19 Outturn Reports Not necessarily first come, first served. Depends on: Any issues / queries If we’ve been unable to contact schools with holidays etc. May receive report BEFORE easter Final closure after receipt of oracle report
12
FAQ – BACS / Cheque runs Q Invoices were processed before closedown but I hadn’t paid them, can I pay them after submission? A Yes – Inputting the invoices affects the final balance (surplus/deficit) so it doesn’t matter if they’re paid or not. You can process a payment run when the payments are due Timings will be included in the pack to ensure this runs smoothly But if necessary, yes you can process a payment run AFTER submission as it won’t affect rollover into NEW year! BANK and ZCC01 will change ZCC01 - is unpaid , processed invoices (no cheque has been raised in system)
13
Any feedback? All feedback welcome Contact us: 03000 415415
Pack Procedure notes Timing Training Support / Helpdesk Contact us: Took on board comments from the pilot schools last year From our own staff Will take everything into account for next year where possible