Leak Management Best Practices
Central Hudson Gas & Electric Corp. Leak Management Best Practices Roundtable October 15, 2014
2
Today’s Agenda Company Overview Leak Survey Program
Details Scheduling Data Transfer Leak Repair Program Leak Classification Central Hudson Practices Bonus Structure & Results Business Intelligence Summary
3
Company Overview Hudson Valley, NY 61,000 services 75,000 customers
174 miles transmission main 1,241 miles distribution main
4
Leak Survey- Details Work done by contractor 4 year contract
Contractor qualified to classify leaks Perform existing leak surveillances Bonuses awarded based on performance: Distribution survey completion deadline is Sept. 1 Leaks found
5
Leak Survey- Schedule Annually Business district mains & services
In 2012, revised leak survey frequency to: Annually Business district mains & services 50 miles of main 2,575 services Metallic mains & services not monitored & protected 230 miles of main 15,200 services Once every 5 years: Metallic mains and services protected against corrosion Plastic mains and services 961 miles of main 43,100 services Continuously during frost conditions: All cast iron mains 63 miles of main
6
Leak Survey- Data Transfer
New inspection software implemented (2012) GL Essentials Everything (mains, services, meter sets, leaks, etc.) electronically mapped & assigned
7
Leak Survey- Data Transfer (cont’d)
All inspections completed & submitted electronically More efficient scheduling More efficient surveying Completed work uploaded daily
8
Leak Survey – Field View
9
Leak Repair Program Leak Repair Program Leak Classification
Central Hudson Practices Bonus Structure & Results Business Intelligence
10
Leak Classification
11
Leak Repair- CH Practices
Target time for initial leak repair Type 2/2A within 30 days of discovery Type 3 within 6 months of discovery Above State Regulations Annually budget capital dollars for unidentified pipe replacements due to emergent leaks
12
Leak Repair- Details Combination of Internal & Contractor Crews
Contract Details Multiple contractors on property Balanced Risk Approach between the company and contractors T&M type contracts for leak repair vs. no payment unless leak closes Two attempts to close assigned leak before payment Daily upload of repair records- penalties for late/missing paperwork
13
Leak Repair Bonus Structure
Contract Details A 5% of contract leak cost bonus is awarded to a leak that a contractor fixes and closes on first attempt. Payable directly to crew members Implemented starting in 2013
14
Bonus Structure- Results
From company wide cost per closed leak repaired by contractors decreased by 10% During that same time period a 5% reduction in repair attempts per closed leak was realized The trend is continuing into cost per closed leak continues to decrease.
16
Leak Surveillance
17
Leak Repair- BI Software
Business intelligence software presents real- time leak data in an organized way
18
Leak Repair- BI Software
Dashboard displays data clearly
19
Leak Management- Summary
A well-managed leak survey program helps drive a successful leak repair program Real time data from field crews is critical Success incorporating bonus structure into contracts. Business Intelligence is very helpful to manage programs
20
Questions? Erica Rybinski Tom Palmer