Jeff Byler (AECOM) Shane Winner Wayne Swinehart
Shell Appalachia Project Safety Considerations Design & Planning Phases Jeff Byler (AECOM) Shane Winner Wayne Swinehart Projects and Technology 11/16/2018
2
Overview Safety Perspectives Front End – Planning/Engineering Efforts
Integrated Schedule Appalachia Web Site & Assessing Safe Route Proactive vs. Reactive Road Projects Partnering with PENNDOT/Townships/Competitors Engineering/Technical Contributions to Safe Projects Road Project Examples – Fuller 826 Road Upgrade Well Pad Examples – Pad sizing, Lease Roads Questions and Feedback? 11/16/2018
3
Safety Perspectives Shell Internal Staff and Operations
Contractors/Vendors Working for Shell General Public – Motorists and Landowners 11/16/2018
4
Appalachia Integrated Project Schedule
Snapshot of Fuller 826 Well Site activities: All groups working from same plan Avoid SIMOPS - concurrent work Provide reasonable time to complete De-clutter for safer work site Avoid/minimize Winter work 11/16/2018
5
Route Selection – Appalachia Road Users Site
Assess each site for safe/cost effective route – (rarely the shortest route) Avoid – posted bridges, school zones, urban areas, steep grades, and poor sight distance. Execute Permits and Bonding with PENNDOT/Townships Share and maintain site for all functional groups use Goal: Safety/Logistics and minimizing impacts to the community 11/16/2018
6
Benefits of Upgrade Vs. Repair – SR 2022
Typical Deterioration Typical Deterioration Larger investment but safer project Once and done strategy Avoid rework and high risk emergency repairs Full Reconstruction 11/16/2018
7
Partnering Project - Example
11/16/2018
8
Partnering project - Example
FOR IMMEDIATE RELEASE November 17, 2015 Route 144 to Re-open Today as Potter County Improvement Job Winds down for 2015 Galeton, PA – The Pennsylvania Department of Transportation is advising area drivers that a section of Route 144 between Pigeon Hill and Galeton will re-open today. This section of Route 144 has been closed since late September, as work continued to rehabilitate more than 50 miles of weight restricted roadway on Routes 44 and 144 in Potter County. With the re-opening of this section, PennDOT will lift the detour that made use of Routes 44 and 6. This two-year project was made possible through a partnership between PennDOT and industry partners Shell, Tenaska, and Dominion Transmission. 11/16/2018
9
Partnering projects yield safety Benefits
Combine Resources to build long term upgrade projects Share work zone traffic control – signage, message boards Public Awareness – Standard radio and press releases Add safety features otherwise not included – guiderail, reflectors/delineators, signage upgrades. Eliminates interim repairs during Drilling/Completions 11/16/2018
10
Engineering/Technical Contributions
Road Project Examples Fuller 826 Road Upgrade Existing Intersection Drainage/Stormwater Utilities Roadway Upgrade Sight Distance Turning Radius Design Well Pad Safety Examples Lease Roads Pad Size and layout Pad Surface Water Pad BMP Controls Road Projects – Road safety standards also apply to Well Pad lease roads 11/16/2018
11
Fuller 826 – Mistletoe Hill Road Upgrade
Existing Intersection Complex intersection Increase turning radius Steep grade (12-14%) Land acquisition Utility Lines Existing drives and side roads DOT/Township partnering 11/16/2018
12
Fuller 826 – Mistletoe Hill Road Upgrade
11/16/2018
13
Fuller 826 – Mistletoe Hill Road Upgrade
Drainage/Stormwater Eliminate drainage hazards Increase runoff capacity Extend pipes for widening 11/16/2018
14
Fuller 826 – Mistletoe Hill Road Upgrade
Relocation of aerial utility lines Utility Coordination Time Existing Gas Line Potholing 11/16/2018
15
Fuller 826 – Mistletoe Hill Road Upgrade
Roadway Upgrade Pavement vs Gravel HOP Coordination 11/16/2018
16
Fuller 826 – Mistletoe Hill Road Upgrade
Intersection Sight Distance Design Speed Drivers Eye Height (3.5 feet) 11/16/2018
17
Fuller 826 – Mistletoe Hill Road Upgrade
Intersection Sight Distance PennDot Table 11/16/2018
18
Fuller 826 – Mistletoe Hill Road Upgrade
Turning Radius Design WB-67 Truck Software Used 11/16/2018
19
Fuller 826 – Mistletoe Hill Road Upgrade
11/16/2018
20
WELL PAD safety examples
Lease Roads Sight Distance Grades 12% or less Turnouts every 500’ Road Widths Guide Rail Recoverable Slope PennDot Standards Road Projects – Road safety standards also apply to Well Pad lease roads 11/16/2018
21
WELL PAD safety examples
Pad Size and layout Road Projects – Road safety standards also apply to Well Pad lease roads 11/16/2018
22
WELL PAD safety examples
Pad Surface Soil Cement Cross Slope Safety Berm Water Pad Locate close to township/state road BMP Environmental Controls Are designed with a factor of safety Will aid in controlling/containing any leaks or spills on the well pad Road Projects – Road safety standards also apply to Well Pad lease roads 11/16/2018