1 VTrcks/Exis – Vaccine Tracking System Integration Implementation Phase
New Mexico Department of Health Immunization Program

2 DEFINITIONS: NMSIIS – the New Mexico Statewide Immunization Information System – the vaccine registry VTrckS – CDC’s system to help states and providers order and inventory vaccines. ExIS – External Information System – the interface that enables providers to upload inventory data and orders to the Immunization Program and the Program to download shipment information.

3 Current Reality – Providers inventory and orders to the Program which enters these manually into VTrckS – only 2 staff use it now. Future Vision – Providers Bring their own inventory into VTrckS using the interface, and upload their orders electronically. Program approves and forwards for filling.

4 Project Steering Committee
Jane Peacock, Division Director Terry Reusser, CIO Daniel Burke, Immunization Program Manager (Project Director) Jane Cotner, Infectious Disease Bureau Chief Paula Morgan, IT Staff Manger (Project Manager)

5 Work Plan Overview 1. VOMs technical set up and provider assessment
Three phase rollout to a completely paperless and automated system Automated process 1. VOMs technical set up and provider assessment 2. Provider Training & ExIS Validation 3. Single direction integration from NMSIIS system On going sustainment Phase 1 Implement VOMS in secure cloud-based environment Provider readiness assessment State administrator training and system configuration Train the Trainer Phase 2 CDC ExIS site validation Pilot Rollout Cohort 1 (ready with minimal intervention) Cohort 2 (additional intervention required to improve readiness) Phase 3 Full bi-directional integration into IIS System 11/15/2018

6 Project Budget Project Manager IV&V Project Management
Phase / Activity Associated Deliverables Estimated Budget Staff - Internal Project Manager Consulting Services IV&V Project Management Implementation Vendor(s) 33,705 90,000 Consulting Implementation management 193,314 Data Management 93,456 Training and Materials Development 49,392 Professional Training 283,838 Software VOMS Vaccine Ordering Module 60,000 TOTALS $803,705

7 Project Schedule

8 Conclusion Certification History Date DoIT Phase Amount
    Certification History Date DoIT Phase Amount Funding Source(s) (use specific citations to laws, grants, etc.) 9/25/2013 Approved Initiation and Planning $ 30,000 DOHIM1301 DOHIM1401 PPHF Grant # IH23IP Project ID: DOHIZSIIS1201 12/18/2013 Current Request Implementation $773,705 DOHIZPH1204