1
StratoBuoy II Results Matt Voll Brian Mayernik Pat O’Hara
2
Mission Recap Tested development hardware and software for the power system of the SpaceBuoy nanosat project Simulated loads (for current/voltage sensing) Telemetry recorded using IIC interface
3
Pre-flight Modifications
Analog-to-Digital converter failed at some point in final testing. The A-to-D is a critical part of recording telemetry data, so a crucial part of our SHOT II payload Last minute problems with our 12V - 5V DC converter supply for our CDH board (overheating)
4
Solutions
5
Results Approximately 2 hours of telemetry data logged, at 1 sample/sec Less than flight time. What happened? Batteries still supplying power at recovery Possible causes: Faulty connection caused power loss at balloon separation/burst (large ∆v) Low temps affected exposed power lines (ice build- up) Still plenty of data to work with
6
Results Continued…
7
3.3V Reg Voltage vs. Time (s)
* Needs adjustment
9
* Needs adjustment
11
* Needs adjustment
13
* Needs adjustment
14
Lessons Learned Don’t leave things for the last minute
However, always be prepared for things to go wrong at the last minute
15