A Contractor and Supplier Workshop Schools Capital Improvement Program
YOU ARE CORDIALLY INVITED TO ATTEND A Contractor and Supplier Workshop for the Schools Capital Improvement Program Where: MLK Jr., Middle School Auditorium 1000 Mosby Street Richmond, VA Wednesday, August 22, 2018 From 5:00 P.M. To 7:00 P.M. Learn about new schools construction projects and the opportunities to participate. Information on projects, schedules and bid process will be shared. Space is limited so please RSVP to:
2
PROGRAM OVERVIEW Phase 1 Projects:
George Mason Elementary School (same site, 650 pupils) ESH Greene Elementary School (same site, 1,000 pupils) Elkhardt Thompson Middle School (Elkhardt site, 1,500 pupils) George Wythe High School (Same site, 2,000 students) Communities In Schools Approach LEED Silver for Schools Green Building / Sustainable Design / Energy Efficiency Design Phase Update Construction Phase Schedule
3
General Scopes of work for all projects
Structural steel Masonry Structural concrete Underground utilities Heavy site work Glazing (windows, curtain walls, storefront systems) Light gauge steel Dry wall Painting Electrical Low voltage Plumbing HVAC Landscape Flooring, resilient Flooring, carpet Acoustical ceilings Roofing Case work Doors
4
Elkhardt Thompson Middle School
1,500-pupil facility 19 Acres Approximately 200,000 sq. ft. new construction Existing Elkhardt Thompson MS will remain in full operation at Thompson MS site
5
Elkhardt Thompson Middle School AERIAL
6
George Mason Elementary School
650-pupil facility 8 Acres Approx. 100,000 sq. ft. of new construction Existing George Mason will remain in full operation Construction in 2 phases: Phase 1 - Site & Utility Construction Phase 2 - Building Construction/Demo Existing
7
George Mason Elementary School AERIAL
8
ESH Greene Elementary School
1,000-pupil facility 15 Acres Approximately 120,000 sq. ft. new construction Construction in 2 phases Phase 1 – Site & Utility Construction Phase 2 - Building Construction
9
ESH Greene Elementary School AERIAL
10
Elementary School Construction SCHEDULES
George Mason Elementary– Construction CMR RFQ issued 7/11/18 CMR RFP ad 9/3/18 CMR award 11/18 Groundbreaking 11/18 Complete construction 8/20 Students occupy 9/20 Complete demo/final site 4/21 ESH Greene Elementary – Construction CMR RFQ issued 7/11/18 CMR RFP ad 9/3/18 CMR award 11/18 Groundbreaking 11/18 Complete construction 8/20 Students occupy 9/20 Complete demo/fina site 4/21
11
Elkhardt Thompson Middle School Schedule
CMR RFQ 7/18 CMR RFP add 9/18 CMR award 10/18 Groundbreaking 10/18 Complete construction 8/20 Students occupy 9/20 Complete final site 11/20
12
George Wythe High School
2,000-pupil facility 28 Acres Approximately 270,000 sq. ft. new construction Construction in 3 phases Phase 1 – Site & Utility Construction Phase 2 - Building Construction Phase 3 – Demolition of existing school Phase 4 – Completion of site work
13
George Wythe High School Projected Schedule
Design RFQ – Winter 2018 Design RFP – Spring 2019 IFB RFQ Spring 2020 IFB - Summer 2020
14
DEPARTMENT OF PROCUREMENT SERVICES
RFQ Process RFP Process Pre-bid Meetings Sealed Bid/Bid Openings How to find New Solicitations ( Current Solicitations Posted How to be a “Responsive” Bidder
15
OFFICE OF MINORITY BUSINESS DEVELOPMENT
OMBD’s Registration: Website: Telephone: (804) Fax: (804) Certifications: 1. Commonwealth of Virginia’s Department of Minority Business Enterprise 2. Small Business Administration’s 8(a) Program 3. Virginia Department of Transportation’s DBE Program Business Information Update Website Workshops Technical Assistance Loan Program
16
QUESTION & ANSWER
17
PROGRAM COMMUNICATIONS
For information during procurement process: Contact Gary Hundley For information after procurement: Contact Michael McIntyre For MBE/ESB Information: Contact LaQuiana Bailey Communication Resources: City and RPS website