Software Test Termination

Similar presentations


Presentation on theme: "Software Test Termination"— Presentation transcript:

1 Software Test Termination
1209

2 Testing is expensive

3 When do we terminate testing?

4 Finding all the bugs

5 Fault Seeding Seed (add) errors to code
Use standard techniques to identify errors Estimate total errors based on fraction of seeded errors found

6 Fault Seeding ST: total seeded faults SD: Seeded faults detected
NT: Total faults that were not seeded ND: Detected faults that were not seeded SD/ST = Fraction of seeded faults found ND/NT = Fraction of non-seeded faults found SD/ST = ND/NT

7 Example: We seed 20 faults in a system.
The testing group finds 38 faults, 8 of which were seeded. How many unseeded faults remain?

8 Problems with this approach

9 Software is good enough

10 Measures of Software Quality: Usability
Ship when product is usable enough based on customer usability studies

11 Measures of Software Quality: Reliability, Availability, Maintainability

12 Measures MTTF: Mean time to failure MTTR: Mean time to repair
MTBF: Mean time between failure MTBF = MTTF + MTTR Failure Failure System repaired Time TTF TTR TBF

13 Software Reliability Models
Statistical models of reliability Track the first N failures Look for a probability distribution that matches this data Example models include Basic execution time Logarithmic Poisson Execution Time

14 Failures, not faults Time Execution time (more accurate)
Calendar time (more useful)

15 Non-static failure behavior
Faults are repaired when the system fails The probability of failure changes over time

16 Developing models Track failures and execution time
Time to failure Time between failure Fit to statistical distribution Estimate distribution parameters Estimate reliability for some future time

17 Need to Ship: Factors Market-driven need (need to be first to market)
Business need Need to market product to generate revenue Lack of resources (money) to continue testing Cost/benefit analysis is positive Political factors

18 Retire the System “retirement” here may mean “terminate maintenance”


Download ppt "Software Test Termination"