Team 11 Adam Fisher Presented by: Mitchell Quetant Nathan Hammond
2
Presentation Overview
Background Information Project Scope First Semester (Design) Second Semester (Manufacturing) Test maneuvers Problems Encountered Possible Improvements 11/15/2018 Team 11 Progress Report
3
Project Background CAPS is researching the development of fully electric ships Developing real time hardware-in-the-loop simulation capabilities for electric ship power systems Navy hopes to be able to create fully electric ships 11/15/2018 Team 11 Progress Report
4
Project Scope Build a display for classroom and tour demonstrations
Given budget of $3000 Will monitor current and voltage changes during dynamic maneuvers 11/15/2018 Team 11 Progress Report
5
First Semester Needs Assessment Engineering Specifications
Concept Generation -Initial Design - Final Design Cost Analysis 11/15/2018 Team 11 Progress Report
6
Needs Assessment 11/15/2018 Team 11 Progress Report
7
Engineering Specifications
11/15/2018 Team 11 Progress Report
8
Initial Design Not maneuverable Required too large of a pump Costly
11/15/2018 Team 11 Progress Report
9
Final Design More cost efficient Lighter and more maneuverable
11/15/2018 Team 11 Progress Report
10
Cost Analysis Projected materials costs were approximately $2300.
Though within the budget, still close to limit. 11/15/2018 Team 11 Progress Report
11
Second Semester Construction of Apparatus Project Components
Final Product 11/15/2018 Team 11 Progress Report
12
Construction of Apparatus
Took approximately two months to build Met with many delays 11/15/2018 Team 11 Progress Report
13
Project Components Tank Wooden Support Pump Motor Piping System
Motor and Drive System 11/15/2018 Team 11 Progress Report
14
Tank 8”x12”x30” Acrylic tank ¼ in wall thickness
Bound using Acrylic solvent 11/15/2018 Team 11 Progress Report
15
Wooden Support Constructed using 2”x4” wood pieces and 2 ½” wood screws 11/15/2018 Team 11 Progress Report
16
Pump Teel 4RJ94 11/2 HP Used for Pools and Spas
Requires 120 volt (typical wall plug) Pumps 160 GPM 8” to 4” Coupler 11/15/2018 Team 11 Progress Report
17
Piping System PVC Schedule 40 pipe and fixtures 4” to 2” Coupler
Valves are orientated strategically to throttle water 11/15/2018 Team 11 Progress Report
18
Motor and Drive System Uses a 12 V DC motor
Drives a 4” metal propeller Propeller weighs approx. ½ lb Supported by wood and aluminum 11/15/2018 Team 11 Progress Report
19
Final Product Eureka!!!! 11/15/2018 Team 11 Progress Report
20
Actual Cost Analysis 11/15/2018 Team 11 Progress Report
21
Test Maneuvers There are five maneuvers for the apparatus
Accelerating Ship Cruising Ship Coasting Ship Ship at Rough Seas 11/15/2018 Team 11 Progress Report
22
Accelerating Ship Cruising Ship Coasting Ship
Simulates the ship at start up Cruising Ship Similar to the accelerating ship maneuver, but adds use of the pump to simulate the ship already in motion Coasting Ship Simulates a ship moving in open water without use propulsion Currently cannot test 11/15/2018 Team 11 Progress Report
23
Ship at Rough Seas Two phases
With aid of the pump Without aid of the pump Simulates a boat in rough seas where the propeller will enter and exit the water 11/15/2018 Team 11 Progress Report
24
Crash-Astern Simulates the effects of going into full reverse while already traveling at full ahead Currently cannot test 11/15/2018 Team 11 Progress Report
25
Test Data 11/15/2018 Team 11 Progress Report
26
11/15/2018 Team 11 Progress Report
27
Problems Encountered Initially did not know everything to order through CAPS Wavered on what kind of pump to use Many unexpected delays in the ordering pipeline 11/15/2018 Team 11 Progress Report
28
Possible Improvements
Connect system to LABView Change to the drive motor Add an automated mechanical lifting system Add a flow meter Change ball valves 11/15/2018 Team 11 Progress Report
29
Acknowledgements Dr. Michael “Mischa” Streurer Anthony Gleaton
Keith Larson Thomas Anthony Cliff Loughmiller Website: 11/15/2018 Team 11 Progress Report
30
Questions? 11/15/2018 Team 11 Progress Report