Team 5 Project Plan Review
Presented By: Nick White Charles Reyzer
2
Outline Team Responsibilities Scheduling Group Dynamics
February 1, 2005 AAE 451 – Team 5
3
Responsibilities Leadership Teams Nick White (CEO)
Charles Reyzer (CTO) Teams Aerodynamics Christian Naylor, Charles Reyzer Propulsion James Roesch, Maria Mullins Structures Ross May, Clay Stangle Dynamics & Control Trent Lobdell, Eamonn Needler February 1, 2005 AAE 451 – Team 5
4
Responsibilities Teams CAD/Industrial Design Budget Center of Gravity
Clay Stangle, Ross May, Christian Naylor Budget Maria Mullins Center of Gravity Eamonn Needler Class Note-Taker Clay Stangle Webpage Charles Reyzer February 1, 2005 AAE 451 – Team 5
5
Scheduling Presentations February 1, 2005 AAE 451 – Team 5 Name Time #
Nick 30 4 Charles 5 Christian 25 Ross Clay 3 Trent James Maria Eamonn February 1, 2005 AAE 451 – Team 5
6
Scheduling Estimated Budget Milestones 9015 Man-Hours
Project Planning (2/1) Airfoil Selection (2/8) Motor Selection (2/22) Design “Frozen” (2/24) Parts Ordered (3/10) Critical Design Review (CDR) (3/24) Begin Construction (3/24) Flight (4/19) Estimated Budget 9015 Man-Hours $450,750 Development Cost February 1, 2005 AAE 451 – Team 5
7
Scheduling Group Meetings Team Meetings
Weekly Meetings (Sundays 12:30) After Class (Tuesday/Thursday) Team Meetings Arranged by teams when needed February 1, 2005 AAE 451 – Team 5
8
Group Dynamics Monthly Lunches Code of Conduct Constructive Criticism
Communication with Leaders February 1, 2005 AAE 451 – Team 5